The following guidelines should be met as far as practicable:
the flow around the inlet sampling probe should be unrestricted without any obstructions affecting the airflow in the vicinity of the sampler (normally some metres away from buildings, balconies, trees and other obstacles and at least 0.5 m from the nearest building in the case of sampling points representing air quality at the building line);
in general, the inlet sampling point should be between 1.5 m (the breathing zone) and 4 m above the ground. Higher positions (up to 8 m) may be necessary in some circumstances. Higher siting may also be appropriate if the station is representative of a large area;
the inlet probe should not be positioned in the immediate vicinity of sources in order to avoid the direct intake of emissions unmixed with ambient air;
the sampler’s exhaust outlet should be positioned so that recirculation of exhaust air to the sampler inlet is avoided;
location of traffic-orientated samplers;
for all pollutants, such sampling points should be at least 25 m from the edge of major junctions and at least 4 m from the centre of the nearest traffic lane,
for nitrogen dioxide, inlets should be no more than 5 m from the kerbside,
for particulate matter and lead, inlets should be sited so as to be representative of air quality near to the building line.
The following factors may also be taken into account:
interfering sources;
security;
access;
availability of electrical power and telephone communications;
visibility of the site in relation to its surroundings;
safety of public and operators;
the desirability of co-locating sampling points for different pollutants;
planning requirements.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: