This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 28/08/2015.
Changes to legislation:
There are currently no known outstanding effects for the The Town and Country Planning (Local Development Plan) (Wales) Regulations 2005, PART 7.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
PART 7E+WANNUAL MONITORING REPORT
Annual monitoring reportE+W
37.—(1) An LPA must publish its annual monitoring report on its website and also submit it to the National Assembly on or before the date specified in guidance made under section 75.
(2) Where a policy specified in an LDP is not being implemented, the annual monitoring report must identify that policy.
(3) Where an annual monitoring report identifies a policy pursuant to paragraph (2), that report must include a statement of—
(a)the reasons why that policy is not being implemented;
(b)the steps (if any) that the LPA intend to take to secure that the policy is implemented; and
(c)whether the LPA intends to prepare a revision of the LDP to replace or amend the policy.
(4) The annual monitoring report must specify —
(a)the housing land supply taken from the current Housing Land Availability Study; and
(b)the number (if any) of net additional affordable and general market dwellings built in the LPA’s area
both in the period in respect of which the report is made; and in the period since the LDP was first adopted or approved.