The East Anglia ONE North Offshore Wind Farm Order 2022

Acquisition of landE+W+S

6.  Regardless of any provision in the Order or anything shown on the land plan or contained in the book of reference to the Order, the undertaker must not acquire any interest in land or any apparatus or override any easement or other interest of the statutory undertaker otherwise than by agreement, such agreement not to be unreasonably withheld or delayed.

Commencement Information

I1Sch. 10 Pt. 5 para. 6 in force at 22.4.2022, see art. 1(2)