Chwilio Deddfwriaeth

The Boiler Upgrade Scheme (England and Wales) Regulations 2022

Changes over time for: PART 3

 Help about opening options

Alternative versions:

Status:

Point in time view as at 08/05/2024.

Changes to legislation:

There are currently no known outstanding effects for the The Boiler Upgrade Scheme (England and Wales) Regulations 2022, PART 3. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 3E+WEligible plant

Eligible plantE+W

8.—(1) For the purposes of these Regulations, a heat pump is an eligible plant where—

(a)it meets the requirements for heat pumps set out in regulation 9(1), and

(b)once installed—

(i)it meets the suitability criteria in relation to the eligible property F1... for which it is installed, determined in accordance with regulation 9(2), and

(ii)it is first commissioned [F2no more than 120 days before the date on which the grant application is properly made, unless the Authority has made a decision to extend this period under paragraph (3)].

(2) For the purposes of these Regulations, subject to regulation 11, a biomass boiler is an eligible plant where—

(a)it meets the requirements for biomass boilers set out in regulation 10(1), and

(b)once installed—

(i)it meets the suitability criteria in relation to the eligible property, F3... for which it is installed, determined in accordance with regulation 10(2), and

(ii)it is first commissioned [F4no more than 120 days before the date on which the grant application is properly made, unless the Authority has made a decision to extend this period under paragraph (3)].

[F5(3) The Authority may by notice extend the period specified in paragraph (1)(b)(ii) or (2)(b)(ii) where—

(a)that period has been exceeded, or is likely to be exceeded, following a decision by the Authority under regulation 15(7), 15(8), 16(8), 21(1), 23 or 25(5), and

(b)it is satisfied that it is reasonable to do so.]

Requirements for heat pumpsE+W

9.—(1) A heat pump meets the requirements in this paragraph where—

(a)no part of the heat pump which generates heat, other than the ground loop in the case of a subsequent heat pump installation in relation to a shared ground loop system, was used before the plant was first commissioned,

(b)it has a capacity of no more than 45 kilowatt thermal, or, in the case of a shared ground loop system, [F6the system has a capacity of no more than 300] kilowatt thermal,

(c)it meets the requirements set out in the standards for heat pumps approved by the Secretary of State under regulation 4(1)(b) which are applicable when the plant is first commissioned,

(d)it has a seasonal coefficient of performance of at least 2.8, determined in accordance with the standard approved by the Secretary of State under regulation 4(1)(c) which is applicable when the plant is first commissioned,

(e)it uses a compressor which is driven by electricity, and

(f)if it is an air source heat pump, it is not designed to use heat in air which has been expelled from an appliance or building.

(2) A heat pump meets the suitability criteria in relation to the eligible property F7... for which it is installed where—

(a)it provides heating—

(i)solely to that property, or to both that property and any related property, and

(ii)for the purpose of both space heating and hot water heating, using liquid as a medium for delivering that heat,

(b)it is capable of meeting the full space heating and hot water heating demands of that property, and

(c)it replaces the heat generating components of the original heating system installed in that property (where applicable), other than any—

(i)supplementary electric heater, including any immersion heater,

(ii)circulation pump, or

(iii)solar thermal collector.

(3) For the purposes of paragraph (1)—

(a)ground loop”, in relation to a shared ground loop system, means the equipment which absorbs energy stored in the form of heat in the ground, including heat in water in the ground, or in surface water,

(b)shared ground loop system” means a system in which a ground loop provides heat energy through a hydraulic connection to two or more ground source heat pumps,

(c)subsequent heat pump installation”, in relation to a shared ground loop system, means the installation of a second or subsequent ground source heat pump as part of an existing shared ground loop system.

(4) For the purposes of paragraph (2) and regulation 10(2), “hot water” means hot water which is intended for the personal use of the individuals who use or occupy the eligible property F8... and does not include hot water used for the purposes of—

(a)space heating,

(b)heating a swimming pool, or

(c)carrying out a process.

Requirements for biomass boilersE+W

10.—(1) A biomass boiler meets the requirements in this paragraph where—

(a)no part of the biomass boiler which generates heat was used before the plant is first commissioned,

(b)it has a capacity of no more than 45 kilowatt thermal,

(c)it meets the requirements set out in the standards for biomass boilers approved by the Secretary of State under regulation 4(1)(d) which are applicable when the plant was first commissioned,

(d)an emissions certificate that meets the requirements set out in Schedule 1 (requirements for emissions certificates)—

(i)has been issued for the plant,

(ii)has been issued for a plant of the same make, model and installation capacity as the plant, or

(iii)specifies the plant as being in the same type-testing range as a plant for which an emissions certificate has been issued (see paragraph 1(m) of Schedule 1),

[F9(e)if the biomass boiler has a cooking function that is not able to be controlled independently of the heating or hot water function.]

(2) A biomass boiler meets the suitability criteria in relation to the eligible property F10... in which it is installed where—

(a)it provides heating—

(i)solely to that property, or to both that property and any related property, and

(ii)for the purpose of space heating and hot water heating, using liquid as a medium for delivering that heat,

(b)it is capable of meeting the full space heating and hot water heating demands of that property, and

(c)it replaces the heat generating components of the original heating system installed in the eligible property (where applicable), other than any—

(i)supplementary electric heater, including any immersion heater,

(ii)circulation pump, or

(iii)solar thermal collector.

Textual Amendments

Commencement Information

I3Reg. 10 in force at 23.5.2022, see reg. 1(1)

Properties in relation to which biomass boilers are not eligible plantE+W

11.  A biomass boiler is not an eligible plant in relation to a property, where the property—

(a)is in an urban area,

(b)is fuelled by mains gas, or

(c)falls within regulation 5(1)(d) and meets the requirements in regulation 7 (new-build properties).

Commencement Information

I4Reg. 11 in force at 23.5.2022, see reg. 1(1)

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Asesiadau Effaith

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill