Explanatory Note
(This note is not part of the Order)
This Order authorises SP Manweb PLC (referred to in this Order as the undertaker) to install and keep installed, use and maintain, a 132kV underground cable, 1.2 km in length and a 132kV electric line above ground, 21.3 km in length in Shropshire and to undertake lower voltage line diversions and works to the Oswestry and Wem substations. The Order permits the undertaker to acquire, compulsorily or by agreement, rights in land and to use land for this purpose.
A copy of the land plans and the works plans and the book of reference mentioned in this Order and certified in accordance with article 35 (certification of plans etc.) and Schedule 9 (documents to be certified) of this Order may be inspected free of charge during working hours at Wem Library, High Street, Wem SY4 5AA