The A19/A184 Testo's Junction Alteration Development Consent Order 2018

Modification of Part 1 of the 1965 ActE+W+S

25.—(1) Part 1 of the 1965 Act, as applied to this Order by section 125 M1 (application of compulsory acquisition provisions) of the 2008 Act is modified as follows.

(2) In section 4A(1) M2 (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to the High Court in respect of compulsory purchase order), the three year period mentioned in section 4” substitute “ section 118 M3 (legal challenges relating to applications for orders granting development consent) of the Planning Act 2008, the five year period mentioned in article 22 (time limit for exercise of authority to acquire land compulsorily) of the A19/A184 Testo's Junction Alteration Development Consent Order 2018 M4.

(3) In section 11A M5 (powers of entry: further notice of entry)—

(a)in subsection (1)(a), after “land” insert “ under that provision ”;

(b)in subsection (2), after “land” insert “ under that provision ”.

(4) In section 22(2) (expiry of time limit for exercise of compulsory purchase power not to affect acquisition of interests omitted from purchase), for “section 4 of this Act” substitute “ article 22 (time limit for exercise of authority to acquire land compulsorily) of the A19/A184 Testo's Junction Alteration Development Consent Order 2018 ”.

(5) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—

(a)for paragraphs 1(2) and 14(2) substitute—

(2) But see article 27(3) (acquisition of subsoil or airspace only) of the A19/A184 Testo's Junction Alteration Development Consent Order 2018, which excludes the acquisition of subsoil or airspace only from this Schedule.; and

(b)after paragraph 29, insert—

PART 4 E+W+SINTERPRETATION

30.  In this Schedule, references to entering on and taking possession of land do not include doing so under articles 18 (protective work to buildings), 29 (temporary use of land for carrying out the authorised development) or 30 (temporary use of land for maintaining the authorised development) of the A19/A184 Testo's Junction Alteration Development Consent Order 2018..

Marginal Citations

M1Section 125 was amended by section 190 of, and paragraph 17 of Schedule 16 to, the Housing and Planning Act 2016 (c. 22).

M2Section 4A(1) was inserted by section 202(1) of the Housing and Planning Act 2016.

M3Section 118 was amended by paragraphs 1 and 59 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20) and section 92(4) of the Criminal Justice and Courts Act 2015 (c. 2).

M5Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016.