Search Legislation

The Clocaenog Forest Wind Farm Order 2014

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: PART 3

 Help about opening options

Alternative versions:

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Clocaenog Forest Wind Farm Order 2014. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to Schedule 1 Part 3:

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

PART 3E+WRequirements

DefinitionsE+W

1.  In this Part of this Schedule—

“abnormal indivisible load” has the same meaning as in the Road Vehicles (Authorisation of Special Types) (General) Order 2003;

“commencement”, in relation to the authorised development, means the date on which the authorised development begins by the carrying out of a material operation as defined in section 155 of the 2008 Act and “commence” and “commenced” shall be construed accordingly;

“ecological clerk of works” means a suitably qualified environmental professional or group of professionals;

“European protected species” means a species listed in Schedules 2 or 5 of the Conservation of Habitats and Species Regulations 2010;

“felling” means any felling or lopping undertaken pursuant to article 28 (felling or lopping of trees) of this Order;

“first export date” means the date the authorised development first exports electricity on a commercial basis;

“Noise Guidance” means the guidance in Part 4 of this Schedule;

“NRW” means Natural Resources Wales;

“site” means land within the Order limits;

“stakeholder group” means the representatives of organisations which will advise on the measures within the habitat management plan and the implementation of those measures;

“TMFGL” means Tir Mostyn and Foel Goch Limited (reg no 5264934) or the owner from time to time of the Tir Mostyn and Foel Goch Wind Farm;

“Welsh devolved function” has the meaning given by section 36 of the Public Bodies Act 2011; and

“wind turbines” means the wind turbines forming part of Work No. 1 and “wind turbine” shall be construed accordingly.

Commencement Information

I1Sch. 1 Pt. 3 para. 1 in force at 2.10.2014, see art. 1

Submission and approval of detailsE+W

2.  Where, under any Requirement, details or a scheme or plan are to be submitted for the approval of the relevant planning authority then unless the Requirement provides otherwise—

(a)those details or scheme or plan and that approval must be in writing,

(b)the details, scheme or plan must be implemented as approved, and

(c)the approved details, scheme or plan are to be taken to include any amendments that may subsequently be approved in writing by the relevant planning authority, provided that no amendments may be approved by the relevant planning authority where such amendments may give rise to any materially different environmental effects to those assessed in the environment statement and that where under any Requirement there is an obligation to consult with a third party prior to the submission of any details, scheme or plan for approval to the relevant planning authority then there shall be an obligation to consult with the same third party prior to the submission of any amendments to the approved details, scheme or plan to the relevant planning authority.

Commencement Information

I2Sch. 1 Pt. 3 para. 2 in force at 2.10.2014, see art. 1

Time limitsE+W

3.  The authorised development must be commenced within 5 years of the date of this Order.

Commencement Information

I3Sch. 1 Pt. 3 para. 3 in force at 2.10.2014, see art. 1

Expiry of development consentE+W

4.—(1) The development consent granted by this Order expires 25 years after the first export date.

(2) Confirmation of the first export date must be provided by the undertaker to the relevant planning authority within one month of its occurrence.

Commencement Information

I4Sch. 1 Pt. 3 para. 4 in force at 2.10.2014, see art. 1

Decommissioning and site restorationE+W

5.—(1) Not less than 12 months before the expiry of the development consent granted by this Order, a decommissioning and site restoration scheme must be submitted to the relevant planning authority for its approval.

(2) The decommissioning and site restoration scheme must include provision for—

(a)removal of all above-ground elements of the authorised development (with the exception of Work No. 3 and Work No.4A or 4B),

(b)removal of turbine bases and cabling to one metre below ground level, and

(c)restoration of the disturbed areas.

(3) Decommissioning and restoration must be completed in accordance with the approved decommissioning and site restoration scheme within the period set out in the approved scheme.

Commencement Information

I5Sch. 1 para. 5 in force at 2.10.2014, see art. 1

Failure of turbinesE+W

6.—(1) If any wind turbine fails to provide electricity to the grid for a continuous period of 12 months the undertaker must—

(a)notify the relevant planning authority within one month of the expiry of that 12 month period;

(b)if so instructed by the relevant planning authority, submit to the relevant planning authority within 2 months of that instruction a detailed scheme setting out how the wind turbine and its associated ancillary equipment, including cabling (but excluding the turbine bases and cabling more than one metre below ground level) is to be removed from the Order limits and how the disturbed areas will be restored, and

(c)implement the approved scheme no later than 6 months from its approval unless a longer period is agreed in writing by the relevant planning authority.

(2) The agreement of the relevant planning authority in paragraph (1)(c) may only be given in relation to immaterial changes where the subject matter of the agreement sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

Commencement Information

I6Sch. 1 para. 6 in force at 2.10.2014, see art. 1

PlansE+W

7.—(1) Subject to the power to deviate set out in article 6 (power to deviate) and any other Requirement the authorised development is to be carried out in accordance with the plans or other documents certified in accordance with article 36 (certification of plans etc).

(2) No wind turbine may be constructed—

(a)within 50m from the highest point of existing and new forest edge, when measured from the closest part of the rotor sweep of any wind turbine; and

(b)within 50m of any watercourse shown on Figure 8.1 of the environmental statement.

(3) Subject to the requirements of paragraph (2), no other part of the authorised development with the exception of road widening and culverting may be carried out within 30m of any watercourse shown on Figure 8.1 of the environmental statement unless shown on the plans or other documents certified in accordance with article 36 or unless approved by the relevant planning authority.

(4) The approval of the relevant planning authority in paragraph (2) may only be given in relation to immaterial changes where the subject matter of the approval sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

Commencement Information

I7Sch. 1 para. 7 in force at 2.10.2014, see art. 1

Construction traffic management planE+W

8.—(1) No authorised development may commence until, following consultation with the Department of Transport of the Welsh Government and any relevant highway authority, a construction traffic management plan has been submitted to and approved by the relevant planning authority.

(2) The construction traffic management plan in paragraph (1) must include—

(a)construction vehicle routing plans,

(b)site access plans,

(c)details of the management of junctions to and crossings of the public highway and other public rights of way,

(d)details of the scheduling and timing of movements of delivery vehicles including details of abnormal indivisible loads,

(e)details of escorts for abnormal indivisible loads,

(f)details of temporary warning signs and banksman and escort details,

(g)proposals for assessing the existing condition of affected highways,

(h)details of any temporary or permanent improvements to the public highway,

(i)details of the implementation and management of temporary passing places along the B4501 and the unnamed road into the Site,

(j)details for the making good of any incidental damage to highways by construction traffic associated with the authorised project including street furniture, structures, drainage features, highway verge and carriageway surfaces, and

(k)details of the maintenance of access to TMFG wind farm from the B4501 during the construction period of any works to the B4501 in connection with the authorised development together with details of the maintenance of access to clusters B and C of the TMFG wind farm along highways PR1 and PR2 shown on the access plan during the construction of the authorised development.

(3) The construction traffic management plan must be implemented as approved.

(4) Before any wind turbine is removed or replaced a revised construction traffic management plan, dealing with that removal or replacement, must be submitted to and approved by the relevant planning authority.

Commencement Information

I8Sch. 1 para. 8 in force at 2.10.2014, see art. 1

Construction method statementE+W

9.—(1) No authorised development may commence until, following consultation with NRW, a construction method statement has been submitted to and approved by the relevant planning authority.

(2) The construction method statement in paragraph (1) must be based on the principles set out in the Outline Construction Method Statement, included as Annex 3.1 to the environmental statement, and include the following plans as appendices—

(a)Construction Environmental Management Plan;

(b)Waste Management Plan;

(c)Emergency Response Plan;

(d)Soil and Peat Management Plan;

(e)Borrow Pit Design and Site Restoration Plan;

(f)any relevant Species Protection Plans; and

(g)Surface Water Management Plan.

(3) The construction method statement in paragraph (1) must include details of—

(a)roles and responsibilities and accountabilities for the multi-discipline team of engineering construction and environment staff,

(b)mitigation measures to avoid harm to relevant protected species and minimise damage to relevant habitats,

(c)the timing of construction works, including the timing of vegetation removal to avoid the potential for effects on protected species including reptiles and nesting birds,

(d)the vehicle washing facilities, including siting if required to be undertaken on site,

(e)the timing of works and methods of working for cable trenches, foundation works and erection of the wind turbines,

(f)the timing of works and construction of the substation/control buildings and anemometry mast,

(g)the cleaning of site accesses, site tracks and the adjacent public highway and the sheeting of all heavy goods vehicles taking spoil or construction materials to/from the site to prevent spillage or deposit of any materials on the highway,

(h)the pollution control and prevention measures including—

(i)sediment control measures,

(ii)measures for the bunding of fuel, oil and chemical storage areas,

(iii)sewage disposal measures,

(iv)measures for the protection of water courses and ground water and soils,

(v)a programme for monitoring private water supplies, water courses and water bodies before and during the authorised project, including details of the action to be taken if monitoring indicates adverse effects on private water supplies, water courses or water bodies,

(i)the management of waste arisings,

(j)the management of construction noise (including identification of access routes, locations of materials lay-down areas, details of equipment to be employed, operations to be carried out, mitigation measures and a scheme for the monitoring of noise),

(k)a routing strategy to ensure that construction vehicles use agreed routes,

(l)the handling, storage and re-use on site of excavated top soil,

(m)the handling, storage and management of any peat excavated,

(n)the design and construction methods of Works No. 3, and 4A or 4B, including drainage provisions, and the pollution prevention measures to be implemented to ensure there are no polluting discharges from tracks and disturbed areas including provision to ensure that no polluting discharge from those Works and disturbed areas enters any watercourse,

(o)access track construction and widening including the nature, type and quantity of materials to be imported on site for backfilling operations or construction of access tracks,

(p)the management of groundwater and surface water (including mitigation to protect water bodies, water courses and private water supplies),

(q)the management of dust generation during excavations and soil handling,

(r)the proposed location of temporary site compounds for storage of materials, machinery and parking within the sites clear of the highway, including the siting of the temporary buildings and all means of enclosure, oil/fuel and chemical storage and any proposals for temporary lighting, and details of proposals for restoration of the sites of the temporary compounds and works within 12 months of the first export date,

(s)the design and construction of any culverts upgrades or replacements,

(t)the method of borrow pit working including means of extraction, handling, storage and re-use of soil, drainage control and restoration,

(u)the protocols and programme for any required environmental monitoring to be made publicly available on an annual basis,

(v)the restoration of the site which will be temporarily used for construction, and

(w)the proposed communications protocol and the mechanism for investigating complaints, including the action to be taken where complaint investigations indicate materially adverse effects have occurred as a result of the construction of the authorised project.

(4) Before any wind turbine is removed or replaced a revised construction method statement, dealing with that removal or replacement, shall be submitted to and approved by the relevant planning authority.

(5) The construction method statement shall be implemented as approved.

Commencement Information

I9Sch. 1 para. 9 in force at 2.10.2014, see art. 1

HighwaysE+W

10.  No wind turbine parts may be delivered to the site before detailed plans and drawings in respect of Work No. 4A or 4B (whichever is decided on by the undertaker) have been submitted to and approved by the relevant planning authority and such works have been constructed in accordance with the plans and drawings so approved.

Commencement Information

I10Sch. 1 para. 10 in force at 2.10.2014, see art. 1

11.  The authorised development may not commence until, following consultation with the Department for Transport of the Welsh Government and any relevant highway authority, details of temporary or permanent improvements to the public highway have been submitted to and approved by the relevant planning authority. The improvement works are to be implemented in accordance with the approved details.

Commencement Information

I11Sch. 1 para. 11 in force at 2.10.2014, see art. 1

12.  The authorised development may not commence until following consultation with the Department for Transport of the Welsh Government and any relevant highway authority details of the reinstatement of the public highway and its associated street furniture following completion of the construction of the authorised development have been submitted to and approved by the relevant planning authority. The reinstatement works are to be implemented in accordance with the approved details.

Commencement Information

I12Sch. 1 para. 12 in force at 2.10.2014, see art. 1

Construction hoursE+W

13.—(1) The hours of work during the construction phase of the authorised development and any traffic movements into and out of the site associated with the construction or maintenance of the authorised development shall be 0700 to 1900 hours on Mondays to Fridays and 0700 to 1300 hours on Saturdays other than as allowed for under paragraph (2). No work may take place outside these hours, or on public holidays, unless otherwise previously agreed by the relevant planning authority.

(2) Delivery of turbine and delivery and assembly of crane components and other critical operations may take place outside the times specified in paragraph (1), if approved by the relevant planning authority.

Commencement Information

I13Sch. 1 para. 13 in force at 2.10.2014, see art. 1

14.  With respect to paragraph (2) of Requirement 13, such approval may only be given in relation to immaterial changes where it has been demonstrated to the satisfaction of the relevant planning authority that the approval is unlikely to give rise to any materially new or materially different effects from construction or maintenance activities taking place on the days and hours set out in those clauses.

Commencement Information

I14Sch. 1 para. 14 in force at 2.10.2014, see art. 1

Habitat management planE+W

15.—(1) No authorised development may commence until, following consultation with NRW, a detailed habitat management plan has been submitted to and approved by the relevant planning authority.

(2) The detailed habitat management plan in paragraph (1) is to be based on the key objectives and principles set out in the outline habitat management plan included as Annex 9.10 to the environmental statement.

(3) The habitat management plan in paragraph (1) must include measures to—

(a)establish and manage heathland habitat,

(b)restore and manage peatland habitat,

(c)establish and manage suitable habitat for dormice,

(d)contribute to grey squirrel control,

(e)establish and manage suitable habitat for black grouse and nightjar,

(f)monitor the effect of the authorised development and the effectiveness of habitat management upon bats, dormice, black grouse and heathland/peatland habitats. If, following consideration of monitoring results the relevant planning authority believes it is necessary to do so, management prescriptions included in the habitat management plan will be reviewed as necessary,

(g)monitor the effect of the authorised development upon nightjars. If, following consideration of monitoring results the relevant planning authority believes it is necessary to do so, implement the mitigation measures set out in the environmental statement. The measures shall include undertaking a study of nightjar churring against weather conditions prior to construction commencing to inform detailed mitigation proposals, and

(h)establish the membership, terms of reference and provisions for the management of the proposed stakeholder group.

(4) The habitat management plan is to be implemented as approved.

Commencement Information

I15Sch. 1 para. 15 in force at 2.10.2014, see art. 1

Access management planE+W

16.—(1) No authorised development shall commence until, following consultation with NRW, an access management plan has been submitted to and approved by the relevant planning authority.

(2) The access management plan must include—

(a)details of the temporary re-routing of public rights of way during construction of the authorised development,

(b)details of the permanent re-routing of FP19 prior to the operational phase,

(c)details of the provision of signage and other information alerting the public to construction works,

(d)details of any fencing or barriers to be provided during the construction period,

(e)details as to how public rights of way, paths and roads will be inspected prior to and monitored during the construction period,

(f)a commitment to return all public rights of way, paths and roads to the same condition as they were, or better, once the construction period has ceased,

(g)details as to how any paths found to be impassable during surveying will be cleared,

(h)details of temporary alternative routes for any public rights of way that need to be diverted,

(i)details of funds for improved signage/orientation,

(j)details as to the provision of a new way-marked route for the life of the development,

(k)details of a communications campaign linked with the end of the construction period,

(l)details of an active management plan for crossing points for public rights of way during the construction works, and

(m)details of permissive routes to be provided within the public access management areas during the construction phase.

(3) The access management plan is to be implemented as approved by the relevant planning authority.

Commencement Information

I16Sch. 1 para. 16 in force at 2.10.2014, see art. 1

FellingE+W

17.—(1) All felling must be undertaken in accordance with the relevant guidance specified in paragraph (2) and NRW best practice (as amended from time to time).

(2) The relevant guidance is—

(a)The UK Forestry Standard;

(b)UKFS Guidelines – Forests and Water (2011);

(c)UKFS Guidelines – Forests and Soil (2011);

(d)UKFS Guidelines – Forests and Biodiversity (2011); and

(e)UKFS Guidelines – Forests and Historic Environment (2011).

Commencement Information

I17Sch. 1 para. 17 in force at 2.10.2014, see art. 1

AppearanceE+W

18.  The wind turbines may not be erected until details of their external appearance and colour and surface finish and the design and appearance of the associated external transformer/switchgear units (if any) have been submitted to and approved by the relevant planning authority. The authorised development must be completed in accordance with the approved details.

Commencement Information

I18Sch. 1 para. 18 in force at 2.10.2014, see art. 1

19.  Notwithstanding any design or colour approved by the relevant planning authority pursuant to Requirement 18, all wind turbines must be of a 3 bladed configuration and of a semi-matt finish.

Commencement Information

I19Sch. 1 para. 19 in force at 2.10.2014, see art. 1

20.—(1) No wind turbine may display any name, sign, symbol or logo on any external surface, unless such name, sign, symbol or logo has been approved in writing by the relevant planning authority.

(2) Paragraph (1) of this Requirement does not apply to any name, sign, symbol or logo required by law or for health and safety reasons.

Commencement Information

I20Sch. 1 para. 20 in force at 2.10.2014, see art. 1

21.  All wind turbines’ blades are to rotate in the same direction. Without prejudice to Requirement 28 the wind turbines may not be illuminated, save for a sensor-operated access light.

Commencement Information

I21Sch. 1 para. 21 in force at 2.10.2014, see art. 1

22.  Before construction of Work No. 5A or 5B, details of the external design, appearance and finish of the substation and any associated hard standing areas, and the electrical compound must be submitted to and approved by the relevant planning authority. The authorised development is to be completed in accordance with the approved details.

Commencement Information

I22Sch. 1 para. 22 in force at 2.10.2014, see art. 1

Shadow flickerE+W

23.  The authorised development may not commence until a scheme for the avoidance of any shadow flicker effect at any dwelling which lawfully existed or had planning permission at the date of this Order has been submitted to and approved by the relevant planning authority. The scheme must include a time limit for the investigation of complaints, and for the implementation of mitigation measures. The scheme is to be implemented as approved.

Commencement Information

I23Sch. 1 para. 23 in force at 2.10.2014, see art. 1

ArchaeologyE+W

24.—(1) No authorised development may commence until a scheme of archaeological investigation has been submitted to and approved by the relevant planning authority.

(2) The scheme of archaeological investigation must incorporate—

(a)a walkover survey before commencement of the authorised development;

(b)fencing to be provided around Twr yr Hill round barrow and Maen Cred standing stone during construction works;

(c)where presence of archaeological remains is established a watching brief will be undertaken during construction to record the surviving archaeological remains;

(d)a watching brief during construction of all other infrastructure to record any previously unknown archaeological remains that may be present; and

(e)proposed peat core sampling.

(3) The scheme of archaeological investigation shall be implemented as approved.

Commencement Information

I24Sch. 1 para. 24 in force at 2.10.2014, see art. 1

Ecological clerk of worksE+W

25.—(1) No authorised development may commence until, following consultation with NRW and approval by the relevant local planning authority, an ecological clerk of works has been appointed.

(2) An ecological clerk of works is to be retained throughout the duration of civil construction works on site to advise on minimising ecological effects of the construction activities.

Commencement Information

I25Sch. 1 para. 25 in force at 2.10.2014, see art. 1

Surface water drainageE+W

26.—(1) No authorised development may commence until, following consultation with NRW, details of the surface water drainage system (including means of pollution control) have been submitted to and approved by the relevant planning authority.

(2) The details of the surface water drainage system submitted under paragraph (1) must accord with the Outline Surface Water Management Plan at Annex 8.1 of the environmental statement to ensure that existing runoff regimes are maintained where possible and no increase in peak runoff is experienced within receiving watercourses as a consequence of the authorised development and shall include a mechanism to establish a baseline for the existing surface water drainage conditions.

(3) The surface water drainage system is to be constructed in accordance with the approved details.

Commencement Information

I26Sch. 1 para. 26 in force at 2.10.2014, see art. 1

Accumulation and depositsE+W

27.—(1) No authorised development may commence until, following consultation with NRW, a written scheme for the management of any accumulations and deposits has been submitted to and approved by the relevant planning authority.

(2) The approved scheme for the management of accumulations and deposits is to be implemented before and maintained during the construction, operation and decommissioning of the authorised development.

Commencement Information

I27Sch. 1 para. 27 in force at 2.10.2014, see art. 1

Infra-red aviation lightingE+W

28.  No wind turbine shall be erected until, following consultation with the Ministry of Defence, details of the installation of infra-red aviation warning lights have been submitted to and approved by the relevant planning authority. The lights must be installed in accordance with the approved details and maintained until the wind turbines are decommissioned in accordance with Requirements.

Commencement Information

I28Sch. 1 para. 28 in force at 2.10.2014, see art. 1

Defence Geographic CentreE+W

29.  No wind turbine may be erected before information on the accurate location of the wind turbines has been provided to the Defence Geographic Centre of the Ministry of Defence.

Commencement Information

I29Sch. 1 para. 29 in force at 2.10.2014, see art. 1

NoiseE+W

30.—(1) The level of noise immissions from the combined effects of the wind turbines (including the application of any tonal penalty), when calculated in accordance with the Noise Guidance, may not exceed the values set out in Table 1 below. Noise limits for dwellings which lawfully existed or had planning permission at the date of this Order and which are not listed in Table 1 are to be those of the physically closest location listed in Table 1 below, unless otherwise agreed with the relevant planning authority. The coordinate locations to be used in determining the location of each of the dwellings listed in Table 1 are those listed in Table 2.

(2) The agreement of the relevant planning authority in paragraph (1) may only be given in relation to immaterial changes where the subject matter of the agreement sought is unlikely to give rise to any materially new or materially different environmental effects from those assessed in the environmental statement.

Table 1
The LA90,10min dB noise level
LocationStandardised wind speed at 10 metre height (m/s)
123456789101112
Bron Bannog39.139.139.139.139.139.139.139.139.141.744.346.6
Castell y Waen30.830.830.830.830.830.830.830.831.933.535.136.7
Cefn Rofft36.736.736.736.736.736.736.736.739.042.345.648.8
Cefnbannog37.537.537.537.537.537.537.537.538.342.145.849.3
Crud-y-Gwynt39.339.339.339.339.339.339.339.941.042.343.845.4
Cruglas39.639.639.639.639.639.639.639.639.639.641.444.3
Diffws37.237.237.237.237.339.040.742.243.344.044.444.6
Hafod Caradoc32.032.032.032.032.032.032.032.032.835.438.140.8
Hafod Ty Ddu32.032.032.032.032.032.032.035.139.242.645.748.8
Hafotty Newydd38.738.738.738.738.738.738.738.738.941.744.547.2
Plas Nant Glyn28.228.228.228.228.228.228.228.228.228.228.228.2
Tai’n-y-Waens39.339.339.339.339.339.339.339.340.944.147.250.2
Tal-y-cefn Uchaf39.239.239.239.239.239.239.240.243.446.649.852.8
Trawsnant38.438.438.438.438.438.438.438.438.439.441.944.9
Boced35.135.135.135.135.135.135.135.135.136.138.641.5
Bod Petryal32.732.732.732.732.732.732.733.735.735.735.735.7
Bryn Bach34.234.234.234.234.234.234.234.234.235.237.740.7
Bryn Gaseg34.234.234.234.234.234.234.234.236.539.843.146.3
Bryn-celyn33.833.833.833.833.833.833.834.836.836.836.836.8
Brynhyfryd35.335.335.335.335.335.335.335.336.139.943.647.1
Bryn-y-gwrgi37.637.637.637.637.637.637.637.639.342.545.648.6
Bryn-yr-eryr33.133.133.133.133.133.133.133.135.538.842.145.3
Capel Hiraethog38.238.238.238.238.238.238.238.238.238.240.042.9
Derwydd35.235.235.235.235.235.235.235.237.640.844.247.4
Drws-y-Buddel31.731.731.731.731.731.731.731.731.732.735.238.2
Foel36.136.136.136.136.136.136.136.138.541.745.148.3
Garreg-Iwyd32.032.032.032.032.032.032.032.032.033.436.138.8
Glan-y-gors34.734.734.734.734.734.734.734.734.737.339.942.2
Hafod Olygfa32.032.032.032.032.032.032.034.638.742.145.248.3
Hafotty Bach36.336.336.336.336.336.336.336.336.337.339.942.8
Hafotty Hendre39.639.639.639.639.639.639.639.641.244.447.550.5
Isgaer-wen38.038.038.038.038.038.038.038.038.241.043.846.5
Lodge Isaf35.535.535.535.535.535.535.535.536.340.143.947.3
Lodge Uchaf35.735.735.735.735.735.735.735.736.540.344.047.5
Maes Cadarn37.837.837.837.837.837.837.837.837.837.839.642.5
Nant Uchaf38.138.138.138.138.138.138.138.138.139.141.644.6
Pantdedwydd36.636.636.636.636.636.636.636.638.942.245.548.7
Pedair-a-dimai31.931.931.931.931.931.931.931.934.337.640.944.1
Pen-Bedw35.535.535.535.535.535.535.535.535.536.539.041.9
Pennant38.338.338.338.338.338.338.338.338.338.340.143.0
Pennant Uchaf32.532.532.532.532.532.532.532.532.534.637.340.0
Pen-y-bryn35.235.235.235.235.235.235.236.238.238.238.238.2
Pen-y-Lan37.437.437.437.437.437.437.437.437.438.440.943.8
Seler38.338.338.338.338.338.338.338.338.339.341.844.8
Tai Ucha38.238.238.238.238.238.238.238.238.239.241.744.7
Tai’n-y-graig37.737.737.737.737.737.737.738.741.845.048.251.3
Tal y Cefn Isaf38.838.838.838.838.838.838.838.840.543.746.849.8
Tan-y-bwlch34.834.834.834.834.834.834.835.837.837.837.837.8
Ty Newydd32.032.032.032.032.032.032.032.032.033.836.539.2
Ty-nant37.737.737.737.737.737.737.737.740.143.446.749.9
Ty’n-y-ffordd30.530.530.530.530.530.530.530.532.936.239.542.7
Ty-Uchaf37.837.837.837.837.837.837.837.838.040.843.646.4
Waen Ganol37.537.537.537.537.537.537.537.537.540.142.745.0
Waen Ganol237.237.237.237.237.237.237.237.237.239.842.444.7
Waen Uchaf38.538.538.538.538.538.538.538.538.541.143.746.0
Wern Uchaf27.327.327.327.327.327.327.529.531.834.337.039.7
Table 2
Coordinate locations of the properties listed in Table 1
PropertyEastingNorthing
Bron Bannog303230352830
Castell y Waen299803362240
Cefn Rofft300882349754
Cefnbannog302337351034
Crud-y-Gwynt302463354928
Cruglas302917353853
Diffws302388357614
Hafod Caradoc298722359204
Hafod Ty Ddu301570359341
Hafotty Newydd300176354208
Plas Nant Glyn300377361202
Tai’n-y-Waens299856351666
Tal-y-cefn Uchaf299732352723
Trawsnant302393356134
Boced302976358286
Bod Petryal303760351073
Bryn Bach302098358784
Bryn Gaseg300677349373
Bryn-celyn302053349903
Brynhyfryd303561351370
Bryn-y-gwrgi299592350697
Bryn-yr-eryr300984349178
Capel Hiraethog303741354707
Derwydd300348349609
Drws-y-Buddel302225359813
Foel299701350042
Garreg-Iwyd300264359607
Glan-y-gors304906351677
Hafod Olygfa301400359413
Hafotty Bach303271357991
Hafotty Hendre300246351304
Isgaer-wen299620354471
Lodge Isaf303100351300
Lodge Uchaf302715351159
Maes Cadarn303961355254
Nant Uchaf302894355876
Pantdedwydd301360349728
Pedair-a-dimai300207349245
Pen-Bedw303639357401
Pennant303922354677
Pennant Uchaf299059359533
Pen-y-bryn301707349724
Pen-y-Lan303807356760
Seler302815355559
Tai Ucha302775356368
Tai’n-y-graig298676352289
Tal y Cefn Isaf299388352000
Tan-y-bwlch301894349893
Ty Newydd299434359360
Ty-nant300215350152
Ty’n-y-ffordd299922349210
Ty-Uchaf299007353971
Waen Ganol304136353152
Waen Ganol2304169352986
Waen Uchaf303718353376
Wern Uchaf298304360149

Note to Table 2: The geographical coordinate references are provided for the purpose of identifying the general location of dwellings to which a given set of noise limits applies.

Commencement Information

I30Sch. 1 para. 30 in force at 2.10.2014, see art. 1

31.  Within 21 days from the receipt of a written request from the relevant planning authority and following a complaint to the relevant planning authority from the occupant of a dwelling which lawfully existed or had planning permission at the date this Order came into force, the undertaker must, at its own expense, employ an independent consultant approved by the relevant planning authority to assess the level of noise immissions from the authorised development at the complainant’s property following the procedures described in the Noise Guidance in Part 4.

Commencement Information

I31Sch. 1 para. 31 in force at 2.10.2014, see art. 1

32.  The undertaker must, if directed by the relevant planning authority, switch off any of the wind turbines in order to assess compliance with the noise limits.

Commencement Information

I32Sch. 1 para. 32 in force at 2.10.2014, see art. 1

33.  The undertaker must provide to the relevant planning authority the independent consultant’s assessment and conclusions regarding the noise complaint, including all calculations, audio recordings and the raw data upon which those assessments and conclusions are based. Such information must be provided within 3 months of the date of the written request of the relevant planning authority unless otherwise extended in writing by the relevant planning authority.

Commencement Information

I33Sch. 1 para. 33 in force at 2.10.2014, see art. 1

34.  The undertaker must continuously log wind speed wind direction and power generation at each of the turbines on the site relating to authorised development. The undertaker must continuously log wind speed and wind direction at all anemometer masts on the site. The undertaker must provide all logged data to the relevant planning authority at its written request and in accordance with the Noise Guidance within 28 days of such request. All data is to be retained until the commencement of a decommissioning and site restoration scheme under Requirement 5.

Commencement Information

I34Sch. 1 para. 34 in force at 2.10.2014, see art. 1

35.—(1) No authorised development may commence until an assessment demonstrating that noise from the electrical substation on the site would not exceed a level of 30 dB LAeq at the nearest residential property has been submitted to and approved in writing by the relevant planning authority.

(2) The substation is to be constructed in accordance with the approved assessment.

Commencement Information

I35Sch. 1 para. 35 in force at 2.10.2014, see art. 1

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources