11.The authorised development may not commence until, following consultation with...
12.The authorised development may not commence until following consultation with...
14.With respect to paragraph (2) of Requirement 13, such approval...
19.Notwithstanding any design or colour approved by the relevant planning...
20.(1) No wind turbine may display any name, sign, symbol...
32.The undertaker must, if directed by the relevant planning authority,...
33.The undertaker must provide to the relevant planning authority the...
34.The undertaker must continuously log wind speed wind direction and...
35.(1) No authorised development may commence until an assessment demonstrating...
Land subject to acquisition of new rights and interference with private rights
Modification of compensation and compulsory purchase enactments for creation of new rights
2.(1) Without prejudice to the generality of paragraph 1, the...
4.For section 7 of the 1965 Act (measure of compensation)...
6.The following provisions of the 1965 Act (which state the...
8.Section 20 of the 1965 Act (protection for interests of...
9.Section 22 of the 1965 Act (protection of acquiring authority’s...
Protection for electricity, gas, water and sewerage undertakers
1.For the protection of the utility undertakers referred to in...
2.In this Schedule— “alternative apparatus” means alternative apparatus adequate to...
3.This Schedule does not apply to apparatus in respect of...
4.Regardless of any provision in this Order or anything shown...
6.(1) Where, in accordance with the provisions of this Schedule,...
7.(1) Not less than 28 days before starting the execution...
8.(1) Subject to the following provisions of this paragraph, the...
9.(1) Subject to sub-paragraphs (2) and (3), if by reason...
10.Nothing in this Schedule shall affect the provisions of any...