- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Gwreiddiol (a wnaed Fel)
There are currently no known outstanding effects for the The M25 Junction 28 Development Consent Order 2022, PART 5.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
25.—(1) The undertaker may acquire compulsorily so much of the Order land as is required for the authorised development, or to facilitate it, or is incidental to it.
(2) This article is subject to paragraph (2) of article 28 (compulsory acquisition of rights and imposition of restrictive covenants) and article 34 (temporary use of land for carrying out the authorised development).
Commencement Information
I1Art. 25 in force at 6.6.2022, see art. 1
26. Parts 2 and 3 of Schedule 2 (minerals) to the Acquisition of Land Act 1981(1) are incorporated in this Order subject to the modifications that—
(a)paragraph 8(3) is not incorporated;
(b)for “the acquiring authority” substitute “the undertaker”;
(c)for “undertaking” substitute “authorised development”; and
(d)for “compulsory purchase order” substitute “this order”.
Commencement Information
I2Art. 26 in force at 6.6.2022, see art. 1
27.—(1) After the end of the period of 5 years beginning on the day on which this Order is made—
(a)no notice to treat is to be served under Part 1 (compulsory purchase under Acquisition of Land Act 1946) of the 1965 Act as modified by article 30 (modification of Part 1 of the 1965 Act); and
(b)no declaration is to be executed under section 4 (execution of declaration) of the 1981 Act as applied by article 31 (application of the 1981 Act).
(2) The authority conferred by article 34 (temporary use of land for carrying out the authorised development) ceases at the end of the period referred to in paragraph (1), except that nothing in this paragraph prevents the undertaker remaining in possession of land after the end of that period, if the land was entered and possession was taken before the end of that period.
Commencement Information
I3Art. 27 in force at 6.6.2022, see art. 1
28.—(1) Subject to paragraphs (2) to (5), the undertaker may acquire such rights over the Order land, or impose restrictive covenants affecting the Order land, as may be required for which that land may be acquired under article 25 (compulsory acquisition of land) by creating them as well as acquiring rights already in existence.
(2) In the case of the Order land specified in column (1) of Schedule 6 (land in which new rights only etc. may be acquired) the undertaker’s powers of compulsory acquisition under article 25(1) are limited to the acquisition of such wayleaves, easements, new rights in the land or the imposition of restrictive covenants, as may be required for the purpose specified in relation to that land in column (2) of that Schedule.
(3) The power to impose restrictive covenants under paragraph (1) is exercisable only in respect of plots specified in column (1) of Schedule 6.
(4) The power under paragraph (1) to acquire the rights and to impose the restrictive covenants described in Schedule 6 for the benefit of statutory undertakers or for the benefit of any other person—
(a)does not preclude the acquisition of such other rights and the imposition of such other restrictive covenants in respect of the same land in accordance with Schedule 6 as may be required for the benefit of any other statutory undertaker or any other person; and
(b)must not be exercised by the undertaker in a way that precludes the acquisition of such other rights and the imposition of such other restrictive covenants in respect of the same land in accordance with Schedule 6 as are required for the benefit of any other statutory undertaker or any other person.
(5) Subject to Schedule 2A (counter-notice requiring purchase of land not in notice to treat) of the 1965 Act, as substituted by paragraph 5(8) of Schedule 7 (modification of compensation and compulsory purchase enactments for creation of new rights and imposition of restrictive covenants), where the undertaker acquires a right over land or the benefit of a restrictive covenant affecting land under paragraph (1) or (2), the undertaker is not required to acquire a greater interest in that land.
(6) Schedule 7 (modification of compensation and compulsory purchase enactments for creation of new rights and imposition of restrictive covenants) has effect for the purpose of modifying the enactments relating to compensation and the provisions of the 1965 Act in their application in relation to the compulsory acquisition under this article of a right over land by the creation of a new right or the imposition of a restrictive covenant.
Commencement Information
I4Art. 28 in force at 6.6.2022, see art. 1
29.—(1) Subject to the provisions of this article, all private rights over land subject to compulsory acquisition under this Order are extinguished—
(a)from the date of acquisition of the land by the undertaker, whether compulsorily or by agreement; or
(b)on the date of entry on the land by the undertaker under section 11(1)(2) (powers of entry) of the 1965 Act,
whichever is the earlier.
(2) Subject to the provisions of this article, all private rights over land subject to the compulsory acquisition of rights or the imposition of restrictive covenants under this Order are extinguished in so far as their continuance would be inconsistent with the exercise of the right or the burden of the restrictive covenant—
(a)from the date of the acquisition of the right or the benefit of the restrictive covenant by the undertaker, whether compulsorily or by agreement; or
(b)on the date of entry on the land by the undertaker under section 11(1) of the 1965 Act,
whichever is the earlier.
(3) Subject to the provisions of this article, all private rights over land owned by the undertaker that are within the Order limits are extinguished on commencement of any activity authorised by this Order which interferes with or breaches those rights.
(4) Subject to the provisions of this article, all private rights over land of which the undertaker takes temporary possession under this Order are suspended and unenforceable for as long as the undertaker remains in lawful possession of the land.
(5) Any person who suffers loss by the extinguishment or suspension of any private right under this article is entitled to compensation in accordance with the terms of section 152(3) (compensation in case where no right to claim in nuisance) of the 2008 Act to be determined, in case of dispute, as if it were a dispute under Part 1 of the 1961 Act.
(6) This article does not apply in relation to any right to which section 138(4) (extinguishment of rights, and removal of apparatus, of statutory undertakers etc.) of the 2008 Act or article 37 (statutory undertakers) applies.
(7) Paragraphs (1) to (4) have effect subject to—
(a)any notice given by the undertaker before—
(i)the completion of the acquisition of the land or the acquisition of the right or the imposition of the restrictive covenant over or affecting the land;
(ii)the undertaker’s appropriation of it;
(iii)the undertaker’s entry onto it; or
(iv)the undertaker’s taking temporary possession of it,
that any or all of those paragraphs do not apply to any right specified in the notice; and
(b)any agreement made at any time between the undertaker and the person in or to whom the right in question is vested or belongs.
(8) If any such agreement as is referred to in paragraph (7)(b)—
(a)is made with a person in or to whom the right is vested or belongs; and
(b)is expressed to have effect also for the benefit of those deriving title from or under that person,
it is effective in respect of the persons so deriving title, whether the title was derived before or after the making of the agreement.
(9) References in this article to private rights over land include any right of way, trust, incident, easement, liberty, privilege, right or advantage annexed to land and adversely affecting other land, including any natural right to support and include restrictions as to the user of land arising by virtue of a contract, agreement or undertaking having that effect.
Commencement Information
I5Art. 29 in force at 6.6.2022, see art. 1
30.—(1) Part 1 of the 1965 Act, as applied to this Order by section 125(5)(application of compulsory acquisition provisions) of the 2008 Act, is modified as follows.
(2) In section 4A(1)(6) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to the High Court in respect of compulsory purchase order), the three year period mentioned in section 4” substitute “section 118(7) (legal challenges relating to applications for orders granting development consent) of the Planning Act 2008, the five year period mentioned in article 27 (time limit for exercise of authority to acquire land compulsorily) of the M25 Junction 28 Development Consent Order 2022”.
(3) In section 11A(8) (powers of entry: further notice of entry)—
(a)in subsection (1)(a), after “land” insert “under that provision”;
(b)in subsection (2), after “land” insert “under that provision”.
(4) In section 22(2) (expiry of time limit for exercise of compulsory purchase power not to affect acquisition of interests omitted from purchase), for “section 4 of this Act” substitute “article 27 (time limit for exercise of authority to acquire land compulsorily) of the M25 Junction 28 Development Consent Order 2022”.
(5) In Schedule 2A (counter-notice requiring purchase of land not in notice to treat)—
(a)for paragraphs 1(2) and 14(2) substitute—
“(2) But see article 32(3) (acquisition of subsoil or airspace only) of the M25 Junction 28 Development Consent Order 2022, which excludes the acquisition of subsoil or airspace only from this Schedule.”; and
(b)after paragraph 29, insert—
30. In this Schedule, references to entering on and taking possession of land do not include doing so under articles 21 (protective work to buildings), 34 (temporary use of land for carrying out the authorised development) or 35 (temporary use of land for maintaining the authorised development) of the M25 Junction 28 Development Consent Order 2022.”.
Commencement Information
I6Art. 30 in force at 6.6.2022, see art. 1
31.—(1) The 1981 Act applies as if this Order were a compulsory purchase order.
(2) The 1981 Act, as so applied by paragraph (1), has effect with the following modifications.
(3) In section 1 (application of Act), for subsection 2 substitute—
“(2) This section applies to any Minister, any local or other public authority or any other body or person authorised to acquire land by means of a compulsory purchase order.”.
(4) In section 5(9) (earliest date for execution of declaration), in subsection (2), omit the words from “, and this subsection” to the end.
(5) Omit section 5A(10) (time limit for general vesting declaration).
(6) In section 5B(1)(11) (extension of time limit during challenge) for “section 23 of the Acquisition of Land Act 1981 (application to High Court in respect of compulsory purchase order), the three year period mentioned in section 5A” substitute “section 118 (legal challenges relating to applications for orders granting development consent) of the Planning Act 2008, the five year period mentioned in article 27 (time limit for exercise of authority to acquire land compulsorily) of the M25 Junction 28 Development Consent Order 2022”.
(7) In section 6(12) (notices after execution of declaration) in subsection (1)(b) for “section 15 of, or paragraph 6 of Schedule 1 to, the Acquisition of Land Act 1981” substitute “section 134(13) (notice of authorisation of compulsory acquisition) of the Planning Act 2008”.
(8) In section 7(14) (constructive notice to treat) in subsection (1)(a), omit “(as modified by section 4 of the Acquisition of Land Act 1981)”.
(9) In section 11 (recovery of compensation overpaid), for subsection (1) substitute—
“(1) This section applies where after the execution of a general vesting declaration a person (“the claimant”) claims compensation in respect of the acquisition of an interest in land by virtue of the declaration, and the acquiring authority pay compensation in respect of that interest.”.
(10) In Schedule A1(15) (counter-notice requiring purchase of land not in general vesting declaration), omit paragraph 1(2).
(11) References to the 1965 Act in the 1981 Act are to be construed as references to the 1965 Act as applied by section 125 (application of compulsory acquisition provisions) of the 2008 Act (and as modified by article 30 (modification of Part 1 of the 1965 Act)) to the compulsory acquisition of land under this Order.
Commencement Information
I7Art. 31 in force at 6.6.2022, see art. 1
32.—(1) The undertaker may acquire compulsorily so much of, or such rights in, the subsoil of or of the airspace over the land referred to in paragraph (1) of article 25 (compulsory acquisition of land) as may be required for any purpose for which that land may be acquired under that provision instead of acquiring the whole of the land.
(2) Where the undertaker acquires any part of, or rights in, the subsoil of or the airspace over land referred to in paragraph (1), the undertaker is not required to acquire an interest in any other part of the land.
(3) The following do not apply in connection with the exercise of the power under paragraph (1) in relation to subsoil or airspace only—
(a)Schedule 2A (counter-notice requiring purchase of land not in notice to treat) to the 1965 Act (as modified by article 30 (modification of Part 1 of the 1965 Act));
(b)Schedule A1 (counter-notice requiring purchase of land not in general vesting declaration) to the 1981 Act; and
(c)section 153(4A)(16) (blighted land: proposed acquisition of part interest; material detriment test) of the 1990 Act.
(4) Paragraphs (2) and (3) are to be disregarded where the undertaker acquires a cellar, vault, arch or other construction forming part of a house, building or manufactory.
Commencement Information
I8Art. 32 in force at 6.6.2022, see art. 1
33.—(1) The undertaker may enter on and appropriate so much of the subsoil of, or airspace over, any street within the Order limits as may be required for the purposes of the authorised development and may use the subsoil or airspace for those purposes or any other purpose ancillary to the authorised development.
(2) Subject to paragraph (3), the undertaker may exercise any power conferred by paragraph (1) in relation to a street without being required to acquire any part of the street or any easement or right in the street.
(3) Paragraph (2) does not apply in relation to—
(a)any subway or underground building; or
(b)any cellar, vault, arch or other construction in, on or under a street which forms part of a building fronting onto the street.
(4) Subject to paragraph (5), any person who is an owner or occupier of land in respect of which the power of appropriation conferred by paragraph (1) is exercised without the undertaker acquiring any part of that person’s interest in the land, and who suffers loss as a result, will be entitled to compensation to be determined, in case of dispute, as if it were a dispute under Part 1 of the 1961 Act.
(5) Compensation is not payable under paragraph (4) to any person who is an undertaker to whom section 85 (sharing cost of necessary measures) of the 1991 Act applies in respect of measures of which the allowable costs are to be borne in accordance with that section.
Commencement Information
I9Art. 33 in force at 6.6.2022, see art. 1
34.—(1) The undertaker may, in connection with the carrying out of the authorised development, but subject to article 27(2) (time limit for exercise of authority to acquire land compulsorily)—
(a)enter on and take temporary possession of—
(i)the land specified in column (1) of Schedule 8 (land of which temporary possession only may be taken) for the purpose specified in relation to that land in column (2) of that Schedule relating to the part of the authorised development specified in column (3) of that Schedule; and
(ii)any other Order land in respect of which no notice of entry has been served under section 11 (powers of entry) of the 1965 Act (other than in connection with the acquisition of rights only) and no declaration has been made under section 4 (execution of declaration) of the 1981 Act;
(b)remove any electric line, electrical plant, apparatus, buildings, landscaping and vegetation from that land;
(c)construct temporary works (including the provision of means of access) and buildings on that land; and
(d)construct any works on that land as are mentioned in Schedule 1 (authorised development).
(2) Not less than 14 days before entering on and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land and explain the purpose for which entry is taken in respect of land specified under paragraph (1)(a)(ii).
(3) The undertaker must not, without the agreement of the owners of the land, remain in possession of any land under this article—
(a)in the case of land specified in paragraph (1)(a)(i), after the end of the period of one year beginning with the date of completion of the part of the authorised development specified in relation to that land in column (3) of Schedule 8; or
(b)in the case of any land referred to in paragraph (1)(a)(ii), after the end of the period of one year beginning with the date of completion of the work for which temporary possession of the land was taken unless the undertaker has, by the end of that period, served a notice of entry under section 11 of the 1965 Act or made a declaration under section 4 (execution of declaration) of the 1981 Act in relation to that land.
(4) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land; but the undertaker is not required to—
(a)replace a building removed under this article;
(b)restore the land on which any permanent works have been constructed under paragraph (1)(d);
(c)remove any ground strengthening works which have been placed on the land to facilitate construction of the authorised development;
(d)remove any measures installed over or around statutory undertakers’ apparatus to protect that apparatus from the authorised development; or
(e)remove or reposition any apparatus belonging to statutory undertakers or necessary mitigation works.
(5) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the provisions of this article.
(6) Any dispute as to a person’s entitlement to compensation under paragraph (5), or as to the amount of the compensation, is to be determined as if it were a dispute under Part 1 of the 1961 Act.
(7) Any dispute as to the removal of temporary works and restoration of land under paragraph (4) does not prevent the undertaker giving up possession of the land.
(8) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the carrying out of the authorised development, other than loss or damage for which compensation is payable under paragraph (5).
(9) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.
(10) Section 13(17) (refusal to give possession to acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.
(11) Nothing in this article prevents the taking of temporary possession more than once in relation to any land specified in paragraph (1).
Commencement Information
I10Art. 34 in force at 6.6.2022, see art. 1
35.—(1) Subject to paragraph (2), at any time during the maintenance period relating to any part of the authorised development, the undertaker may—
(a)enter upon and take temporary possession of any land within the Order limits if such possession is reasonably required for the purpose of maintaining the authorised development;
(b)enter onto land within the Order limits for the purpose of gaining such access as is reasonably required for the purpose of maintaining the authorised development; and
(c)construct such temporary works (including the provision of means of access) and buildings on the land as may be reasonably necessary for that purpose.
(2) Paragraph (1) does not authorise the undertaker to take temporary possession of—
(a)any house or garden belonging to a house; or
(b)any building (other than a house) if it is for the time being occupied.
(3) Not less than 28 days before entering upon and taking temporary possession of land under this article the undertaker must serve notice of the intended entry on the owners and occupiers of the land and explain the purpose for which entry is taken.
(4) The undertaker is not required to serve notice under paragraph (3) where the undertaker has identified a potential risk to the safety of—
(a)the authorised development or any of its parts;
(b)the public; or
(c)the surrounding environment,
and in such circumstances, the undertaker may enter the land under paragraph (1) subject to giving such period of notice as is reasonably practical in the circumstances.
(5) The undertaker may only remain in possession of land under this article for so long as may be reasonably necessary to carry out the maintenance of the part of the authorised development for which possession of the land was taken.
(6) Before giving up possession of land of which temporary possession has been taken under this article, the undertaker must remove all temporary works and restore the land to the reasonable satisfaction of the owners of the land.
(7) Any dispute as to the removal of temporary works and restoration of land under paragraph (6) does not prevent the undertaker giving up possession of the land.
(8) The undertaker must pay compensation to the owners and occupiers of land of which temporary possession is taken under this article for any loss or damage arising from the exercise in relation to the land of the powers conferred by this article.
(9) Any dispute as to a person’s entitlement to compensation under paragraph (8), or as to the amount of the compensation, is to be determined as if it were a dispute under Part 1 of the 1961 Act.
(10) Nothing in this article affects any liability to pay compensation under section 152 (compensation in case where no right to claim in nuisance) of the 2008 Act or under any other enactment in respect of loss or damage arising from the execution of any works, other than loss or damage for which compensation is payable under paragraph (8).
(11) Where the undertaker takes possession of land under this article, the undertaker is not required to acquire the land or any interest in it.
(12) Section 13 (refusal to give possession to the acquiring authority) of the 1965 Act applies to the temporary use of land under this article to the same extent as it applies to the compulsory acquisition of land under this Order by virtue of section 125 (application of compulsory acquisition provisions) of the 2008 Act.
(13) In this article “the maintenance period”, in relation to any part of the authorised development means the period of 5 years beginning with the date on which that part of the authorised development is first opened for use.
Commencement Information
I11Art. 35 in force at 6.6.2022, see art. 1
36.—(1) Nothing in this Order affects prejudicially any estate, right, power, privilege, authority or exemption of the Crown and, in particular, nothing in this Order authorises the undertaker or any grantee to take, use, enter upon or in any manner interfere with any land or rights of any description including any portion of the shore or bed of the sea or any river, channel, creek, bay or estuary—
(a)belonging to Her Majesty in right of the Crown and forming part of the Crown Estate without the consent in writing of the Crown Estate Commissioners;
(b)belonging to Her Majesty in right of the Crown and not forming part of the Crown Estate without the consent in writing of the government department having the management of that land; or
(c)belonging to a government department or held in trust for Her Majesty for the purposes of a government department without the consent in writing of that government department.
(2) Paragraph (1) does not apply to the exercise of any right under this Order for the compulsory acquisition of an interest in any Crown land (as defined in the 2008 Act) which is for the time being held otherwise than by or on behalf of the Crown.
(3) A consent under paragraph (1) may be given unconditionally or subject to terms and conditions; and is deemed to have been given in writing where it is sent electronically.
Commencement Information
I12Art. 36 in force at 6.6.2022, see art. 1
37.—(1) Subject to the provisions of Schedule 9 (protective provisions), article 28 (compulsory acquisition of rights and imposition of restrictive covenants), and paragraph (2), the undertaker may—
(a)acquire compulsorily, or acquire new rights, or impose restrictive covenants over any Order land belonging to statutory undertakers; and
(b)extinguish the rights of, and remove or reposition apparatus belonging to, statutory undertakers over or within the Order land.
(2) Paragraph (1)(b) has no effect in relation to apparatus in respect of which the following provisions apply—
(a)Part 3 of the 1991 Act; and
(b)article 38 (apparatus and rights of statutory undertakers in stopped up streets).
Commencement Information
I13Art. 37 in force at 6.6.2022, see art. 1
38.—(1) Where a street is stopped up under article 15 (permanent stopping up of streets), any statutory utility whose apparatus is under, in, on, along or across the street has the same powers and rights in respect of that apparatus, subject to the provisions of this article, as if this Order had not been made.
(2) Where a street is stopped up under article 15 any statutory utility whose apparatus is under, in, on, over, along or across the street may, and if reasonably requested to do so by the undertaker must—
(a)remove the apparatus and place it or other apparatus provided in substitution for it in such other position as the utility may reasonably determine and have power to place it; or
(b)provide other apparatus in substitution for the existing apparatus and place it in such position as described in sub-paragraph (a).
(3) Subject to the following provisions of this article, the undertaker must pay to any statutory utility an amount equal to the cost reasonably incurred by the utility in or in connection with—
(a)the execution of the relocation works required in consequence of the stopping up of the street; and
(b)the doing of any other work or thing rendered necessary by the execution of the relocation works.
(4) If in the course of the execution of relocation works under paragraph (2)—
(a)apparatus of a better type, of greater capacity or of greater dimensions is placed in substitution for existing apparatus; or
(b)apparatus (whether existing apparatus or apparatus substituted for existing apparatus) is placed at a depth greater than the depth at which the existing apparatus was,
and the placing of apparatus of that type or capacity or of those dimensions or the placing of apparatus at that depth, as the case may be, is not agreed by the undertaker, or, in default of agreement, is not determined by arbitration to be necessary, then, if it involves cost in the execution of the relocation works exceeding that which would have been involved if the apparatus placed had been of the existing type, capacity or dimensions, or at the existing depth, as the case may be, the amount which, apart from this paragraph, would be payable to the statutory utility by virtue of paragraph (3) is to be reduced by the amount of that excess.
(5) For the purposes of paragraph (4)—
(a)an extension of apparatus to a length greater than the length of existing apparatus is not to be treated as a placing of apparatus of greater dimensions than those of the existing apparatus; and
(b)where the provision of a joint in a cable is agreed, or is determined to be necessary, the consequential provision of a jointing chamber or of a manhole is to be treated as if it also had been agreed or had been so determined.
(6) An amount which, apart from this paragraph, would be payable to a statutory utility in respect of works by virtue of paragraph (3) (and having regard, where relevant, to paragraph (4)) must, if the works include the placing of apparatus provided in substitution for apparatus placed more than 7 years and 6 months earlier so as to confer on the utility any financial benefit by deferment of the time for renewal of the apparatus in the ordinary course, be reduced by the amount which represents that benefit.
(7) Paragraphs (3) to (6) do not apply where the authorised development constitutes major highway works, major bridge works or major transport works for the purposes of Part 3 of the 1991 Act, but instead—
(a)the allowable costs of the relocation works are to be determined in accordance with section 85 (sharing of cost of necessary measures) of that Act and any regulations for the time being having effect under that section; and
(b)the allowable costs are to be borne by the undertaker and the statutory utility in such proportions as may be prescribed by any such regulations.
(8) In this article—
“relocation works” means work executed, or apparatus provided, under paragraph (2); and
“statutory utility” means a statutory undertaker for the purposes of the 1980 Act or a public communications provider as defined in section 151(1) (interpretation of chapter 1) of the Communications Act 2003(18).
Commencement Information
I14Art. 38 in force at 6.6.2022, see art. 1
39.—(1) Where any apparatus of a public utility undertaker or of a public communications provider is removed under article 37 (statutory undertakers) any person who is the owner or occupier of premises to which a supply was given from that apparatus is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of effecting a connection between the premises and any other apparatus from which a supply is given.
(2) Paragraph (1) does not apply in the case of the removal of a public sewer but where such a sewer is removed under article 37, any person who is—
(a)the owner or occupier of premises the drains of which communicated with that sewer; or
(b)the owner of a private sewer which communicated with that sewer,
is entitled to recover from the undertaker compensation in respect of expenditure reasonably incurred by that person, in consequence of the removal, for the purpose of making the drain or sewer belonging to that person communicate with any other public sewer or with a private sewerage disposal plant.
(3) This article does not have effect in relation to apparatus to which article 38 (apparatus and rights of statutory undertakers in stopped up streets) or Part 3 of the 1991 Act applies.
(4) In this paragraph—
“public communications provider” has the same meaning as in section 151(1) of the Communications Act 2003; and
“public utility undertaker” means a gas, water, electricity or sewerage undertaker.
Commencement Information
I15Art. 39 in force at 6.6.2022, see art. 1
40.—(1) On the exercise by the undertaker of the relevant Order powers, so much of the special category land as is required for the purposes of the exercise by the undertaker of the Order rights is discharged from all rights, trusts and incidents to which it was previously subject, so far as their continuance would be inconsistent with the exercise by the undertaker of the Order rights.
(2) So far as the temporary use of land under article 34 (temporary use of land for carrying out the authorised development) is concerned, then the discharge in paragraph (1) is only for such time as the land is being used under that article.
(3) In this article—
“Order rights” means the rights and powers exercisable over the special category land by the undertaker under article 28 (compulsory acquisition of rights and imposition of restrictive covenants) and article 34;
“the special category land” means the land identified as forming part of a common, open space, or fuel or field allotment and numbered 1/8 and 1/8a in the book of reference and on the plan entitled “special category land plans”; and
“special category land plans” means the documents of that description certified by the Secretary of State as the special category land plans for the purposes of this Order.
Commencement Information
I16Art. 40 in force at 6.6.2022, see art. 1
Section 11(1) was amended by section 34(1) of, and Schedule 4 to, the Acquisition of Land Act 1981 (c. 67), section 14 of, and paragraph 12(1) of Schedule 5 to, the Church of England (Miscellaneous Provisions) Measure 2006 (No. 1), and sections 186 (1) and (2), 187 and 188 of the Housing and Planning Act 2016 (c. 22).
Section 152 was amended by S.I. 2009/1307.
Section 138 was amended by section 23(1) and (4) of the Growth and Infrastructure Act 2013 (c. 27) and S.I. 2017/1285.
Section 125 was amended by section 190 of, and paragraph 17 of Schedule 16 to, the Housing and Planning Act 2016 (c. 22).
Section 4A(1) was inserted by section 202(1) of the Housing and Planning Act 2016 (c. 22).
Section 118 was amended by paragraphs 1 and 59 of Schedule 13, and Part 20 of Schedule 25, to the Localism Act 2011 (c. 20) and section 92(4) of the Criminal Justice and Courts Act 2015 (c. 2).
Section 11A was inserted by section 186(3) of the Housing and Planning Act 2016 (c. 22).
Section 5 was amended by Schedule 15 to the Housing and Planning Act 2016.
Section 5A was inserted by section 182(2) of the Housing and Planning Act 2016.
Section 5B(1) was inserted by section 202(2) of the Housing and Planning Act 2016.
Section 6 was amended by section 4 of, and paragraph 52(2) of Schedule 2 to, the Planning (Consequential Provisions) Act 1990 (c. 11) and paragraph 7 of Schedule 15 to the Housing and Planning Act 2016.
Section 134 was amended by section 142 of, and Part 21 of Schedule 25 to, the Localism Act 2011 and S.I. 2012/16.
Section 7(1) was substituted by paragraphs 1 and 3 of Schedule 18 to the Housing and Planning Act 2016.
Schedule A1 was inserted by paragraph 6 of Part 1 of Schedule 18 to the Housing and Planning Act 2016.
Subsection (4A) of section 153 was inserted by section 200(1) and (2) of the Housing and Planning Act 2016.
Section 13 was amended by sections 62(3) and 139 of, and paragraphs 27 and 28 of Schedule 13, and Part 3 of Schedule 23 to, the Tribunals, Courts and Enforcement Act 2007 (c. 15).
2003 c. 21. There are amendments to section 151 which are not relevant to this Order.
Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys