Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Regulation 25
1. The requirements to be satisfied in relation to a slurry storage system are as follows.E+W
Commencement Information
I1Sch. 6 para. 1 in force at 1.4.2021, see reg. 1(3)
2. The base of the slurry storage tank, the base and walls of any effluent tank, channels and reception pit, and the walls of any pipes, must be impermeable.E+W
Commencement Information
I2Sch. 6 para. 2 in force at 1.4.2021, see reg. 1(3)
3. The base and walls of the slurry storage tank, any effluent tank, channels and reception pit, and the walls of any pipes, must be protected against corrosion in accordance with paragraph 7 of the code of practice on buildings and structures for agriculture published by the British Standards Institution and numbered BS 5502: Part 50: 1993(1).E+W
Commencement Information
I3Sch. 6 para. 3 in force at 1.4.2021, see reg. 1(3)
4. The base and walls of the slurry storage tank and of any reception pit must be capable of withstanding characteristic loads calculated on the assumptions and in the manner indicated by paragraph 5 of the code of practice on buildings and structures for agriculture published by the British Standards Institution and numbered BS 5502: Part 50: 1993.E+W
Commencement Information
I4Sch. 6 para. 4 in force at 1.4.2021, see reg. 1(3)
5.—(1) Any facilities used for the temporary storage of slurry before it is transferred to a slurry storage tank must have adequate capacity to store—E+W
(a)the maximum quantity of slurry that (disregarding any slurry which will be transferred directly into a slurry storage tank) is likely to be produced on the premises in any two day period, or
(b)a lesser capacity that NRBW agrees in writing is adequate to avoid any significant risk of pollution of controlled waters.
(2) Where slurry flows into a channel before discharging into a reception pit and the flow of slurry out of the channel is controlled by means of a sluice, the capacity of the reception pit must be adequate to hold the maximum quantity of slurry that can be released by opening the sluice.
Commencement Information
I5Sch. 6 para. 5 in force at 1.4.2021, see reg. 1(3)
6. In the case of a slurry storage tanks with walls made of earth, the tank must have at least 750 mm of freeboard and 300 mm of freeboard in all other cases.E+W
Commencement Information
I6Sch. 6 para. 6 in force at 1.4.2021, see reg. 1(3)
7. No part of the slurry storage tank or any effluent tank, channels or reception pit may be situated within 10 metres of any inland freshwaters or coastal waters into which slurry could enter if it were to escape unless precautions are taken that NRBW agrees in writing are adequate to avoid any significant risk of pollution of controlled waters.E+W
Commencement Information
I7Sch. 6 para. 7 in force at 1.4.2021, see reg. 1(3)
8. The slurry storage tank and any effluent tank, channels, pipes and reception pit must be designed and constructed so that with proper maintenance they are likely to continue to satisfy the requirements of paragraphs 2 to 4 for at least 20 years.E+W
Commencement Information
I8Sch. 6 para. 8 in force at 1.4.2021, see reg. 1(3)
9. If the walls of the slurry storage tank are not impermeable, the base of the tank must—E+W
(a)extend beyond the walls;
(b)be provided with channels designed and constructed so as to collect any slurry that escapes from the tank;
(c)have adequate provision for the drainage of the slurry from those channels to an effluent tank through a channel or pipe.
Commencement Information
I9Sch. 6 para. 9 in force at 1.4.2021, see reg. 1(3)
10.—(1) Subject to sub-paragraph (3), if the slurry storage tank or any effluent tank or reception pit is fitted with a drainage pipe there must be two valves in series on the pipe with each valve separated from the other by a minimum distance of 1 metre.E+W
(2) Each valve must be capable of shutting off the flow of slurry through the pipe and must be kept shut and locked in that position when not in use.
(3) Sub-paragraph (1) does not apply in relation to a slurry storage tank that drains through the pipe into another slurry storage tank if the other tank is of equal or greater capacity or if the tops of the tanks are at the same level.
Commencement Information
I10Sch. 6 para. 10 in force at 1.4.2021, see reg. 1(3)
Publication date: 15th April 1993. ISBN 0-580-22053-2.
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’. Dim ond yn Saesneg y mae’r fersiwn ddiwygiedig ar gael ar hyn o bryd.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed) - Saesneg: Mae'r wreiddiol Saesneg fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed)-Cymraeg:Y fersiwn Gymraeg wreiddiol o’r ddeddfwriaeth fel yr oedd yn sefyll pan gafodd ei deddfu neu ei gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Pwynt Penodol mewn Amser: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search. A point in time version is only available in English.
Rhychwant ddaearyddol: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Dangos Llinell Amser Newidiadau: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys