SCHEDULE 3INTERNATIONAL CARRIAGE UNDER THE WARSAW CONVENTION AS AMENDED BY ADDITIONAL PROTOCOL NO. 1 OF MONTREAL 1975

PART I

CHAPTER IIILiability of the Carrier

Article 17

The carrier is liable for damage sustained in the event of the death or wounding of a passenger or any other bodily injury suffered by a passenger, if the accident which caused the damage so sustained took place on board the aircraft or in the course of any of the operations of embarking or disembarking.

Article 18

(1) The carrier is liable for damage sustained in the event of the destruction or loss of, or of damage to, any registered baggage or any cargo, if the occurrence which caused the damage so sustained took place during the carriage by air.

(2) The carriage by air within the meaning of the preceding paragraph comprises the period during which the baggage or cargo is in charge of the carrier, whether in an aerodrome or on board an aircraft, or, in the case of a landing outside an aerodrome in any place whatsoever.

(3) The period of the carriage by air does not extend to any carriage by land, by sea or by river performed outside an aerodrome. If, however, such a carriage takes place in the performance of a contract for carriage by air, for the purpose of loading, delivery or transhipment, any damage is presumed, subject to proof to the contrary, to have been the result of an event which took place during the carriage by air.

Article 19

The carrier is liable for damage occasioned by delay in the carriage by air of passengers, baggage or cargo.

Article 20

(1) The carrier is not liable if he proves that he and his servants or agents have taken all necessary measures to avoid the damage or that it was impossible for him or them to take such measures.

(2) In the carriage of cargo and baggage the carrier is not liable if he proves that the damage was occasioned by negligent pilotage or negligence in the handling of the aircraft or in navigation and that, in all other respects, he and his servants or agents have taken all necessary measures to avoid the damage.

Article 21

If the carrier proves that the damage was caused by or contributed to by the negligence of the injured person the court may, in accordance with the provisions of its own law, exonerate the carrier wholly or partly from his liability.

Article 22

(1) In the carriage of passengers the liability of the carrier for each passenger is limited to the sum of 8,300 Special Drawing Rights. Where, in accordance with the law of the court seised of the case, damages may be awarded in the form of periodic payments, the equivalent capital value of the said payments shall not exceed this limit. Nevertheless, by special contract, the carrier and the passenger may agree to a higher limit of liability.

(2) In the carriage of registered baggage and of cargo, the liability of the carrier is limited to a sum of 17 Special Drawing Rights per kilogramme, unless the consignor has made, at the time when the package was handed over to the carrier, a special declaration of interest in delivery at destination and has paid a supplementary sum if the case so requires. In that case the carrier will be liable to pay a sum not exceeding the declared sum, unless he proves that that sum is greater than the consignor’s actual interest in delivery at destination.

(3) As regards objects of which the passenger takes charge himself the liability of the carrier is limited to 332 Special Drawing Rights per passenger.

(4) The sums mentioned in terms of the Special Drawing Right in this Article shall be deemed to refer to the Special Drawing Right as defined by the International Monetary Fund. Conversion of the sums into national currencies shall, in case of judicial proceedings, be made according to the value of such currencies in terms of the Special Drawing Right at the date of the judgement. The value of a national currency, in terms of the Special Drawing Right, of a High Contracting Party which is a Member of the Monetary Fund, shall be calculated in accordance with the method of valuation applied by the International Monetary Fund, in effect at the date of the judgement, for its operations and transactions. The value of national currency, in terms of the Special Drawing Right, of a High Contracting Party which is not a Member of the International Monetary Fund, shall be calculated in a manner determined by that High Contracting Party.

Article 23

Any provision tending to relieve the carrier of liability or to fix a lower limit than that which is laid down in this Schedule shall be null and void, but the nullity of any such provision does not involve the nullity of the whole contract, which shall remain subject to the provisions of this Schedule.

Article 24

(1) In the cases covered by Articles 18 and 19 any action for damages, however founded, can only be brought subject to the conditions and limits set out in this Schedule.

(2) In the cases covered by Article 17 the provisions of the preceding paragraph also apply, without prejudice to the questions as to who are the persons who have the right to bring suit and what are their respective rights.

Article 25

(1) The carrier shall not be entitled to avail himself of the provisions of this Schedule which exclude or limit his liability, if the damage is caused by his misconduct, or by such default on his part as, in accordance with the law of the court seised of the case, is considered to be equivalent to wilful misconduct.

(2) Similarly the carrier shall not be entitled to avail himself of the said provisions, if the damage is caused as aforesaid by any servant or agent of the carrier acting within the scope of his employment.

Article 26

(1) Receipt by the person entitled to delivery of baggage or cargo without complaint is prima facie evidence that the same has been delivered in good condition and in accordance with the document of carriage.

(2) In the case of damage, the person entitled to delivery must complain to the carrier forthwith after the discovery of the damage, and, at the latest, within three days from the date of receipt in the case of baggage and seven days from the date of receipt in the case of cargo. In the case of delay the complaint must be made at the latest within fourteen days from the date on which the baggage or cargo has been placed at his disposal.

(3) Every complaint must be made in writing upon the document of carriage or by separate notice in writing despatched within the times aforesaid.

(4) Failing complaint within the times aforesaid, no action shall lie against the carrier, save in the case of fraud on his part.

Article 27

In the case of the death of the person liable, an action for damages lies in accordance with the terms of this Schedule against those legally representing his estate.

Article 28

(1) An action for damages must be brought, at the option of the plaintiff in the territory of one of the High Contracting Parties to the Warsaw Convention as amended by Additional Protocol No. 1 of Montreal 1975, either before the court having jurisdiction where the carrier is ordinarily resident, or has his principal place of business, or has an establishment by which the contract has been made or before the Court having jurisdiction at the place of destination.

(2) Questions of procedure shall be governed by the law of the court seised of the case.

Article 29

(1) The right to damages shall be extinguished if an action is not brought within two years, reckoned from the date of arrival at did destination, or from the date on which the aircraft ought to have arrived, or from the date on which the carriage stopped.

(2) The method of calculating the period of limitation shall be determined by the law of the court seised of the case.

Article 30

(1) In the case of carriage to be performed by various successive carriers and falling within the definition set out in the third paragraph of Article 1, each carrier who accepts passengers, baggage or cargo is subjected to the rules set out in this Schedule, and is deemed to be one of the contracting parties to the contract of carriage in so far as the contract deals with that part of the carriage which is performed under his supervision.

(2) In the case of carriage of this nature, the passenger or his representative can take action only against the carrier who performed the carriage during which the accident or the delay occurred, save in the case where, by express agreement, the first carrier has assumed liability for the whole journey.

(3) As regards baggage or cargo, the passenger or consignor will have a right of action against the first carrier, and the passenger or consignee who is entitled to delivery will have a right of action against the last carrier, and further, each may take action against the carrier who performed the carriage during which the destruction, loss, damage or delay took place. These carriers will be jointly and severally liable to the passenger or to the consignor or consignee.