Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
75.—(1) OFCOM shall determine the winning 2.3 GHz assignment stage bids in accordance with this regulation after the deadline for paying the required assignment stage deposit under regulation 89.
(2) The winning 2.3 GHz assignment stage bids shall be those valid 2.3 GHz assignment stage bids that comprise the winning combination of valid 2.3 GHz assignment stage bids.
(3) The winning combination of valid 2.3 GHz assignment stage bids shall be the valid combination of 2.3 GHz assignment stage bids having the highest total value of amounts bid.
(4) A combination of valid 2.3 GHz assignment stage bids is a valid combination of 2.3 GHz assignment stage bids if—
(a)within that combination there is one valid 2.3 GHz assignment stage bid from each winning bidder for 2.3 GHz lots;
(b)each of those valid 2.3 GHz assignment stage bids is for a 2.3 GHz assignment stage option as determined by OFCOM for the bidder;
(c)no numbered 2.3 GHz lot is included in more than one of the 2.3 GHz assignment stage bids included in the combination of valid 2.3 GHz assignment stage bids; and
(d)the numbered 2.3 GHz lots not included in that combination of valid 2.3 GHz assignment stage bids, taken together, form a single block of numbered 2.3 GHz lots.
(5) Where there is more than one valid combination of 2.3 GHz assignment stage bids for which the total value is equal highest, OFCOM shall employ a method of random selection from amongst those valid combinations of 2.3 GHz assignment stage bids for which the value is equal highest to determine the winning combination of valid 2.3 GHz assignment stage bids.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: