Chwilio Deddfwriaeth

The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022

Changes over time for: SCHEDULE 7

 Help about opening options

Version Superseded: 19/01/2023

Alternative versions:

Status:

Point in time view as at 02/06/2022.

Changes to legislation:

There are currently no known outstanding effects for the The M25 Junction 10/A3 Wisley Interchange Development Consent Order 2022, SCHEDULE 7. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Article 32

SCHEDULE 7E+WLAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN

Commencement Information

I1Sch. 7 in force at 2.6.2022, see art. 1

(1)

Plot Reference Number shown on Land Plans

(2)

Purpose for which temporary possession may be taken

(3)

Relevant part of the authorised development

Land Plans – Sheet 1
1/6The main site compound to include, but not limited to, site offices, welfare facilities, parking provisions, storage of plant and materials.All works
1/14Required for works to tie in the B2039 Ockham Road North to the improved A3 Ockham Park junction.

Work No.31(c),

Work No.31(h)

1/30, 1/31For works relating to the improvement of Mill Lane at the tie-in with the A3 northbound on-slip and construction of a drainage attenuation pond.

Work No.31(e),

Work No.31(d),

Work No.52(a)

Land Plans – Sheet 2
2/1For the provision of a topsoil and materials storage and processing area, structures worksite, traffic management area, welfare facilities and for the construction of a bridleway.

All Works

Work No.34

2/1aTo provide working space for the construction of a highway, a bridleway and a highway fence.

Work No.33,

Work No.63(a)

2/1bTo provide working space for the construction of a highway, a bridleway and highway fence.Work No.33
2/2, 2/4For the provision of a topsoil and materials storage area, structures worksite, traffic management area and welfare facilities.All Works
2/3For the provision of a topsoil and materials storage and a structures worksite, traffic management area, welfare facilities and for the construction of a bridleway.

All Works

Work No.34

2/5aTo provide working space for the construction of a highway and bridleway.Work No.33
2/5cFor the construction of a bridleway.Work No.34
2/6For the provision of a topsoil and materials storage area, structures worksite, traffic management area, welfare facilities and for the construction of a bridleway.

Work No.34

All Works

2/11To provide working space for a utility diversion.

Work No.33,

Work No.63(a)

2/13For the construction of a highway and utilities diversion.

Work No.33,

Work No.63(a)

2/21, 2/21aFor the improvement and widening of the A3 northbound and to provide working space for the construction of a retaining wall and utility diversion.

Work No.2,

Work No.64(a)

2/26To provide working space and access for the realignment of Wisley Lane and diversion of a footpath.

Work No.33(e),

Work No.33(h)

2/27aTo provide working space and access for the realignment of Wisley Lane.Work No.33(e)
2/28To provide working space and access and to allow the construction of a temporary road.

Work No.33(e),

Work No.33(f),

Work No.33(g),

Work No.65(c)

2/28bTo provide working space and access during modifications to the entrance to RHS Garden Wisley and utility diversions.

Work No.33(e),

Work No.33(f),

Work No.33(g),

Work No.62(c),

Work No.65(c)

2/30To provide working space and access and remediation of redundant carriageway.Work No.33(e)
2/31, 2/32To provide sufficient working space and access for the realignment of Wisley Lane and diversion of a footpath.

Work No.33(e),

Work No.33(h)

2/33To provide working space and access for diversion of a footpath.Work No.33(h)
Land Plans – Sheet 3
3/3, 3/3cTo provide working space to construct a bridleway and utility diversion.

Work No.35,

Work No.63(a)

3/7To provide working space to construct a bridleway, utility diversions, gantry, highways fence and for the improvement and widening of the A3 northbound.

Work No.1(c),

Work No.23(c),

Work No.35,

Work No.63(a),

Work No.64(a)

3/13aTo provide working space for utility diversion.Work No.63(a)
3/19bTo provide working space for the improvement of A3 southbound, works to a watercourse and access for environmental mitigation and enhancement works.

Work No.5(c),

Work No.5(d),

Work No.36,

Work No.53(b),

Work No.55

3/24To provide working space to construct a bridleway, utility diversions, gantry, highways fence and for the improvement and widening of the A3 northbound.

Work No.1(c),

Work No.23(c),

Work No.35,

Work No.63(a),

Work No.64(a)

3/33To provide working space to construct a bridleway, a utility diversion, and for environmental mitigation works.

Work No.35,

Work No.63(a),

Work No.56

3/34To provide working space to construct a bridleway, utility diversion and highway fence.

Work No.35,

Work No.63(a)

3/37aTo provide working space to extend a culvert, construct a utility diversion and a highway fence.

Work No.1(e),

Work No.63(a)

Land Plans – Sheet 4
4/3, 4/3bTo provide working space to construct a bridleway, a utilities diversion and for environmental mitigation works.

Work No.35,

Work No.56,

Work No.63(a)

4/3aTo provide sufficient working space and access to construct a new maintenance access and bridleway, to divert a gas pipeline and associated equipment, to build a highway fence and to construct a filter drain.

Work No.35,

Work No.63(a)

4/4cTo provide working space to construct a bridleway, a utility diversion, a highways fence and for the improvement and widening of the A3 northbound.

Work No.1(c),

Work No.35,

Work No.63(a)

4/15bTo provide working space for the alteration of the A3 southbound on-slip, improvement of junction of Old Lane, a utility diversion and construction of a highways fence.

Work No.4,

Work No.65(a)

4/19To provide working space for the construction of a bridleway, stopping up of existing accesses and improvement of junction of Old Lane.

Work No.4,

Work No.35(d)

4/22To provide working space to construct a bridleway and footpath.

Work No.35,

Work No.35(b),

Work No.35(d)

4/22aTo provide working space for the realignment of the access points to Ockham Common Car Park and to construct a bridleway and soakaway.Work No.35(d)
4/24To provide working space for the realignment of the access points to Ockham Bites Café and Ockham Common Car Park, the construction of a bridleway, the alteration and widening of the A3 southbound on-slip, the construction of an environmental barrier and highways fence and a utility diversion.

Work No.4,

Work No.35(d),

Work No.65(a),

Work No.61(d)

4/25To provide working space for the alteration and widening of the A3 southbound on-slip, improvement of junction of Old Lane and utility diversions

Work No.4,

Work No.62(f),

Work No.65(a)

4/27To provide working space to construct a bridleway.Work No.35(d)
4/30aTo provide working space for the alteration and widening of the A3 southbound on-slip, demolition of the Cockcrow overbridge, the construction of bridleway, environmental barrier and utilities diversion.Work No.4, Work No.35(b), Work No.35, Work No.61(d), Work No.65(a)
4/32, 4/33To provide working space to construct a bridleway and footpath.Work No.35, Work No.35(b)
4/35To provide working space for the alteration and widening of the A3 southbound on-slip, demolition of the Cockcrow overbridge, the construction of bridleway, environmental barrier and utility diversion.

Work No.4,

Work No.35,

Work No.61(d),

Work No.65(a)

4/40, 4/40aTo provide working space to construct a bridleway, a utility diversion, and to construct an access to a drainage attenuation pond.

Work No.35(b),

Work No.35(c),

Work No.63(a),

Work No.52(e)

4/42To provide working space to construct a bridleway, a drainage attenuation pond and a soakaway.

Work No.35,

Work No.52(f)

4/45, 4/45aTo provide working space for the widening of the A3 northbound, construction of a gantry, bridleway, utility diversions and a highways fence.

Work No.1(c),

Work No.23(d),

Work No.35,

Work No.62(e),

Work No.63(a),

Work No.64(b),

Work No.65(d)

4/46a, 4/46bTo provide working space to construct a bridleway and utility diversion.

Work No.35,

Work No.63(a)

4/48, 4/49, 4/49bTo provide working space to construct a bridleway and realignment to a private means of access.Work No.35(c)
4/48bTo provide working space to construct a bridleway, realignment to a private means of access and soakaway.Work No.35(c)
4/52aFor use as a construction access route.All Works
4/57To provide working space to construct a bridleway and utilities diversion.

Work No.35(c),

Work No.63(a)

4/58To provide working space and access to construct a bridleway, utilities diversion, environmental barrier and improvement of the A3 northbound carriageway.

Work No.1(c),

Work No.35(c),

Work No.63(a),

Work No.61(a)

4/62To provide working space to construct utilities diversion, environmental barrier and improvement of the A3 northbound carriageway.

Work No.1(c),

Work No.63(a),

Work No.61(a)

4/64, 4/65, 4/66, 4/66aTo provide working space to construct a utility diversion and to construct an access to a drainage attenuation pond.

Work No.63(a),

Work No.52(e)

4/69For the provision of a structures worksite.Work No.35(b)
4/74, 4/76, 4/78, 4/78a, 4/79, 4/80To provide working space to construct an access to a drainage attenuation pond.Work No.52(e)
4/81, 4/81aTo provide working space to construct a utility diversion and to construct an access to a drainage attenuation pond.

Work No.63(a),

Work No.52(e)

4/84To provide working space to for the demolition of the Cockcrow overbridge, construction of a drainage attenuation pond, utilities diversions, environmental barrier and improvement of the A3 northbound carriageway.

Work No.1(c),

Work No.63(a),

Work No.61(a),

Work No.35(b),

Work No.52(e),

Work No.61(a)

4/88For the provision of a site compound and working space for the improvement of the A3 northbound off-slip and construction of a drainage attenuation pond.All Works
Land Plans – Sheet 5
5/1For the provision of topsoil storage and to provide working space for the construction of a free-flow slip lane, alteration and widening of the M25 westbound off-slip, a bridleway, utilities diversions and environmental barrier.

Work No.11,

Work No.28,

Work No.35,

Work No.62(f),

Work No.61(d),

Work No.65(a)

5/2To provide working space to construct a bridleway and a drainage attenuation pond and fencing.

Work No.35,

Work No.52(g)

5/2aTo provide working space to construct a drainage attenuation pond and fencing.Work No.52(g)
5/7bTo provide working space for the construction of a free-flow slip lane, for the alteration and widening of the M25 eastbound on-slip and the construction of a bridleway, environmental barrier and the diversion or realignment of a watercourse.

Work No.10,

Work No.26,

Work No.35,

Work No.53(f),

Work No.61(c)

5/9To provide working space to construct a bridleway, a diversion or realignment of a watercourse and to construct a drainage attenuation pond and fencing.Work No.35, Work No.53(f), Work No.52(i)
5/11For use as a construction access route.All Works
5/12To provide working space for the construction of a temporary slip road, free-flow slip lane, environmental barrier, for a utility diversion, improvement of the M25 westbound on-slip and for the diversion and/or realignment of a watercourse.

Work No.29,

Work No.8,

Work No.53(d),

Work No.62(g),

Work No.61(a)

5/13To provide working space for the construction of a temporary slip road, free-flow slip lane, environmental barrier, for a utility diversion and improvement of A3 northbound off-slip.

Work No.3,

Work No.8,

Work No.62(g),

Work No.61(a)

5/22, 5/23To provide working space for the construction of a temporary slip road, free-flow slip lane, the improvement, realignment and widening of the M25 eastbound off-slip, the improvement, realignment and widening of the A3 northbound on-slip and the construction of an environmental barrier.

Work No.9,

Work No.14,

Work No.25,

Work No.61(b)

5/31To provide working space to construct a gantry.Work No.23(f)
Land Plans – Sheet 6
6/2a, 6/12, 6/12a,To provide working space to construct a bridleway.Work No.35
6/5, 6/5aFor use as a structures worksite.Work No.35(f)
6/13, 6/13a, 6/13b, 6/14To provide working space to construct a bridleway.Work No.39
6/18To provide working space for the improvement of the A3 southbound carriageway, works associated with stopping up an access to Painshill Park, to construct a retaining wall, a utility diversion and a highway fence.

Work No.17(a),

Work No.17(b),

Work No.17(e),

Work No.65(a)

6/21a, 6/21bTo provide working space for the improvement of the A3 southbound carriageway, to construct a retaining wall, a utility diversion and a highway fence.

Work No.17(a),

Work No.17(b),

Work No.23(h),

Work No.65(a)

6/22bTo provide working space for the improvement of the A3 southbound carriageway, to construct a retaining wall, a utility diversion and a highway fence.

Work No.17(a),

Work No.17(b),

Work No.65(a)

Land Plans – Sheet 7
7/6For the provision of a construction site compound.All works
7/12, 7/22For the provision of topsoil and materials storage.All works
7/13, 7/13a, 7/14To provide access and working space for a utility diversion.Work No.63(c)
7/23a, 7/28To provide working space for the improvement and widening of the A3 northbound off-slip, utility diversion and highway fence.

Work No.16,

Work No.62(k)

Land Plans – Sheet 8
8/7a, 8/7bTo provide working space to construct a footpath, utilities diversions and highways fence.

Work No.41,

Work No.62(l),

Work No.63(c),

Work No.65(a)

8/27, 8/28, 8/29, 8/30To provide working space to improve the A245 Portsmouth Road at the tie-in with the A3 Painshill junction.

Work No.42(a),

Work No.42(b)

8/34To provide working space to improve the A3 southbound carriageway, the A3 Painshill junction and the A245 Portsmouth Road at the tie-in with the A3 Painshill junction.

Work No.17(a),

Work No.42(a),

Work No.42(b)

Land Plans – Sheet 9
9/4To provide working space to construct improvements to the A245 Byfleet Road westbound and eastbound carriageways and B365 Seven Hills Road, a dedicated slip road, a utility diversion and a highway fence.

Work No.44(a),

Work No.44(e),

Work No.44(f),

Work No.45,

Work No.47(a),

Work No.62(p)

9/4aTo provide working space to construct new private access to Feltonfleet School from B365 Seven Hills Road.

Work No.45,

Work No.46

9/7To provide working space to construct improvements and widening to the A245 Byfleet Road westbound and eastbound carriageways, a dedicated slip road, stopping up of an access, utilities diversions and a highway fence.

Work No.44(a),

Work No.44(b),

Work No.44(c),

Work No.44(d),

Work No.44(e),

Work No.44(f),

Work No.47(a),

Work No.47(b),

Work No.62(p),

Work No.62(o)

9/8, 9/9, 9/10To provide working space and construct improvements to the A245 Byfleet Road eastbound carriageway.Work No.47(a)
9/12To provide working space for the improvement and widening of the A245 Byfleet Road eastbound carriageway and for the construction of a footway, utilities diversions and a highway fence.

Work No.47(a),

Work No.47(b),

Work No.47(e),

Work No.62(q),

Work No.64(k),

Work No.65(h)

Land Plans – Sheet 11
11/1To provide working space for the improvement of the M25 westbound carriageway, the improvement and widening of the M25 westbound on-slip and the construction of an environmental barrier.

Work No.27(a),

Work No.29,

Work No.61(a)

11/9, 11/9aFor the provision of topsoil and materials storage and working space for the improvement of the M25 westbound carriageway, the improvement and widening of the M25 westbound on-slip, the construction of a soakaway and an environmental barrier.All Works
11/10, 11/10a, 11/11For the provision of topsoil and materials storage and working space for the improvement of the M25 westbound carriageway, the improvement and widening of the M25 westbound on-slip, the construction of a soakaway and an environmental barrier.All Works
11/26To provide working space for the construction of a bridleway and drainage attenuation pond and fencing.

Work No.49,

Work No.52(m)

Land Plans – Sheet 12
12/1dTo provide working space for the construction of a bridleway and drainage attenuation pond and fencing.

Work No.49,

Work No.52(m)

12/5To provide working space for the construction of a bridleway and demolition and replacement of existing Clearmount overbridge.Work No.49
12/25aTo provide working space for the construction of a bridleway tie-in to an existing permissive signposted route.Work No.49
12/25dTo provide working space for the construction of a new gas main diversion under the M25.Work No.63(e)
Land Plans – Sheet 13
13/1To provide working space to construct a bridleway, a diversion or realignment of a watercourse and drainage ditch.

Work No.35(e),

Work No.53(f)

13/1aTo provide working space to construct a bridleway.Work No.35(e)
Land Plans – Sheet 20
20/1a, 20/5For modifications to road signage.Work No.33(i)
Land Plans – Sheet 23
23/2For modifications to the entrance to Orchard Cottage.Work No.34
23/3To provide working space for the construction of a turning head on Elm Lane.Work No.34
23/5, 23/6To provide access to construction of Work No.34.Work No.34
23/7

For modifications to the entrance to Orchard Cottage and to provide working space for the construction of a turning head on Elm Lane.

To provide access to construction of Work No.34.

Work No.34
Land Plans – Sheet 24
24/1To provide working space to tie-in Elm Lane to Elm Corner.Work No.50(a)
24/2For the improvement of Byway 525 (Byway Open to All Traffic), between Elm Corner and Old Lane.Work No.50(a)
24/3

For the improvement of Byway 525 (Byway Open to All Traffic), between Elm Corner and Old Lane.

To provide working space to tie-in Elm Lane to Hatch Lane.

Work No.50(a)
24/4, 24/4a, 24/4bTo provide working space to tie-in Elm Lane to Old Lane and to install two toad underpasses and associated reptilian fencing along Old Lane.    To provide working space to clear trees and other vegetation to create a visibility splay including road traffic mitigation measures

Work No.50(a)

Work No.50(b)

Land Plans – Sheet 26
26/2aTo provide working space for the construction of a footpath.Work No.51

Yn ôl i’r brig

Options/Help

Print Options

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill