11. –
(1) A contracting authority using the open procedure shall comply with the following paragraphs of this regulation.
(2) The contracting authority shall publicise its intention to seek offers in relation to the public works contract by sending to the Official Journal as soon as possible after forming the intention a notice, in a form substantially corresponding to that set out in Part B of Schedule 2, inviting tenders and containing the information therein specified in relation to the contract.
(3) Subject to paragraph (4) below, the date which the contracting authority shall fix as the last date for the receipt by it of tenders made in response to the contract notice shall be specified in the notice and shall be not less than 52 days from the date of despatch of the notice but, if the contract documents are too bulky to be supplied within this time or it is necessary that contractors be given the opportunity to inspect the site on which the work or works under the contract is or are to be carried out or documents relating to the contract documents, then that minimum period shall be extended to allow for such supply or inspection.
(4) Where the contracting authority has published a notice in accordance with regulation 9 in relation to the public works contract it may substitute for the period of not less than 52 days specified in paragraph (3) above a period of not less than 36 days.
(5) The contracting authority shall send the contract documents within 6 days of the receipt of a request from any contractor provided that the documents are requested in good time and any fee specified in the contract notice has accompanied the request.
(6) The contracting authority shall supply such further information relating to the contract documents as may reasonably be requested by a contractor provided that the request is received in sufficient time to enable the contracting authority to supply the information no later than 6 days before the date specified in the contract notice as the final date for the receipt of tenders.
(7) The contracting authority may exclude a tender from the evaluation of offers made in accordance with regulation 20 only if the contractor may be treated as ineligible to tender on a ground specified in regulation 14 or if the contractor fails to satisfy the minimum standards of economic and financial standing and technical capacity required of contractors by the contracting authority; for this purpose the contracting authority shall make its evaluation in accordance with regulations 14, 15, 16 and 17.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: