The Associated British Ports (Immingham Eastern Ro-Ro Terminal) Development Consent Order 2024

Emergency circumstances

41.—(1) The undertaker acknowledges that the IOT Operators provides services to His Majesty’s Government, using its apparatus, which may affect any works to be carried under this Order.

(2) In the following circumstances, the IOT Operators may on written notice to the undertaker require the immediate suspension of works to construct the authorised development if such works necessitate the stopping or suspending of the supply of product through any apparatus and the IOT Operators shall not be in breach of its obligations under this protective provision in circumstances—

(a)in which, in the determination of the Secretary of State, there subsists a material threat to national security, or a threat or state of hostility or war or other crisis or national emergency (whether or not involving hostility or war); or

(b)in which a request has been received, and a decision to act upon such request has been taken, by His Majesty’s Government for assistance in relation to the occurrence or anticipated occurrence of a major accident, crisis or natural disaster; or

(c)in which a request has been received from or on behalf of NATO, the EU, the UN, the International Energy Agency (or any successor agency thereof) or the government of any other state for support or assistance pursuant to the United Kingdom’s international obligations and a decision to act upon such request has been taken by His Majesty’s Government or the Secretary of State; or

(d)identified by the COBRA committee of His Majesty’s Government (or any successor committee thereof) as identified as falling within any of the above sub-paragraphs of this paragraph; or

(e)where the United Kingdom is engaged in any planned or unplanned military operations within the United Kingdom or overseas, in connection with which the Secretary of State requires fuel capacity.

(3) The parties agree to act in good faith and in all reasonableness to agree any revisions to any schedule, programme or costs estimate (which shall include costs of demobilising and remobilising any workforce, and any costs to protect the IOT Operators’ apparatus “mid-works”) to account for the suspension.

(4) The IOT Operators shall not be liable for any costs, expenses, losses or liabilities the undertaker incurs as a result of the suspension of any activities under this paragraph or delays caused by it.