234.—(1) The undertaker must not, in reliance on or in exercise of any power under this Order, interfere with, remove, damage or prevent or impair the functioning of, and must on reasonable request (or in case of emergency, on demand) allow access by National Highways to, the highway drainage assets located in plots 2-14, 4-20, 5-01, 5-02, 5-03, 5-04, 5-10, 5-12, 5-14, 5-15, 5-20, 5-22, 5-23, 6-02, 6-03, 6-04, 6-05, 6-06,

(2) The undertaker must not, in reliance on or in exercise of any power under this Order, interfere with, remove or prevent access by National Highways in pursuance of any right held over plots 2-03, 2-14 and 5-05.

(3) The undertake must not, in reliance on or in exercise of any power under this Order, acquire, extinguish or remove any right National Highways holds for the purposes of its undertaking in any of the plots listed in sub-paragraphs (1) and (2) and plot 9-04.

Commencement Information

I1Sch. 10 para. 234 in force at 11.4.2024, see art. 1(2)