E+W+S
and in connection with the construction of any of those works, and to the extent that they do not otherwise form part of any such work, and whether or not shown on the plans referred to in the requirements further development within the order limits consisting of—
(a)the provision of up to two construction compounds and two working compounds in the areas shown on the works plans;
(b)alteration of the layout of any street permanently or temporarily, including but not limited to realignment of carriageways and increasing the width of the carriageway of the street by reducing the width of any kerb, footpath, footway, cycle track or verge within the street; altering the level or increasing the width of any such kerb, footway, cycle track or verge; and reducing the width of the carriageway of the street;
(c)ramps, means of access, footpaths, bridleways, cycle tracks, embankments, aprons, abutments, shafts, foundations, retaining walls, wing walls, bunds, embankment swales, fencing, boundary treatments and highway lighting and culverts;
(d)street works including breaking up or opening a street, or any sewer, drain or tunnel under it, tunnelling or boring under a street, work to place or maintain apparatus in a street, works to alter the position of apparatus, including mains, sewers, drains and cables;
(e)the provision of thin surface course and carriageway markings;
(f)temporary and permanent diversion of utilities apparatus, including gas and water pipelines and electric and telecommunication cables;
(g)earthworks, including the extension of earthworks;
(h)retaining structures;
(i)barriers, including safety barriers;
(j)fencing;
(k)refurbishment works to any existing bridge or gantry;
(l)works to alter the course of, or otherwise interfere with a watercourse, including without limitation works to the River Team including temporary culverting;
(m)landscaping, noise barriers, works associated with the provision of ecological mitigation and other works to mitigate any adverse effects of the construction, maintenance or operation of the authorised development;
(n)works for the benefit or protection of land affected by the authorised development;
(o)works to place, alter, remove or maintain road furniture;
(p)signage and road marking;
(q)site preparation works, site clearance (including fencing, vegetation removal, demolition of existing structures and the creation of alternative footpaths); earthworks (including soils stripping, storage, and site levelling);
(r)the felling of trees and hedgerows;
(s)the establishment of site construction compounds, storage areas, temporary vehicle parking, construction fencing, perimeter enclosure, security fencing, construction related buildings, welfare facilities, construction lighting, haulage roads and other machinery apparatus, works and conveniences;
(t)the provision of other works including pavements works, kerbing and paved areas works, signing, signals gantries, road markings, traffic management measures including temporary roads and such other works as are associated with the construction of the authorised development;
(u)the provision of drainage works including attenuation ponds, outfalls, ditches, culverts; and
(v)such other works, working sites storage areas, works of demolition or works of whatever nature as may be necessary or expedient for the purposes of, or for purposes associated with or ancillary to, the construction, operation or maintenance of the authorised development which do not give rise to any materially new or materially different environment effects in comparison with those reported in the environmental statement.
Commencement Information
I1Sch. 1 in force at 9.2.2021, see art. 1