26.—(1) The heat generated by a plant must be individually metered.
(2) But the heat generated by two or more plants may be metered using one meter provided that—
(a)the plants use the same source of energy and technology;
(b)the plants will, once given accreditation, be eligible to receive the same tariff;
(c)the plants will then share the same tariff start date and tariff end date; and
(d)it is the Authority's opinion that a single meter is capable of metering the heat generated by all of those plants.