Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
4.—(1) Subject to the provisions of this Order, including the requirements in Schedule 2 (requirements), the undertaker is granted development consent for the authorised development to be carried out within the Order limits.
(2) Any enactment applying to land within, adjoining, or sharing a common boundary with the Order limits has effect subject to the provisions of this Order.
Commencement Information
I1Art. 4 in force at 21.5.2020, see art. 1
5.—(1) Subject to the following provisions of this article, the undertaker must construct the authorised development within the Order limits.
(2) In constructing and maintaining the non-linear works comprised in the authorised development, the undertaker may deviate laterally within the limits of deviation for those works shown on the works plans.
(3) In constructing or maintaining the linear works comprised in the authorised development—
(a)in the case of linear works for which limits of deviation are shown on the works plans, the undertaker may deviate laterally from the lines or situations shown on those plans to the extent of the limits of deviation; and
(b)in the case of linear works for which limits of deviation are not shown on the works plans, the undertaker may deviate laterally from the lines or situations shown on those plans to the extent of the Order limits.
(4) In constructing and maintaining the part of the new bridge comprising Work No.1D, the undertaker—
(a)must not, unless otherwise agreed with the harbour authority, construct any tidal work within the part of Lake Lothing which is located between the two areas identified in paragraph (5); and
(b)must safeguard the width of the navigable channel within Lake Lothing by preserving a distance of no less than 32 metres between the outer edge of the fenders referred to in each of paragraphs (5)(a) and (5)(b).
(5) The two areas referred to in paragraph (4) are—
(a)in relation to the pier located to the south of the north quay of Lowestoft Harbour, the area between the north quay wall and the outer edge of the fenders surrounding that pier; and
(b)in relation to the pier located to the north of the south quay of Lowestoft Harbour, the area between the south quay wall and the outer edge of the fenders surrounding that pier.
(6) In constructing and maintaining the authorised development, the undertaker may deviate vertically from the levels shown on the engineering section drawings and plans—
(a)to any extent upwards as the undertaker considers to be necessary or convenient but not exceeding 0.5 metres or, in relation to the parts of the authorised development referred to in column (1) of the table below, not exceeding the limit for each such part set out in the corresponding entry in column (2) of that table; and
(b)subject to paragraph (7), to any extent downwards as the undertaker considers to be necessary or convenient, except in relation to the parts of the authorised development referred to in column (1) of the table below, where the extent of permitted downwards deviation for each such part is set out in the corresponding entry in column (3) of that table.
(1) Numbered Work | (2) Upwards vertical limit of deviation | (3) Downwards vertical limit of deviation |
---|---|---|
Work No. 1A | 1 metre | 1.5 metres |
Work No. 1B | 1 metre | 2.3 metres |
Work No. 1C | 1 metre | 4 metres |
Work No. 1D | 1 metre | 2.5 metres |
Work No. 1E | 1 metre | 1.1 metres |
Work No. 5 | 1.5 metres | - |
Work No. 6 | 5 metres | 2.5 metres |
(7) Paragraph (6)(b)—
(a)does not prevent the undertaker, in constructing the piles comprising part of each of Work Nos. 1B, 1C, 1D and 1E, from deviating to any extent downwards as the undertaker considers to be necessary or convenient;
(b)does not permit the undertaker in constructing the bridge deck between piers within Lake Lothing, comprising part of Work No. 1D, to deviate downwards to a level which is less than 12 metres above Highest Astronomical Tide;
(c)does not prevent the undertaker, in constructing the lifting elements of the superstructure of the new bridge, comprising part of Work No. 1D, from deviating by up to 2.5 metres above the levels shown on the engineering section drawings and plans (mainline long section sheet 2 of 2), and to any extent downwards as the undertaker considers to be necessary or convenient; and
(d)does not permit the undertaker in constructing the bridge deck comprising part of Work No. 1B, to deviate downwards to a level which provides less than 4.9 metres headroom above the running rail of the railway.
(8) The undertaker must not undertake any capital dredge to a depth lower than—
(a)6.4m below chart datum in respect of works in Lake Lothing except Work No.7; and
(b)3m below chart datum in respect of Work No.7,
unless the undertaker has demonstrated to the MMO and the MMO has agreed in writing that dredging to a depth lower than those set out in sub-paragraphs (a) and (b) would not give rise to any materially new or materially different environmental effects than those assessed in the environmental statement.
(9) Without limitation on the scope of paragraphs (2) to (7) in constructing or maintaining the authorised development the undertaker may—
(a)deviate by up to 3 metres from the points of commencement and termination of any of the linear works, except in the case of the coterminous point of termination and commencement of Work Nos 1A and 1B, from which the undertaker may deviate by up to 10 metres in a north-easterly direction following the centreline of Work No. 1A, and by up to 3 metres in a south-westerly direction following the centreline of Work No. 1B; and
(b)deviate from the design of the new bridge or bridge structure shown on the engineering section drawings and plans, provided that any such deviation is in accordance with the final version of the design guidance manual approved under paragraph 3(2) of Schedule 2.
(10) In this article, references to—
(a)“linear works” are references to any works shown on the works plans by way of centre lines; and
(b)“non-linear works” are references to any other works shown on the works plans.
Commencement Information
I2Art. 5 in force at 21.5.2020, see art. 1
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys