The Hornsea Four Offshore Wind Farm Order 2023

Changes over time for: Paragraph 13

 Help about opening options

Alternative versions:

Status:

Point in time view as at 31/01/2024.

Changes to legislation:

There are currently no known outstanding effects for the The Hornsea Four Offshore Wind Farm Order 2023, Paragraph 13. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Pre-construction plans and documentationE+W+S

13.—(1) The licensed activities for each stage of construction of the authorised scheme must not commence until the following (insofar as relevant to that activity or stage of activity) has been submitted to and approved in writing by the MMO, in consultation with, where relevant, Trinity House, the MCA, UK Hydrographic Office and relevant SNCB—

(a)A design plan, prepared in accordance with the layout principles at a scale of between 1:25,000 and 1:50,000, or in such other format as may be appropriate, including detailed representation on the most suitably scaled chart, which shows for the relevant stage—

(i)the proposed location, including grid co-ordinates of the centre point of the proposed location for each wind turbine generator, and offshore accommodation platform within the relevant stage, subject to any micro-siting required due to anthropological constraints, environmental constraints or difficult ground conditions discovered post approval under this condition and choice of foundation types for all wind turbine generators and offshore accommodation platforms within the relevant stage;

(ii)the number, specifications and dimensions of the wind turbine generators to be installed within the relevant stage;

(iii)the length and arrangement of cable comprising Work No. 1(c) within the relevant stage;

(iv)the dimensions of all monopile foundations, mono suction bucket foundations, jacket foundations or gravity base structures (for the offshore accommodation platform only) within the relevant stage; and

(v)any exclusion zones or micro-siting requirements identified in any mitigation project pursuant to sub-paragraph 13(2)(d) or relating to any habitats of principal importance identified as part of surveys undertaken in accordance with condition 17;

to ensure conformity with the description of Work No. 1 and compliance with conditions 1, 2 and 3 above;

(b)a construction programme to include details for the relevant stage of—

(i)the proposed construction start date;

(ii)proposed timings for mobilisation of plant delivery of materials and installation works; and

(iii)an indicative written construction programme for all wind turbine generators, offshore accommodation platforms and cable comprised in the works at paragraph 2 to 3(b) of Part 1 (licensed marine activities) of this Schedule (insofar as not shown in paragraph (ii) above),

unless otherwise agreed in writing with the MMO;

(c)a construction method statement in accordance with the construction methods assessed in the environmental statement and including details for the relevant stage of—

(i)foundation installation methodology, including drilling methods and disposal of drill arisings and material extracted during seabed preparation for foundation and cable installation works and having regard to any mitigation scheme pursuant to sub-paragraph 13(1)(g);

(ii)advisory safe passing distances for vessels around construction sites;

(iii)cable (including fibre optic cable) installation;

(iv)contractors;

(v)vessels and vessels transit corridors;

(vi)codes of conduct for vessel operators;

(vii)associated ancillary works;

(viii)guard vessels to be employed;

(ix)details of means to address impacts on European sites, habitats of principal importance and any international or nationally designated sites, where relevant; and

(x)measures to ensure appropriate co-ordination with the Marine Helicopter Coordination Centre;

(d)a construction project environmental management and monitoring plan covering the period of construction for the relevant stage to include details of—

(i)a marine pollution contingency plan to address the risks, methods and procedures to deal with and report any spills and collision incidents of the authorised scheme in relation to all activities carried out;

(ii)a chemical risk review to include information regarding how and when chemicals are to be used, stored and transported in accordance with recognised best practice guidance;

(iii)a marine biosecurity plan detailing how the risk of introduction and spread of invasive non-native species will be minimised;

(iv)waste management and disposal arrangements;

(v)a vessel management plan, to determine vessel routing to and from construction sites and ports, to include a code of conduct for vessel operators; and

(vi)the appointment and responsibilities of a company fisheries liaison officer;

(e)a scour protection management plan for the relevant stage providing details of the need, type, sources, quantity and installation methods for scour protection, which must be updated and resubmitted in writing for approval if changes to it are proposed following cable laying operations;

(f)details for the relevant stage of proposed pre-construction monitoring surveys, construction monitoring, post-construction monitoring and related reporting in accordance with conditions 17, 18 and 19;

(g)in the event that driven or part-driven pile foundations are proposed to be used for the relevant stage, a piling marine mammal mitigation protocol for that stage, in accordance with the outline marine mammal mitigation protocol, the intention of which is to prevent injury to marine mammals, including details of soft start procedures with specified duration periods following current best practice as advised by the relevant statutory nature conservation bodies;

(h)a cable specification and installation plan for the relevant stage which accords with the principles of the outline cable specification and installation plan, to include—

(i)technical specification of offshore cables (including fibre optic cable) below MHWS within that stage, including a desk-based assessment of attenuation of electromagnetic field strengths, shielding and cable burial depth in accordance with good industry practice;

(ii)a detailed cable laying plan for the Order limits within that stage, incorporating a burial risk assessment encompassing the identification of any cable protection that exceeds 5% of navigable depth referenced to Chart Datum and, in the event that any area of cable protection exceeding 5% of navigable depth is identified, details of any steps (to be determined following consultation with the MCA and Trinity House) to be taken to ensure existing and future safe navigation is not compromised or similar such assessment to ascertain suitable burial depths and cable laying techniques, including cable protection;

(iii)proposals for the volume and areas of cable protection to be used for each cable crossing, and proposals for timing and methodology for reporting on actual volumes and areas post construction within that stage; and

(iv)proposals for monitoring offshore cables within that stage including cable protection during the operational lifetime of the authorised scheme which includes a risk based approach to the management of unburied or shallow buried cables;

(i)an aids to navigation management plan for that stage to be agreed in writing by the MMO following consultation with Trinity House, to include details of how the undertaker will comply with the provisions of condition 8 relating to that stage for the lifetime of the authorised scheme;

(j)an ornithological monitoring plan for the relevant stage which accords with the principles set out in the outline ornithological monitoring plan setting out the circumstances in which ornithological monitoring will be required and the monitoring to be carried out in such circumstances.

(2) Subject to condition 13(3), the licensed activities or any relevant stage of those activities must not commence unless no later than six months prior to the commencement of the relevant stage a marine written scheme of archaeological investigation for the stage in construction has been submitted to and approved by the MMO in writing, in accordance with the outline marine written scheme of investigation, and in accordance with industry good practice, in consultation with the statutory historic body to include—

(a)details of responsibilities of the undertaker, archaeological consultant and contractor;

(b)a method statement for further site investigation including any specifications for geophysical, geotechnical and diver or remotely operated vehicle investigations;

(c)archaeological analysis of survey data, and timetable for reporting, which is to be submitted to the MMO within six months of any survey being completed;

(d)delivery of any mitigation including, where necessary, identification and modification of archaeological exclusion zones prior to construction;

(e)monitoring of archaeological exclusion zones during and post construction, including provision of a report on such monitoring;

(f)a requirement for the undertaker to ensure that a copy of any agreed archaeological report is deposited with the National Record of the Historic Environment, by submitting a Historic England OASIS (‘online access to the index of archaeological investigations’) form with a digital copy of the report within six months of completion of construction of the authorised scheme, and to notify the MMO that the OASIS form has been submitted to the National Record of the Historic Environment within two weeks of submission;

(g)a reporting and recording protocol, designed in reference to the Offshore Renewables Protocol for Reporting Archaeological Discoveries as set out by the Crown Estate and reporting of any wreck or wreck material during construction, operation and decommissioning of the authorised scheme; and

(h)a timetable for all further site investigations, which must allow sufficient opportunity to establish a full understanding of the historic environment within the offshore Order limits and the approval of any necessary mitigation required as a result of the further site investigations prior to commencement of licensed activities.

(3) Pre-construction archaeological investigations and pre-commencement material operations which involve intrusive seabed works must only take place in accordance with a written scheme of investigation specific to the relevant pre-construction activities (which must accord with the details set out in the outline marine written scheme of investigation) which has been submitted to and approved by the MMO in consultation with the statutory historic body.

(4) In the event that driven or part-driven pile foundations are proposed to be used, the hammer energy used to drive or part-drive monopile foundations must not exceed 5,000kJ and the hammer energy used to drive or part-drive pin pile foundations must not exceed 3,000kJ.

(5) No more than two vessels may be engaged at any time in activities related to piling for the licenced activities. There will only be a maximum installation of two piled foundations within a 24-hour period. It is possible for installation of the two piled foundations to occur concurrently i.e. within a 24-hour period at up to two locations within the area of Work No. 3(a) or up to two locations within the array. The two piled foundation locations may also be piled simultaneously.

(6) The licensed activities or any part of those activities must not commence until a fisheries coexistence and liaison plan in accordance with the outline fisheries coexistence and liaison plan has been submitted to and approved by the MMO in writing.

(7) The undertaker must, before submitting any pre-construction plans and documentation required under this condition, provide a copy of the plans and documentation to any other undertaker to whom part of the benefit of this Order has been transferred or leased pursuant to article 5 (benefit of the order) of the Order.

(8) The undertaker to whom part of the benefit of the Order has been transferred or leased pursuant to article 5 (benefit of the order) must provide any comments on the plans and documentation to the undertaker within 14 days of receipt.

(9) The undertaker and any other undertaker must participate in liaison meetings as requested from time to time by the MMO in writing in advance and must consider such matters as are determined by the MMO relating to the efficient operation of a deemed marine licence issued under this Order (including as varied or transferred).

Commencement Information

I1Sch. 11 para. 13 in force at 3.8.2023, see art. 1

Yn ôl i’r brig

Options/Cymorth

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open yr Offeryn Cyfan

Yr Offeryn Cyfan you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

Y Rhestrau you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill