The Electricity and Gas (Energy Company Obligation) Order 2022

Further applications: standard alternative methodology measuresE+W+S

This adran has no associated Memorandwm Esboniadol

40.—(1) A participant may apply to the Administrator in writing for a measure which has been approved as a data light measure to be approved as a standard alternative methodology measure.

(2) An application under paragraph (1) must include the information and consent referred to in article 38(2).

(3) The Administrator may only approve the application if it is satisfied that the threshold in article 39(3) is met.

Commencement Information

I1Art. 40 in force at 27.7.2022, see art. 1(1)