Change control: regulator power to specify notifiable changes and major changesE+W
This
adran has no associated
Memorandwm Esboniadol
25. The regulator may specify that a particular type of controlled change is a notifiable change or a major change, in relation to specified work, by giving notice in writing to that effect to the client, principal contractor (or sole contractor) and the principal designer (or sole or lead designer) for that work.