Chwilio Deddfwriaeth

The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023

Changes over time for: Section 7

 Help about opening options

Alternative versions:

Status:

Point in time view as at 01/10/2023.

Changes to legislation:

There are currently no known outstanding effects for the The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, Section 7. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Building control approval applications for HRB work or stage of HRB work: decisionsE+W

This adran has no associated Memorandwm Esboniadol

7.—(1) The regulator must grant the building control approval sought in a building control approval application for HRB work or a building control approval application for a stage of HRB work unless the application or any document that accompanied the application—

(a)does not comply with the requirements of regulation 4 (building control approval applications for HRB work or stage of HRB work) or any direction relating to the application or the document given by the regulator under regulation 59 (electronic submission and directions);

(b)is not sufficiently detailed in any respect to allow the regulator to determine whether the HRB work or the stage of HRB work would contravene any applicable requirement of the building regulations;

(c)shows the HRB work or the stage of HRB work would contravene any applicable requirement of the building regulations;

(d)shows the strategies, policies or procedures in relation to the HRB work or the stage of HRB work (including in relation to controlled changes, mandatory occurrence reporting, competence of persons or sharing of information and co-operation) would contravene, or would be likely to contravene, the requirements of—

(i)regulations 18 to 21 and 26 to 29 (changes to documents or persons);

(ii)regulations 31, 38 and 39 (golden thread etc);

(iii)regulations 32 to 37 (mandatory occurrence reporting);

(iv)Part 2A (dutyholders and competence) of the 2010 Regulations.

(2) If one or more of the reasons in paragraph (1) applies, the regulator may—

(a)reject the building control approval application for HRB work or the building control approval application for a stage of HRB work, or

(b)with the written consent of the applicant, grant the building control approval sought in the application subject to one or more requirements.

(3) The types of requirement that may be imposed under paragraph (2)(b) include—

(a)a requirement to provide a specified plan or document, or a revised version of a specified plan or document, within a specified period;

(b)a requirement that work does not proceed beyond a specified point until a specified plan or other document, or a revised version of a specified plan or other document, has been given to, and approved by, the regulator.

(4) The regulator must notify the applicant of the outcome of the application (and where the applicant is not the client, also give a copy of the notification to the client) within the period referred to in regulation 5 (building control approval applications for HRB work or stage of HRB work: validity and time limit).

(5) A notice that the application has been rejected must give the reasons for rejection.

(6) A notice that the building control approval sought in the application has been granted subject to a requirement must specify the requirement imposed.

(7) If requested by the applicant, the regulator must provide a paper copy of the notice of building control approval.

(8) Where a building control approval application for HRB work or a building control approval application for a stage of HRB work is successful the effect is that from the date of the notice under paragraph (4)—

(a)building control approval for the HRB work or, as the case may be, building control approval for the stage of HRB work is granted;

(b)subject to paragraphs (9) and (10)—

(i)the description of the proposed HRB work or, as the case may be, the description of the proposed stage of HRB work,

(ii)the plans of the HRB work or, as the case may be, the plans of the stage of HRB work that accompanied the application, and

(iii)each of the other documents that accompanied the application,

are approved.

(9) Where building control approval has been granted subject to a requirement that a plan or document must be revised, the unrevised plan or document is not approved by paragraph (8)(b).

(10) Where—

(a)building control approval has been granted subject to a requirement that any plan or document must be revised, and

(b)the plan or document is subsequently revised in accordance with the requirement,

then that revised plan or document is approved from the date specified in the approval given by the regulator for the revision.

(11) Where building control approval has been granted subject to a requirement of a type described in paragraph (3)(a), the client must ensure that work does not start before the plan or document is provided.

(12) Where building control approval has been granted subject to a requirement of a type described in paragraph (3)(b)—

(a)the requirement must set out the points specified in relation to the work and the plans or documents which must be approved for each point;

(b)the client must ensure work to which the requirement relates does not proceed beyond the point specified in the requirement until the approval by the regulator in relation to that plan or document has been received.

(13) If requested by the client, the regulator must provide a paper copy of the approval referred to in paragraph (12)(b).

(14) Where the regulator decides not to approve a plan or document under paragraph (12) if requested the regulator must give the reasons for the decision.

Commencement Information

I1Reg. 7 in force at 1.10.2023, see reg. 1(1)

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Memorandwm Esboniadol

Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Asesiadau Effaith

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill