5.—(1) No part of the authorised development may be commenced until written details of the following for that part have been submitted to and approved by the relevant planning authority—
(a)the siting, design, external appearance, dimensions and floor levels of all permanent buildings and structures;
(b)the colour, materials and surface finishes of all permanent buildings and structures;
(c)the durability of all cladding materials; and
(d)the consideration given to the inclusion of the climate change mitigation measures referred to in table 13-1 of the environmental statement and the measures that have been included.
(2) The details to be submitted for approval under sub-paragraph (1) must—
(a)be in accordance with the design and access statement; and
(b)include appropriately scaled plans and sectional drawings.
(3) The authorised development must be carried out in accordance with the approved plans and any other approvals given by the relevant planning authority pursuant to this requirement.
(4) The authorised development must be carried out in accordance with the parameters specified in Table 1 below and the works plans (as the same may be amended by approval of the relevant planning authority pursuant to requirement 17).
Work No. | Building or structure | Maximum length (metres) | Maximum width (metres) | Minimum height (metres above site level unless otherwise stated) | Maximum height (metres above site level unless otherwise stated) |
---|---|---|---|---|---|
1(a) | Local equipment room and control | 23.1 | 13.75 | - | 9.9 |
1(b) | Generator | 5.5 | 4.4 | - | 6.6 |
1(c) | Gas turbine | 16.5 | 8.8 | - | 14.5 |
1(d) | Heat recovery steam generator | 30.8 | 16.5 | - | 35.2 |
1(e) | Heat recovery steam generator stack | - | 4 diameter | 79m AOD | 82m AOD |
1(f) | Turbine hall | 25.3 | 19.8 | - | 16.5 |
1(g) | CHP pipe bridge | 40.7 | 4.4 | - | 12 |
1(h) | Dump condenser | 16.5 | 13.2 | - | 8.8 |
1(i) | Fin fan cooler | 11.55 | 7.15 | - | 7.7 |
1(j) | Package boiler stack | - | 0.8 diameter | 44m AOD | 44m AOD |
1(k) – 1(w) | All other plant items | - | - | - | 7.5 |
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys