Article 34
(1) Plot Reference Number shown on land plans | (2) Purpose for which temporary possession may be taken | (3) Relevant part of the authorised development |
---|---|---|
Land Plans – Sheet 4 | ||
4/1a | Land required temporarily for temporary traffic management purposes. | Ancillary works |
4/1b | Required to facilitate and provide a working space and temporary access for works associated with the diversion of power cables. | Work No. 35 |
4/1c | Required to facilitate and provide a working space and temporary access for works associated with the construction of a new bridleway and associated drainage and landscaping features to connect Long Walk and Easton Lane. | Work No. 9 |
4/1d | Land required temporarily for temporary traffic management purposes. | Ancillary works |
4/2a | Required to facilitate and provide a working space and temporary access for works associated with the diversion of 50 metres in length of power cables. | Work No. 35 |
4/2b | Required to facilitate and provide a working space and temporary access for works associated with the diversion of power cables. | Work No. 35 |
4/2c | Land required temporarily for temporary traffic management purposes. | Ancillary works |
Land Plans – Sheet 5 | ||
5/5a | Requirement to facilitate and provide a working space and temporary access for works associated with the construction of a drainage outfall into the River Itchen. | Work No. 43 |
5/2d | Land required temporarily for temporary traffic management purposes. | Ancillary Works |
5/2e | Required to facilitate and provide a working space and temporary access for works associated with: 1. the improvement and construction of the realignment of the northbound and southbound carriageways of the A33 between B3047 (London Road) / A33 junction and proposed A33 / M3 northbound onslip roundabout; 1(g). the construction of the extension of the existing central reserve with associated vehicle restraint system; 1(h). the construction of carriageway realignment on the existing River Itchen bridge (including possible remediation works); 3. the construction improvements and realignment of the southbound carriageway of the A34; 42. the construction of a drainage outfall into the River Itchen. | Work No. 1, 1(g), 1(h), 3, 42 |
5/3c | Required temporarily to facilitate construction generally and to facilitate and provide a working space and temporary access for works associated with the construction of a new bridleway and associated drainage and landscaping features to connect Long Walk to Easton Lane. | Work No. 9 |
5/4 | Required temporarily to facilitate construction of surface water drainage outfall. | Work No. 42 |
Land Plans – Sheet 6 | ||
6/1f | Required to facilitate and provide a working space and temporary access for works associated with: 9. the construction of a new bridleway and associated drainage and landscaping features to connect Long Walk and Easton Lane; 9(a). the construction of an attenuation basin maintenance track; 20. the diversion of a low-pressure gas main pipeline; 26. the diversion of telecommunication equipment; 33. the realignment of the National Cycle Route 23 and associated earthworks and landscaping. | Work No. 9, 9(a), 20, 26, 33 |
6/1g | Required to construct a temporary construction site compound. | Work No. 38 |
6/4d | Required to facilitate and provide a working space and temporary access for works associated with the construction of a new bridleway and associated drainage and landscaping features to connect Long Walk to Easton Lane. | Work No. 9 |
6/6a | Required to facilitate and provide a working space and temporary access for works associated with the diversion of a low-pressure gas main pipeline. | Work No. 20 |
6/6b | Required to facilitate and provide a working space and temporary access for works associated with: 20. the diversion of a low-pressure gas main pipeline; 38: the construction of a temporary construction site compound situated on land to the east of the M3 Junction 9 gyratory. | Work Nos. 20, 38 |
Land Plans – Sheet 7 | ||
7/1a | Required to facilitate and provide a working space and temporary access for works associated with the construction of a temporary construction site compound situated on land to the east of the M3 Junction 9 gyratory. | Work No. 38 |
7/2c | Land required temporarily for temporary traffic management purposes. | Ancillary works |
7/4g | Land required temporarily for temporary traffic management purposes. | Ancillary works |
7/5 | Land required temporarily for temporary traffic management purposes. | Ancillary works |
7/6 | Land required temporarily for temporary traffic management purposes | Ancillary works |
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys