Print Options
PrintThe Whole
Instrument
PrintThe Whole
Part
PrintThis
Section
only
Changes over time for: Section 33
Llinell Amser Newidiadau
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 29/12/2022.
Changes to legislation:
There are currently no known outstanding effects for the The Keadby 3 (Carbon Capture Equipped Gas Fired Generating Station) Order 2022, Section 33.
Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Felling or lopping of trees and removal of hedgerowsE+W+S
33.—(1) The undertaker may fell or lop any tree or shrub adjoining the authorised development or cut back its roots, if it reasonably believes it to be necessary to do so, to prevent the tree or shrub from obstructing or interfering with the passage of abnormal indivisible load vehicles to the extent necessary for the purposes of construction of the authorised development.
(2) In carrying out any activity authorised by paragraph (1) the undertaker must do no unnecessary damage to any tree or shrub and must pay compensation to any person for any loss or damage arising from such activity.
(3) Any dispute as to a person’s entitlement to compensation under paragraph (2), or as to the amount of compensation, is to be determined under Part 1 of the 1961 Act.
(4) The undertaker may, for the purposes of the authorised development subject to paragraph (2) remove any hedgerows within the Order limits that may be required for the purposes of carrying out the authorised development.
(5) The undertaker may not pursuant to paragraph (1) or (4) fell or lop a tree or remove hedgerows within the extent of the publicly maintainable highway without the prior consent of the highway authority.
(6) In this article “hedgerow” has the same meaning as in the Hedgerows Regulations 1997().