Chwilio Deddfwriaeth

The A1 Birtley to Coal House Development Consent Order 2021

Status:

Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol).

Article 26

SCHEDULE 6LAND IN RESPECT OF WHICH ONLY NEW RIGHTS ETC. MAY BE ACQUIRED

(1)

Plot Reference Number shown on Land Plan

(2)

Purpose for which rights over land may be acquired

(3)

Relevant part of the authorised development

Land Plans – Sheet 2
2/2Construction of retaining wall, new/relocation of existing ADS signs, upgrading of road lighting (including rights for access and maintenance).Work Nos. 1a and 3a
Land Plans – Sheet 3
3/1Construction of retaining wall, new/relocation of existing ADS signs, upgrading of road lighting (including rights for access and maintenance).Work Nos. 1a and 3a
3/3eRequired for works within and around junction 67 (Coal House) Roundabout including works to River Team. Required for access to construct and maintain works to junction 67 (Coal House) northbound on slip road. Rights to construct and retain grouting works under land and maintenance.Work Nos. 1b and 3d
3/3fRequired for works within and around junction 67 (Coal House) Roundabout including works to River Team. Required for access to construct and maintain works to junction 67 (Coal House) northbound on slip road. Rights to construct and retain grouting works under land.Work Nos. 2 and 3d
3/3g

New right to widen the existing Kingsway Viaduct and operate, access and maintain the structure (including the airspace underneath and extending up to 15m either side) and for grouting works on the land underneath the proposed new

structure.

Work Nos. 2 and 3d
3/3h

New right to widen the existing Kingsway Viaduct and operate, access and maintain the structure (including the airspace underneath and extending up

to 15m either side) and for grouting works on the land underneath the proposed new structure.

Work Nos. 2 and 3a
3/3iNew right to widen the existing Kingsway Viaduct and operate, access and maintain the structure (including the airspace underneath and extending up to 15m either side). Rights to construct and retain grouting works under land.Work Nos. 2 and 3a
3/3zNew right to widen the existing Kingsway Viaduct and operate, access and maintain the structure (including the airspace underneath and extending up to 15m either side). Grouting works under land.Work Nos. 2, 3c and 3d
3/3ddRequired for works within and around junction 67 (Coal House) Roundabout including works to River Team. Required for access to construct works to junction 67 (Coal House) northbound off slip road. Grouting works under land.Work Nos. 1b, 2, 3c and 3d
3/3ff

Required for works within and around junction 67 (Coal House) Roundabout including works to River Team.

Required for access to construct works to junction 67 (Coal House) northbound off slip road. Grouting works under land.

Work Nos. 2 and 3c
3/3ggRequired for works within and around junction 67 (Coal House) Roundabout including works to River Team. Rights to construct and retain grouting works under land.Work Nos. 2 and 3b
3/3hh

New right to widen the existing Kingsway Viaduct and operate, access and maintain the structure (including the airspace underneath and extending up to 15m either side) and for grouting works on the land

underneath the proposed new structure.

Work Nos. 2 and 3b
3/3llNew right to construct, operate, access and maintain a private maintenance access road on land adjacent to Lamesley Road and extending to land adjacent to south side of the proposed Allerdene Bridge and the East Coast Main Line for the benefit of Network Rail, Highways England and Northern Gas Networks Ltd.Work No. 11
3/3mmRequired for diversion of existing Northern Gas Networks pipelines. Required for access to construct works to junction 67 (Coal House) northbound off slip road. Grouting works under land.Work Nos. 3c, 13 and 14
3/3pp, 3/3qq, 3/3ttRequired for works within and around junction 67 (Coal House) Roundabout including works to River Team. Rights to construct and retain grouting works under land.Work Nos. 1a and 3b
3/3wwRequired to access and carry out the demolition of the existing Allerdene Bridge, the construction of the replacement Allerdene Bridge and associated Overhead Line Equipment, and for installation and retention of grouting works on the land underneath the proposed new structure.Work Nos. 5a, 5b and 23
3/3yyNew right to demolish the existing Allerdene Bridge and construct, operate, access and maintain a replacement offline Allerdene Bridge structure.Work Nos. 5a, 5b and 21
3/3aaaRequired for proposed Northumbrian Water pipeline diversion. Rights to construct and retain grouting works under land.Work Nos. 4b, 5a, and 22
3/3hhhNew right to access, operate, make alterations to and maintain the existing drainage outlet pipeline.Work No. 6a
3/3kkkRequired for access and to construct proposed highway and associated embankment. Rights to construct and retain grouting works under land.Work Nos. 6a and 7a
3/3lllNew right to access, operate, make alterations to and maintain the existing drainage outlet pipeline. Rights to construct and retain grouting works under land.Work Nos. 6a and 7a
3/3nnnRequired for access and to construct proposed highway and associated embankment. Required to alter existing drainage outlets. Rights to construct and retain grouting works under land.Work Nos. 6a and 7a
3/4a, 3/4b

New right to widen the existing Kingsway Viaduct and operate, access and maintain the structure (including the airspace underneath and extending up to 15m either side) and for grouting works on the land underneath the proposed new

structure.

Work Nos. 1a, 1b and 2
3/4qRequired to access, maintain and alter existing drainage outlet and ditch and to access the main highway works. Rights to construct and retain grouting works under land.Work No. 6b
3/6bNew right to construct, operate, access and maintain a private maintenance access road on land adjacent to Lamesley Road and extending to land adjacent to south side of the proposed Allerdene Bridge and the East Coast Main Line for the benefit of Network Rail, Highways England and Northern Gas Networks Ltd.Work No. 11
3/6dRequired for diversion of existing Northern Gas Networks pipelines. Required for access to construct works to junction 67 (Coal House) northbound off slip road. Grouting works under land.Work Nos. 9, 13, 14 and 15
3/6fRequired for diversion of existing Northern Gas Networks pipelines and construction of associated gas transfer station building adjacent to northbound carriageway. Rights to construct and retain grouting works under land.Work Nos. 10, 14 and 15
3/6kRequired for construction compound. Rights to construct and retain grouting works under land.N/A
3/6lNew right to access and maintain Allerdene culvert and drainage ditch.Work No. 20
3/10dNew right to demolish the existing Allerdene Bridge and construct, operate, access and maintain a replacement offline Allerdene Bridge structure and for installation and retention of grouting works on the land.Work Nos. 5a, 5b and 23
3/10g, 3/12d, 3/12f

New right to construct, operate, access and maintain a replacement offline Allerdene Bridge structure and for grouting works on the land underneath the proposed new

structure.

Work No. 5a
3/10e, 3/10f, 3/12c, 3/12eNew right to operate, access and maintain a replacement offline Allerdene Bridge structure and for installation and retention of grouting works on the land.Work No. 5a
3/10hNew right to construct, operate, access and maintain a replacement offline Allerdene Bridge structure, associated Overhead Line Equipment and for installation and retentions of grouting works on the land.Work Nos. 4a, 4b, 5a, 5b and 23
3/12bRequired to access and carry out the demolition of the existing Allerdene Bridge, the construction of the replacement Allerdene Bridge and associated Overhead Line Equipment, and for installation and retention of grouting works on the land.Work Nos. 4a, 4b, 5a, 5b and 23
Land Plans – Sheet 4
4/2dNew right to extend the Longbank Bridleway Underpass and operate, access and maintain the structure and associated equipment. Grouting works under land.Work Nos. 6a and 19
4/3bRequired for utility diversions and associated works within junction 66 (Eighton Lodge) Roundabout. Rights to construct and retain grouting works under land.Work No. 6a
4/3q, 4/4bRequired for the construction compound at junction 66 (Eighton Lodge) and associated access. Rights to construct and retain grouting works under land.N/A
4/6bRequired to construct the extension of Longbank Bridleway Underpass, including temporary working space and diversions for pedestrians during the Underpass closure. Rights to construct and retain grouting works under land.Work Nos. 6a and 19
4/7b, 4/7eRequired to carry out the demolition and construction of the replacement North Dene Footbridge and for temporary diversion of pedestrians during closure of the Footbridge. Rights to construct and retain grouting works under land.Work No. 18
4/7fNew right to access, operate, make alterations to and maintain the existing drainage outlet pipeline. Grouting works under land.Work Nos. 6a and 19
4/9b, 4/10New right to access, operate, make alterations to and maintain the existing drainage outlet pipeline.Work No. 6b
4/12b, 4/13b, 4/13dRequired to carry out the demolition and construction of the replacement North Dene Footbridge and for temporary diversion of pedestrians during closure of the Footbridge. Rights to construct and retain grouting works under land.Work No. 18
4/14bRequired to carry out the demolition and construction of the replacement North Dene Footbridge and rights to construct and retain grouting works under land.Work No. 18
Land Plans – Sheet 5
5/3b, 5/4b, 5/4dRequired for access and construction of main highway works and junction 65 (Birtley) off slip. Rights to construct and retain grouting works under land.Work Nos. 6a and 8a
5/5aRequired to construct the proposed highway works and associated access. Rights to construct and retain grouting works under land.Work No. 8a
5/6, 5/7, 5/8, 5/9, 5/11Required for construction of junction 65 (Birtley) southbound off slip road works and temporary footpath diversion. Rights to construct and retain grouting works under land.Work No. 8a

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill