Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
6.—(1) This paragraph applies for the purpose of determining liability for a water discharge activity that consists of a discharge of sewage effluent from a discharging sewer vested in a discharging undertaker.
(2) A discharging undertaker causes a discharge of sewage effluent if—
(a)matter included in the discharge is received by the discharging undertaker into the discharging sewer or into any other sewer or works vested in it;
(b)the discharging undertaker was bound (either unconditionally or subject to conditions which were observed) to receive the matter into the discharging sewer or other sewer or works; and
(c)sub-paragraph (3) does not apply.
(3) This sub-paragraph applies if, before the discharging undertaker discharges the sewage effluent from the discharging sewer, the sending undertaker, under an agreement with the discharging undertaker under section 110A of the Water Industry Act 1991, discharges the sewage effluent through a main connection into—
(a)the discharging sewer; or
(b)any other sewer or works vested in the discharging undertaker.
(4) If sub-paragraph (3) applies, the sending undertaker causes the discharge if—
(a)matter included in the discharge is received by the sending undertaker into a sewer or works vested in it; and
(b)it was bound (either conditionally or subject to conditions which were observed) to receive that matter into that sewer or works.
(5) A sewerage undertaker is not guilty of an offence under regulation 38(1) in relation to a water discharge activity that consists of a discharge of sewage effluent from a sewer or works vested in it if—
(a)the contravention is attributable to a discharge which another person caused or knowingly permitted to be made into the sewer or works;
(b)the undertaker either was not bound to receive the discharge into the sewer or works or was bound to receive it there subject to conditions which were not observed; and
(c)the undertaker could not reasonably have been expected to prevent the discharge into the sewer or works.
(6) A person is not guilty of an offence under regulation 38(1) in relation to a discharge which the person caused or knowingly permitted to be made into a sewer or works vested in a sewerage undertaker if that undertaker was bound to receive the discharge, either unconditionally or subject to conditions which were observed.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: