The M42 Junction 6 Development Consent Order 2020

Limits of deviationE+W

6.—(1) In carrying out the authorised development the undertaker may, so far as the undertaker considers it necessary or convenient—

(a)deviate laterally from the lines or situations of the authorised development shown on the works plans to the extent of the limits of deviation shown on those plans;

(b)deviate vertically from the levels of the authorised development shown on the engineering drawings and sections—

(i)in respect of the construction of a new Solihull Road Overbridge referred to in Work No. 3, to a maximum of 1.5 metres upwards or downwards; and

(ii)in respect of any other work comprised in the authorised development, to a maximum of 0.5 metres upwards or downwards.

(2) The maximum limits of deviation set out in paragraph (1) do not apply where it is demonstrated by the undertaker to the Secretary of State’s satisfaction and the Secretary of State, following consultation with the relevant planning authority, certifies accordingly that a deviation in excess of these limits would not give rise to any materially new or materially different environmental effects from those reported in the environmental statement.