The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023

Status:

Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol).

Change control applications: decisions

This adran has no associated Memorandwm Esboniadol

24.—(1) The regulator must grant the building control approval sought in a change control application unless the application or any document that accompanied the application—

(a)does not comply with the requirements of regulation 21 (change control applications) or any direction relating to the application or the document given by the regulator under regulation 59 (electronic submission and directions);

(b)is not sufficiently detailed in any respect to allow the regulator to determine whether the HRB work, the stage of HRB work or work to existing HRB would contravene any applicable requirement of the building regulations;

(c)shows the HRB work, the stage of HRB work or work to existing HRB would contravene any applicable requirement of the building regulations;

(d)shows the strategies, policies or procedures in any agreed document (including in relation to controlled changes, mandatory occurrence reporting, competence of persons or sharing of information and co-operation) would contravene, or would be likely to contravene, the requirements of—

(i)regulations 18 to 21 and 26 to 29 (changes to documents or persons);

(ii)regulations 31, 38 and 39 (golden thread etc);

(iii)regulations 32 to 37 (mandatory occurrence reporting);

(iv)Part 2A (dutyholders and competence) of the 2010 Regulations.

(2) If one or more of the reasons in paragraph (1) applies, the regulator may—

(a)reject the change control application, or

(b)with the written consent of the applicant, grant the building control approval sought in the application subject to one or more requirements.

(3) The types of requirement that may be imposed under paragraph (2)(b) include—

(a)a requirement to provide a specified plan or document, or a revised version of a specified plan or document, within a specified period;

(b)a requirement that work does not proceed beyond a specified point until a specified plan or other document, or a revised version of a specified plan or other document, has been given to, and approved by, the regulator.

(4) The regulator must notify the applicant of the outcome of the change control application (and where the applicant is not the client, also give a copy of the notification to the client) within the period referred to in regulation 22 (change control applications: validity and time limit).

(5) A notice that the application has been rejected must give the reasons for rejection.

(6) A notice that the building control approval sought in the change control application has been granted subject to a requirement must specify the requirement imposed.

(7) If requested by the applicant, the regulator must provide a paper copy of the notice of building control approval.

(8) Where a change control application is successful the effect is that from the date of the notice under paragraph (4)—

(a)building control approval for the HRB work, the stage of HRB work or work to existing HRB is granted;

(b)subject to paragraphs (9) and (10)—

(i)the description of the proposed controlled change, and

(ii)the revised version of the agreed document that accompanied the application,

are approved.

(9) Where building control approval has been granted subject to a requirement that a plan or document must be revised, the unrevised plan or document is not approved by paragraph (8)(b).

(10) Where—

(a)building control approval has been granted subject to a requirement that a plan or document must be revised, and

(b)the plan or document is revised in accordance with the requirement,

paragraph (8)(b) applies in relation to the revised plan or document.

(11) Where building control approval has been granted subject to a requirement of a type described in paragraph (3)(b)—

(a)the client must ensure the work does not proceed beyond the point specified in the requirement until approval by the regulator to the plan or document has been received;

(b)where a request for approval has been received by the regulator it must notify the client of the outcome of the request within 6 weeks beginning with the date the request is received by the regulator or within such longer period as at any time the regulator and the client agree in writing;

(c)a notice that the request has been rejected must give the reasons for rejection, and

(d)if requested by the client, the regulator must provide a paper copy of the approval.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Asesiadau Effaith

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill