- Y Diweddaraf sydd Ar Gael (Diwygiedig)
- Gwreiddiol (a wnaed Fel)
There are currently no known outstanding effects for the The Building (Higher-Risk Buildings Procedures) (England) Regulations 2023, Paragraph 4.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
4.—(1) This paragraph applies where—
(a)the initial notice for the work, or the part of that notice which relates to the higher-risk building, ceases to be in force by virtue of any provision of Part 2 of the 1984 Act (except section 52(5)) on a date before 6th April 2024 (“the cancellation date”), and
(b)a notice under paragraph 1(4) (notice that work had sufficiently progressed) in relation to that work was not received by a local authority before the cancellation date.
(2) Where this paragraph applies—
(a)if a plans certificate or final certificate relating to the work (or any part of the work) has been accepted before the cancellation date then with effect from that date the certificate ceases to have effect;
(b)accordingly Parts 2 to 6 of these Regulations apply to the work from the cancellation date with the modifications provided for in paragraph (8);
(c)subject to paragraph (d), the 2010 Regulations, to the extent they apply to higher-risk buildings, apply to any of the work from the cancellation date;
(d)regulation 11(3) of the 2010 Regulations does not apply and accordingly the regulator may exercise the power in section 8(3A) of the 1984 Act(1) to dispense with or relax any requirement of the 2010 Regulations.
(3) Where this paragraph applies then with effect from the cancellation date the regulator, and not the local authority for the area, is the building control authority in relation to the higher-risk building and accordingly the duties and functions of the regulator under section 91 of the 1984 Act apply in relation to the work to the higher-risk building (but not in relation to any other work specified in the initial notice).
(4) Where this paragraph applies, not more than five working days after the cancellation date the person which was shown on the initial notice as the approved inspector must—
(a)give a notice to the person intending to carry out the work explaining the initial notice, or such part of the initial notice which applies to the higher-risk building, is no longer in force and the effect of sub-paragraphs (2), (3) and (5), and
(b)give a copy of the notice to the local authority.
(5) Within 10 working days of the cancellation date the person intending to carry out the work must give a notice to the regulator setting out—
(a)their name, address, telephone number and (if available) email address;
(b)the location of the building;
(c)details of the work to be carried out;
(d)the height of the higher-risk building as determined in accordance with regulation 5 of the Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023;
(e)the number of storeys in the higher-risk building as determined in accordance with regulation 6 of the Higher-Risk Buildings (Descriptions and Supplementary Provisions) Regulations 2023, and
(f)a description of any work which was carried out before the cancellation date (including details of the work in relation to which a final certificate was given and not rejected) and details of any inspections undertaken by the approved inspector in relation to that work.
(6) With effect from the cancellation date no further building work in relation to the work described in the initial notice (“HRB project”) may be carried out until the date when the person intending to carry out building work has received confirmation in writing from the regulator that an application for building control approval made to the regulator in relation to that work is valid (“validation date”).
(7) Where any building work was carried out before the cancellation date then—
(a)the person who carried out the work or the owner must comply with any notice from the regulator requiring them within a reasonable time to cut into, lay open or pull down so much of the work as prevents the regulator from ascertaining whether the work contravenes any requirement of the building regulations;
(b)in addition to the other documents which are required to accompany the application for building control approval, the person must provide the regulator with such plans as are necessary to show the work already carried out complies with all applicable requirements of the building regulations.
(8) Where the application for building control approval in relation to the HRB project is rejected by the regulator then with effect from the date the rejection is notified to the applicant (“rejection date”) no further building work in relation to the HRB project may be carried out until a building control approval is granted in relation to the building.
(9) Parts 2 to 6 of these Regulations have effect in relation to the HRB project—
(a)from the cancellation date as if—
(i)regulation 5(1)(b) (building control applications: for HRB work or stage of HRB work: validity and time limit) and regulation 13(1)(b) (building control applications: for work to existing HRB: validity and time limit) were omitted;
(ii)in relation to any change control which is proposed or occurs between the cancellation date and the date application for building control approval is determined by the regulator, Part 3 (change control) required the change to be recordable in the change control log;
(iii)regulation 47 (regularisation) does not apply in relation to any work carried out before the cancellation date and accordingly any reference to a regularisation certificate in Parts 2 to 6 of these Regulations in relation to such work is to be ignored;
(iv)regulations 50 to 56 (section 30A applications) did not apply in relation to the application for building control approval for the HRB project, and
(b)additionally, from the validation date until the rejection date, as if regulation 3 did not prevent work in the HRB project to be started before an application for building control approval for the work is submitted.
Commencement Information
I1Sch. 3 para. 4 in force at 1.10.2023, see reg. 1(1)
Subsection (3A) was inserted by paragraph 11(4) of Schedule 5 to the Building Safety Act 2022 (c. 30).
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Mae Memoranda Esboniadol yn nodi datganiad byr o ddiben Offeryn Statudol ac yn rhoi gwybodaeth am ei amcan polisi a goblygiadau polisi. Maent yn ceisio gwneud yr Offeryn Statudol yn hygyrch i ddarllenwyr nad oes ganddynt gymhwyster cyfreithiol, ac maent yn cyd-fynd ag unrhyw Offeryn Statudol neu Offeryn Statudol Drafft a gyflwynwyd ger bron y Senedd o Fehefin 2004 ymlaen.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys