Within the area of land described on the works plans as Works No. 9b—
(a)the removal and replacement of the existing 132kv tower with a new terminal tower;
(b)restringing to the new terminal tower;
(c)installation of underground cabling to connect into the underground cabling in Works No. 6; and
(d)a temporary access and set down and assembly area for the demolition of existing tower and construction of new tower to include a temporary office and welfare facility.