The Meters (Certification) Regulations 1998

 Help about what version

What Version

 Help about advanced features

Advanced Features

More Resources

Changes to legislation:

There are currently no known outstanding effects for the The Meters (Certification) Regulations 1998, SCHEDULE 1. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Regulations 3(2)(c) and 4(2)(d)

SCHEDULE 1E+W+SAUTHORISED MANUFACTURERS' AND AUTHORISED REPAIRERS'TESTS AND TESTING METHODS FOR ALTERNATING CURRENT WATTHOUR METERS

Pre-heatingE+W+S

1.—(1) The following tests shall not be carried out until the voltage circuits of meters under test and the voltage circuits of working standard integrating meters have been energised for a period of one hour or half an hour if a current of not less than either 10 per cent. of basic current or 5 per cent. of marked current is applied to the current circuits of the meters, provided that the non-registration and starting current tests may be carried out during the pre-heating period.

(2) Sub-paragraph (1) shall not apply to a meter which the examiner is satisfied is capable of full operation as soon as it is energised.

Commencement Information

I1Sch. 1 para. 1 in force at 1.8.1998, see reg. 1

Non-registration testE+W+S

Induction meters

2.—(1) Induction meters shall be tested to ensure that when the current circuits are open and a voltage of 110 per cent. of the declared system voltage is applied to the voltage circuits, rotors cease to rotate before completing one revolution.

Static meters

(2) Static meters shall be tested for non-registration by one of the following methods—

  • Method 1

    (a)
    (i)

    When subjected to the test conditions specified in paragraph 2(1), the meter shall not emit more than one output pulse over the minimum test period determined in paragraph (ii);

    (ii)

    the minimum test period shall be computed by the formula—

    No math image to display

    where

    t

    =

    minimum test period

    K

    =

    number of pulses per kWh emitted by the meter

    m

    =

    number of elements

    V

    =

    declared system voltage

    Im

    =

    maximum rated current.

    For transformer-operated meters, k and Im must either both relate to primary values or both relate to secondary values.

  • Method 2

    (b)

    When static meters are fitted with inhibiting circuits, they may be tested for non-registration with a current which is less than the threshold current in respect of a meter of that type and at a voltage of 100 per cent. of the declared system voltage of the meters under test. Meters shall not emit more than one output pulse over the minimum test period determined as follows—

    No math image to display

    where

    t

    =

    minimum test period

    V

    =

    declared system voltage

    I

    =

    total current of all phases

    k

    =

    number of pulses emitted per kWh by the meter

    pf

    =

    power factor.

  • Method 3

    (c)

    The period calculated for method 1 or method 2 may be halved if the meters under test do not emit any output pulses during the period of the test.

Commencement Information

I2Sch. 1 para. 2 in force at 1.8.1998, see reg. 1

Accuracy testsE+W+S

3.—(1) Apparatus used for determining the errors of repaired meters during these tests shall comply with directions.

(2) The rate of advance of a meter over a test period shall be obtained by reading the electro-mechanical register or electronic display on or connected to the meter or by monitoring the rotation of the disc or pulse output of the meter.

(3) For any test load, the load applied to a working standard integrating meter shall not be less than 25 per cent. or more than 125 per cent. of its full load rating.

(4) For a working standard wattmeter, the applied load shall not be less than 40 per cent. or more than 100 per cent. of its full scale or range reading.

Commencement Information

I3Sch. 1 para. 3 in force at 1.8.1998, see reg. 1

Methods of accuracy testE+W+S

4.  The tests in table 2 shall be carried out by one of the following methods—

  • Method A test

    (1)

    A long period dial test where the advance of a kWh display, which is part of or connected to a meter under test, is compared with the advance of a precision kilowatt-hour meter;

  • Method B test

    (2)

    A short period test where the rate of advance of a meter under test is compared to the rate of advance of a precision kilowatt-hour meter; or

  • Method C test

    (3)

    A short period test where the actual rate of advance of a meter, when tested under constant power conditions over a specified test period, is compared to the calculated rate of advance for those conditions.

Commencement Information

I4Sch. 1 para. 4 in force at 1.8.1998, see reg. 1

Reference conditions for all testingE+W+S

5.—(1) All tests shall be carried out under the reference conditions specified in table 1.

Meter position

(2) The meter position requirement given in table 1 applies to induction meters only. Tolerance applies to a horizontal reference line or edge on the meter, such as the lower edge of the terminal block.

Voltage and current supplies for polyphase meters

(3) When testing polyphase meters—

(a)the order of the phases shall correspond to the sequence shown on the connection diagram;

(b)the voltages shall be balanced so that the voltage between any line and neutral or between any two lines shall not differ by more than 1.5 per cent. from the mean of the corresponding voltages;

(c)the currents shall be balanced so that the current in any conductor shall not differ by more than 2.5 per cent. from the mean of these currents; and

(d)the phase displacement between the current and corresponding phase to neutral voltage shall not differ from other current and voltage phase displacements by more than 3 degrees at any power factor under any load conditions specified in table 2.

External magnetic induction

(4) The test given in table 1 in respect of external magnetic induction shall be carried out during commissioning or after major modification or refurbishing of a meter testing system. The test is carried out at 0.1 Ib unity power factor with the meters normally connected to determine the errors—

(a)for single phase meters, after reversing both current and voltage connections, for which half the difference between the two errors is the value of the variation;

(b)for polyphase meters, by making two additional measurements after each of the connections to the current circuits and to the voltage circuits are changed over 120 degrees but with the phase sequence unaltered, for which the greatest difference between each error determined and the mean of the three errors is the value of the variation.

Dial tests

(5) Where all the errors of repaired meters are determined by the method B or method C test, an additional test in accordance with method A shall be carried out. The method A test shall be carried out at one of the loads used for the method B or method C test. The error obtained by the method A test shall not differ by more than 0.6 per cent. from the error obtained at the same load value by the method B or method C test.

Duration of test

(6) The tests described in paragraph 4 shall continue until the error of meters can be calculated within a tolerance not greater than plus or minus 0.2 per cent.

Conditions for mixing methods of test

(7) The method A test may be used for intermediate and high loads, at unity power factor and at 0.5 power factor, and the method B or method C test for the low load, provided that an additional method B or method C test is carried out at one of the test load values used for the method A test.

Commencement Information

I5Sch. 1 para. 5 in force at 1.8.1998, see reg. 1

Test loadsE+W+S

6.—(1) Every repaired meter shall be tested at each of the loads specified in table 2, except that test number 2 in that table may be omitted.

(2) Every new meter shall be calibrated and tested at a sufficient number of load points so as to ensure that meter errors are not greater than the limits specified in paragraph 9.

(3) A test for starting shall also be carried out on new meters in accordance with test number 7 of table 2.

(4) The ratio errors shall be determined for voltage transformers that are intended for use with meters but are not tested with a meter.

(5) Current transformers intended for use with meters but not tested with a meter shall be tested from 5 per cent. to 120 per cent. of rated current.

Commencement Information

I6Sch. 1 para. 6 in force at 1.8.1998, see reg. 1

Multi-register metersE+W+S

Induction meters

7.—(1) (a) All induction meters with more than one register shall be tested on one register in accordance with paragraphs 5 and 6 and on each and every other register at a low load using the method A, method B or method C test and at an intermediate or high load using the method A test.

(b)For the same load conditions the maximum permitted difference between the error on one register, expressed as a percentage, and the error on any other register, expressed as a percentage, is 1 per cent.

Static meters

(2) (a) All static meters with more than one register shall be tested on one register in accordance with paragraphs 5 and 6.

(b)For repaired static meters with more than one register—

(i)where the total units are the sum of all the registers, a further test shall be carried out on each and every other register using method A but

(ii)where the total units are recorded on one register, only that register is required to be tested in accordance with paragraphs 5 and 6.

Commencement Information

I7Sch. 1 para. 7 in force at 1.8.1998, see reg. 1

Polyphase metersE+W+S

8.—(1) Every polyphase meter shall be tested on a circuit having a phase relationship for which that meter is designed, provided that three phase, four wire polyphase meters may be tested without current in the neutral conductor.

(2) Polyphase meters shall be tested by using —

(a)a polyphase kilowatt-hour energy standard;

(b)2 or 3 single phase kilowatt-hour energy standards; or

(c)2 or 3 single phase wattmeters.

Commencement Information

I8Sch. 1 para. 8 in force at 1.8.1998, see reg. 1

Margins of errorE+W+S

9.—(1) The error permitted for—

(a)single phase and polyphase whole current meters and

(b)single phase and polyphase transformer operated meters when tested with transformers connected

shall not exceed plus or minus 1.5 per cent. for test numbers 1, 2, 3 and 4 given in table 2.

(2) The error permitted for both single phase and polyphase transformer operated meters, when tested without transformers connected, shall not exceed plus or minus 1.0 per cent. for test numbers 1, 2, 3 and 4 given in table 2.

(3) The error permitted for polyphase whole current and transformer operated meters, when tested with transformers connected, shall not exceed plus 1.7 per cent. or minus 2.7 per cent. for test numbers 5 and 6 given in table 2.

(4) The error permitted for polyphase transformer operated meters, when tested without transformers connected, shall not exceed plus 1.2 per cent. or minus 2.2 per cent. for test numbers 5 and 6 given in table 2.

(5) Where current and voltage transformers are intended to be used with meters and are not tested connected to a meter then the error of the transformers at any load point throughout the rated range shall not exceed 0.5 per cent.

Commencement Information

I9Sch. 1 para. 9 in force at 1.8.1998, see reg. 1

Insulation property testE+W+S

10.  Each meter shall be tested to demonstrate that the insulation of the meter is of a sufficient standard to enable the meter to operate safely and correctly in the conditions in which it could reasonably be expected to be installed and operated.

TABLE 1

Influence quantitiesReference valueTolerance
Ambient temperatureReference temperature or, if not indicated, 23°C.>15°C to <30°C
Meter positionVertical±3°
VoltageReference voltage±1.5%
FrequencyReference frequency of 50Hz±0.5%
Voltage and current waveformSinusoidal formDistortion factor <5%
External magnetic induction at the reference frequency (paragraph 5(4))ZeroInduction value that does not produce a relative error variation of more than ±0.3%

TABLE 2

Test load in terms of marked current
Test number and loadPower factorBasic/maximumMaximum continuousLong rangeShort rangeMeter typePolyphase meter load
1 (high)1Imax100%100%–200% (Note 1)100%–125% (Note 1)Single and polyphaseBalanced
2 (intermediate)1Ib or 125%IbAny load between 25%–75% of the value specified for test number 1 (Note 1)Single and polyphaseBalanced
3 (low)15%Ib1.67% (Note 2)5%5%Single and polyphaseBalanced
4 (inductive)0.5 (Note 3)Ib or Imax100%The same value selected for test number 1Single and polyphaseBalanced
5 (element)1Ib100%The same value selected for test number 1PolyphaseOne phase loaded in turn
6 (inductive) (element)0.5 (Note 3)Ib100%The same value selected for test number 1PolyphaseOne phase loaded in turn
7 (starting-current)10.5%Ib to 1.0%Ib0.5% to 1.0%0.5% to 1.0%0.5% to 1.0%Single and polyphaseBalanced

Note 1 Where a range is given, any value within that inclusive range may be selected.

  • Note 2 For maximum continuously rated prepayment meters, the low load test value may be twice the value shown.

  • Note 3 For test numbers 4 and 6, the inductive power factor shall be between 0.45 and 0.55 inclusive.

Commencement Information

I10Sch. 1 para. 10 in force at 1.8.1998, see reg. 1

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.