Soil survey and mitigation plan

15.—(1) No part of the authorised development is to commence until an agricultural land classification and soil survey has been undertaken and a soil mitigation plan has been prepared and has been submitted and approved in writing by the Secretary of State following consultation with Natural England.

(2) The undertaker must implement the soil mitigation plan prepared under sub-paragraph (1) during construction of the authorised development.