Compulsory acquisition of landE+W

20.—(1) The undertaker may—

(a)acquire compulsorily so much of the Order land as is required for the authorised development or to facilitate, or as is incidental, to it; and

(b)use any land so acquired for the purpose authorised by this Order or for any other purposes in connection with or ancillary to the authorised development.

(2) This article is subject to article 21 (time limit for exercise of authority to acquire land compulsorily), paragraph (2) of article 22 (compulsory acquisition of rights), article 29 (temporary use of land for constructing the authorised development) and article 31 (statutory undertakers).

Commencement Information

I1Art. 20 in force at 27.9.2024, see art. 1