Traffic managementE+W
10.—(1) No part of the authorised development comprising the construction, alteration or improvement of the M25 or A12 is to commence until a traffic management plan for that part has been submitted to and approved in writing by the Secretary of State, following consultation by the undertaker with the relevant highway authority on matters related to its function.
(2) The traffic management plan prepared under sub-paragraph (1) must be in accordance with the Outline Traffic Management Plan and the relevant mitigation measures set out in the REAC.
(3) The authorised development must be constructed in accordance with the traffic management plan referred to in sub-paragraph (1).
Commencement Information
I1Sch. 2 para. 10 in force at 6.6.2022, see art. 1