17.—(1) In constructing the works, the Commissioners shall act in accordance with—
(a)the statutory nature conservation agency protocol for minimising the risk of disturbance and injury to marine mammals from piling noise dated 2010 (1); and
(b)the JNCC guidelines for minimising the risk of injury to marine mammals from using explosives dated August 2010(2),
both issued by the Joint Nature Conservation Committee(3).
The Joint Nature Conservation Committee is reconstituted by section 31 of and Schedule 4 to the Natural and Rural Communities Act 2006.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: