The Riverside Energy Park Order 2020

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

 Help about opening options

Dewisiadau AgorExpand opening options

Changes to legislation:

There are currently no known outstanding effects for the The Riverside Energy Park Order 2020, Section 23. Help about Changes to Legislation

Time limit for exercise of authority to acquire land compulsorilyE+W

23.—(1) After the end of the period of five years beginning on the day on which this Order comes into force—

(a)no notice to treat may be served under Part 1 (compulsory purchase under Acquisition of Land Act of 1946) of the 1965 Act; and

(b)no declaration may be executed under section 4 (execution of declaration) of the 1981 Act as applied by article 28 (application of the 1981 Act).

(2) The authority conferred by article 31 [F1(temporary use of land for carrying out the authorised development)] must cease at the end of the period referred to in paragraph (1), save that nothing in this paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land was entered and possession was taken before the end of that period.

Textual Amendments

Commencement Information

I1Art. 23 in force at 1.5.2020, see art. 1

Yn ôl i’r brig

Options/Help

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?