The Margate Pier and Harbour Revision Order 1992

Work No. 1

A harbour arm comprising—

(a)a bund commencing at point E on the deposited plan (being a point 194 metres from the base of the existing lighthouse) by a junction with the existing quay wall of the harbour at its southern end, passing north-west for a distance of 82 metres to point F on the deposited plan, then passing in a northerly direction for a distance of 103 metres to point G on the deposited plan and there terminating;

(b)a retaining wall commencing at point M (being a point 188 metres from the base of the existing lighthouse) on the deposited plan by a junction with the said quay wall, passing north-north-west for a distance of 100 metres to a point L on the deposited plan, then passing due north for a distance of 48 metres to point K on the deposited plan and there terminating;

(c)a quay wall commencing at points G-K on the deposited plan by a junction with the bund and retaining wall, passing north-east for a distance of 70 metres to point J on the deposited plan and there terminating 83 metres north-east of the seaward end of the Stone Pier; and

(d)a reclamation area between the bund and retaining wall within points E, F, G, K, L and M on the deposited plan.