The East Anglia ONE North Offshore Wind Farm Order 2022

Interaction at Sizewell GapE+W+S

3.—(1) The undertaker shall consult with EDF Energy in the preparation of the Sizewell Gap construction method statement prior to submission of the Sizewell Gap construction method statement to the relevant planning authority for approval in accordance with requirement 22.

(2) The undertaker shall consult with EDF Energy in the preparation of—

(a)the access management plan, to the extent that it relates to Work Nos. 10, 11 or 15; and

(b)the construction traffic management plan, to the extent that it relates to Work Nos. 10 or 15,

prior to the submission of each plan to the relevant highway authority for approval in accordance with requirements 16 and 28 respectively.

(3) Prior to carrying out any of Work Nos. 10, 11 and or 15, the undertaker shall carry out surveys to establish the location of all utility apparatus within these areas which has the potential to provide services to EDF Energy.

(4) In the event of any damage to any utility apparatus which provides services to EDF Energy within the area of Work Nos. 10, 11 and 15, the undertaker shall immediately inform EDF Energy and shall use best endeavours to secure the repair of any damage within 24 hours.

Commencement Information