Chwilio Deddfwriaeth

The Service Charges (Consultation Requirements) (Wales) Regulations 2004

 Help about what version

Pa Fersiwn

 Help about advanced features

Nodweddion Uwch

Changes over time for: SCHEDULE 4

 Help about opening options

Alternative versions:

Changes to legislation:

There are currently no known outstanding effects for the The Service Charges (Consultation Requirements) (Wales) Regulations 2004, SCHEDULE 4. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Regulation 7(4)

SCHEDULE 4E+WCONSULTATION REQUIREMENTS FOR QUALIFYING WORKS OTHER THAN WORKS UNDER QUALIFYING LONG TERM AGREEMENT OR AGREEMENTS TO WHICH REGULATION 7(3) APPLIES

PART 1E+WCONSULTATION REQUIREMENTS FOR QUALIFYING WORKS FOR WHICH PUBLIC NOTICE IS REQUIRED

Notice of intentionE+W

1.—(1) The landlord shall give notice in writing of intention to carry out qualifying works—E+W

(a)to each tenant; and

(b)where a recognised tenants' association represents some or all of the tenants, to the association.

(2) The notice shall—

(a)describe, in general terms, the works proposed to be carried out or specify the place and hours at which a description of the proposed works may be inspected;

(b)state the landlord’s reasons for considering it necessary to carry out the proposed works;

(c)state that the reason why the landlord is not inviting recipients of the notice to nominate persons from whom the landlord should try to obtain an estimate for carrying out the works is that public notice of the works is to be given;

(d)invite the making, in writing, of observations in relation to the proposed works; and

(e)specify—

(i)the address to which such observations may be sent;

(ii)that they must be delivered within the relevant period; and

(iii)the date on which the relevant period ends.

Commencement Information

I1Sch. 4 Pt. 1 para. 1 in force at 31.3.2004, see reg. 1(1)

Inspection of description of proposed worksE+W

2.—(1) Where a notice under paragraph 1 specifies a place and hours for inspection—E+W

(a)the place and hours so specified must be reasonable; and

(b)a description of the proposed works must be available for inspection, free of charge, at that place and during those hours.

(2) If facilities to enable copies to be taken are not made available at the times at which the description may be inspected, the landlord shall provide to any tenant, on request and free of charge, a copy of the description.

Commencement Information

I2Sch. 4 Pt. 1 para. 2 in force at 31.3.2004, see reg. 1(1)

Duty to have regard to observations in relation to proposed worksE+W

3.  Where, within the relevant period, observations are made in relation to the proposed works by any tenant or the recognised tenants' association, the landlord shall have regard to those observations.E+W

Commencement Information

I3Sch. 4 Pt. 1 para. 3 in force at 31.3.2004, see reg. 1(1)

Preparation of landlord’s contract statementE+W

4.—(1) The landlord shall prepare, in accordance with the following provisions of this paragraph, a statement in respect of the proposed contract under which the proposed works are to be carried out.E+W

(2) The statement shall set out—

(a)the name and address of the person with whom the landlord proposes to contract; and

(b)particulars of any connection between them (apart from the proposed contract).

(3) For the purpose of sub-paragraph (2)(b) it shall be assumed that there is a connection between a person and the landlord—

(a)where the landlord is a company, if the person is, or is to be, a director or manager of the company or is a close relative of any such director or manager;

(b)where the landlord is a company, and the person is a partner in a partnership, if any partner in that partnership is, or is to be, a director or manager of the company or is a close relative of any such director or manager;

(c)where both the landlord and the person are companies, if any director or manager of one company is, or is to be, a director or manager of the other company;

(d)where the person is a company, if the landlord is a director or manager of the company or is a close relative of any such director or manager; or

(e)where the person is a company and the landlord is a partner in a partnership, if any partner in that partnership is a director or manager of the company or is a close relative of any such director or manager.

(4) Where, as regards each tenant’s unit of occupation, it is reasonably practicable for the landlord to estimate the amount of the relevant contribution to be incurred by the tenant attributable to the works to which the proposed contract relates, that estimated amount shall be specified in the statement.

(5) Where—

(a)it is not reasonably practicable for the landlord to make the estimate mentioned in sub-paragraph (4); and

(b)it is reasonably practicable for the landlord to estimate, as regards the building or other premises to which the proposed contract relates, the total amount of the landlord’s expenditure under the proposed contract,

that estimated amount shall be specified in the statement.

(6) Where—

(a)it is not reasonably practicable for the landlord to make the estimate mentioned in sub-paragraph (4) or (5)(b); and

(b)it is reasonably practicable for the landlord to ascertain the current unit cost or hourly or daily rate applicable to the works to which the proposed contract relates,

that cost or rate shall be specified in the statement.

(7) Where it is not reasonably practicable for the landlord to make the estimate mentioned in sub-paragraph (6)(b), the reasons for being unable to comply and the date by which the landlord expects to be able to provide an estimated amount, cost or rate shall be specified in the statement.

(8) Where observations are made to which (in accordance with paragraph 3) the landlord is required to have regard, the statement shall summarise the observations and set out the landlord’s response to them.

Commencement Information

I4Sch. 4 Pt. 1 para. 4 in force at 31.3.2004, see reg. 1(1)

Notification of proposed contractE+W

5.—(1) The landlord shall give notice in writing of intention to enter into the proposed contract—E+W

(a)to each tenant; and

(b)where a recognised tenants' association represents some or all of the tenants, to the association.

(2) The notice shall—

(a)comprise, or be accompanied by, the statement prepared in accordance with paragraph 4 (“the paragraph 4 statement”) or specify the place and hours at which that statement may be inspected;

(b)invite the making, in writing, of observations in relation to any matter mentioned in the paragraph 4 statement;

(c)specify—

(i)the address to which such observations may be sent;

(ii)that they must be delivered within the relevant period; and

(iii)the date on which the relevant period ends.

(3) Where the paragraph 4 statement is made available for inspection, paragraph 2 shall apply in relation to that statement as it applies in relation to a description of proposed works made available for inspection under that paragraph.

Commencement Information

I5Sch. 4 Pt. 1 para. 5 in force at 31.3.2004, see reg. 1(1)

Landlord’s response to observationsE+W

6.  Where observations are made in response to the invitation in the notice under paragraph 5, the landlord shall, within 21 days of their receipt, by notice in writing to the person by whom the observations were made, state the landlord’s response to the observations.E+W

Commencement Information

I6Sch. 4 Pt. 1 para. 6 in force at 31.3.2004, see reg. 1(1)

Supplementary informationE+W

7.  Where a statement prepared under paragraph 4(7) specifies the landlord’s reasons for being unable to comply with sub-paragraph (6) of that paragraph, the landlord shall, within 21 days of receiving sufficient information to enable the landlord to estimate the amount, cost or rate referred to in sub-paragraph (4), (5) or (6) of that paragraph, give notice in writing of the estimated amount, cost or rate (as the case may be)—E+W

(a)to each tenant; and

(b)where a recognised tenants' association represents some or all of the tenants, to the association.

PART 2E+WCONSULTATION REQUIREMENTS FOR QUALIFYING WORKS FOR WHICH PUBLIC NOTICE IS NOT REQUIRED

Notice of intentionE+W

1.—(1) The landlord shall give notice in writing of intention to carry out qualifying works—E+W

(a)to each tenant; and

(b)where a recognised tenants' association represents some or all of the tenants, to the association.

(2) The notice shall—

(a)describe, in general terms, the works proposed to be carried out or specify the place and hours at which a description of the proposed works may be inspected;

(b)state the landlord’s reasons for considering it necessary to carry out the proposed works;

(c)invite the making, in writing, of observations in relation to the proposed works; and

(d)specify—

(i)the address to which such observations may be sent;

(ii)that they must be delivered within the relevant period; and

(iii)the date on which the relevant period ends.

(3) The notice shall also invite each tenant and the association (if any) to propose, within the relevant period, the name of a person from whom the landlord should try to obtain an estimate for the carrying out of the proposed works.

Commencement Information

I7Sch. 4 Pt. 2 para. 1 in force at 31.3.2004, see reg. 1(1)

Inspection of description of proposed worksE+W

2.—(1) Where a notice under paragraph 1 specifies a place and hours for inspection—E+W

(a)the place and hours so specified must be reasonable; and

(b)a description of the proposed works must be available for inspection, free of charge, at that place and during those hours.

(2) If facilities to enable copies to be taken are not made available at the times at which the description may be inspected, the landlord shall provide to any tenant, on request and free of charge, a copy of the description.

Commencement Information

I8Sch. 4 Pt. 2 para. 2 in force at 31.3.2004, see reg. 1(1)

Duty to have regard to observations in relation to proposed worksE+W

3.  Where, within the relevant period, observations are made in relation to the proposed works by any tenant or recognised tenants' association, the landlord shall have regard to those observations.E+W

Commencement Information

I9Sch. 4 Pt. 2 para. 3 in force at 31.3.2004, see reg. 1(1)

Estimates and response to observationsE+W

4.—(1) Where, within the relevant period, a nomination is made by a recognised tenants' association (whether or not a nomination is made by any tenant), the landlord shall try to obtain an estimate from the nominated person.E+W

(2) Where, within the relevant period, a nomination is made by only one of the tenants (whether or not a nomination is made by a recognised tenants' association), the landlord shall try to obtain an estimate from the nominated person.

(3) Where, within the relevant period, a single nomination is made by more than one tenant (whether or not a nomination is made by a recognised tenants' association), the landlord shall try to obtain an estimate—

(a)from the person who received the most nominations; or

(b)if there is no such person, but two (or more) persons received the same number of nominations, being a number in excess of the nominations received by any other person, from one of those two (or more) persons; or

(c)in any other case, from any nominated person.

(4) Where, within the relevant period, more than one nomination is made by any tenant and more than one nomination is made by a recognised tenants' association, the landlord shall try to obtain an estimate—

(a)from at least one person nominated by a tenant; and

(b)from at least one person nominated by the association, other than a person from whom an estimate is sought as mentioned in paragraph (a).

(5) The landlord shall, in accordance with this sub-paragraph and sub-paragraphs (6) to (9)—

(a)obtain estimates for the carrying out of the proposed works;

(b)supply, free of charge, a statement (“the paragraph (b) statement”) setting out—

(i)as regards at least two of the estimates, the amount specified in the estimate as the estimated cost of the proposed works; and

(ii)a summary of any observations made in accordance with paragraph 3 and the landlord’s response to them; and

(c)make all of the estimates available for inspection.

(6) At least one of the estimates must be that of a person wholly unconnected with the landlord.

(7) For the purpose of paragraph (6), it shall be assumed that there is a connection between a person and the landlord—

(a)where the landlord is a company, if the person is, or is to be, a director or manager of the company or is a close relative of any such director or manager;

(b)where the landlord is a company, and the person is a partner in a partnership, if any partner in that partnership is, or is to be, a director or manager of the company or is a close relative of any such director or manager;

(c)where both the landlord and the person are companies, if any director or manager of one company is, or is to be, a director or manager of the other company;

(d)where the person is a company, if the landlord is a director or manager of the company or is a close relative of any such director or manager; or

(e)where the person is a company and the landlord is a partner in a partnership, if any partner in that partnership is a director or manager of the company or is a close relative of any such director or manager.

(8) Where the landlord has obtained an estimate from a nominated person, that estimate must be one of those to which the paragraph (b) statement relates.

(9) The paragraph (b) statement shall be supplied to, and the estimates made available for inspection by—

(a)each tenant; and

(b)the secretary of the recognised tenants' association (if any).

(10) The landlord shall, by notice in writing to each tenant and the association (if any)—

(a)specify the place and hours at which the estimates may be inspected;

(b)invite the making, in writing, of observations in relation to those estimates;

(c)specify—

(i)the address to which such observations may be sent;

(ii)that they must be delivered within the relevant period; and

(iii)the date on which the relevant period ends.

(11) Paragraph 2 shall apply to estimates made available for inspection under this paragraph as it applies to a description of proposed works made available for inspection under that paragraph.

Commencement Information

I10Sch. 4 Pt. 2 para. 4 in force at 31.3.2004, see reg. 1(1)

Duty to have regard to observations in relation to estimatesE+W

5.  Where, within the relevant period, observations are made in relation to the estimates by any tenant or recognised tenants' association, the landlord shall have regard to those observations.E+W

Commencement Information

I11Sch. 4 Pt. 2 para. 5 in force at 31.3.2004, see reg. 1(1)

Duty on entering into contractE+W

6.—(1) Subject to sub-paragraph (2), where the landlord enters into a contract for the carrying out of qualifying works, the landlord shall, within 21 days of entering into the contract, by notice in writing to each tenant and the recognised tenants' association (if any)—E+W

(a)state reasons for awarding the contract or specify the place and hours at which a statement of those reasons may be inspected; and

(b)where observations are made to which (in accordance with paragraph 5) the landlord was required to have regard, summarise the observations and set out the landlord’s response to them.

(2) The requirements of sub-paragraph (1) do not apply where the person with whom the contract is made is a nominated person or submitted the lowest estimate.

  • Paragraph 2 shall apply to a statement made available for inspection under this paragraph as it applies to a description of proposed works made available for inspection under that paragraph.

Commencement Information

I12Sch. 4 Pt. 2 para. 6 in force at 31.3.2004, see reg. 1(1)

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’. Dim ond yn Saesneg y mae’r fersiwn ddiwygiedig ar gael ar hyn o bryd.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed) - Saesneg: Mae'r wreiddiol Saesneg fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed)-Cymraeg:Y fersiwn Gymraeg wreiddiol o’r ddeddfwriaeth fel yr oedd yn sefyll pan gafodd ei deddfu neu ei gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Gweler y wybodaeth ychwanegol ochr yn ochr â’r cynnwys

Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Llinell Amser Newidiadau

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill