The Little Crow Solar Park Order 2022

Statutory Instruments

2022 No. 436

Infrastructure Planning

The Little Crow Solar Park Order 2022

Made

5th April 2022

Coming into force

27th April 2022

An application has been made to the Secretary of State under section 37 of the Planning Act 2008(1) (“the 2008 Act”) in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedure) Regulations 2009(2) for an Order granting development consent.

The application was examined by a single appointed person (appointed by the Secretary of State) pursuant to Chapter 3 of Part 6 of the 2008 Act and carried out in accordance with Chapter 4 of Part 6 of the 2008 Act and the Infrastructure Planning (Examination Procedure) Rules 2010(3).

The single appointed person having considered the representations made and not withdrawn and the application together with the accompanying documents, in accordance with section 83 of the 2008 Act, has submitted a report and recommendation to the Secretary of State.

The Secretary of State, having considered the representations made and not withdrawn, and the recommendations and report of the single appointed person, and taken into account the environmental information in accordance with regulation 4 of the Infrastructure Planning (Environmental Impact Assessment) Regulations 2017(4) has decided to make an Order granting development consent for the development described in the application with modifications which in the opinion of the Secretary of State do not make any substantial changes to the proposals comprised in the application.

The Secretary of State, in exercise of the powers conferred by sections 114, 115 and 120 of the 2008 Act, makes the following Order—

(1)

2008 c. 29. Parts 1 to 7 were amended by Chapter 6 of Part 6 of and Schedule 13 to the Localism Act 2011 (c. 20).

(3)

S.I. 2010/103, amended by S.I. 2012/635.