Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
CostsE+W
72. The undertaker must pay to Transport for London in respect of the Works a sum equal to the whole of any costs and expenses which Transport for London reasonably incur in–E+W
(a)requests from the undertaker to participate in the design of any part of the authorised development, the examination or approval of design or construction information required for the Works including for the protection of the TLRN and for Work No. 29, and reaching agreement on the schedule of highway assets pursuant to paragraph 73;
(b)including the schedule of highway assets agreed pursuant to paragraph 73 within its road maintenance framework contracts;
(c)agreeing and operating a Detailed Local Operating Agreement;
(d)participation in road safety audits relating to the Works;
(e)inspecting the construction and completion of the Works including any remediation works;
(f)the issue of certificates relating to the Works required for the completion, hand over and defects;
(g)carrying out any surveys and testing which are reasonably required in connection with the construction of the Works; and
(h)the transfer or vesting in Transport for London of any land and rights acquired by the undertaker.