Point in time view as at 10/03/2021.
Changes to legislation:
There are currently no known outstanding effects for the The Riverside Energy Park Order 2020, Section 22.
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Compulsory acquisition of landE+W
22.—(1) The undertaker may acquire compulsorily so much of the Order land as is required for the authorised development or to facilitate it, or as is incidental to it.
(2) This article is subject to article 24, article 25 (acquisition of subsoil only) and [article 31].
Textual Amendments
Commencement Information