Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Work No. 1 — Works to construct an integrated energy park—
(a)Work No. 1A — an energy recovery facility with a capacity to process up to 805,920 tonnes of waste per calendar year including—
(i)fuel reception and storage facilities consisting of a tipping hall and vehicle ramp(s), shredder, solid fuel storage bunker, cranes and handling equipment;
(ii)waste processing lines, each line including a feed hopper, ram feed, air cooled moving grates, a boiler and steam systems, combustion air systems and flue gas treatment facilities including residue and reagent storage silos and tanks;
(iii)associated induced fans and emissions control monitoring systems;
(iv)up to two emission stacks;
(v)a steam turbine incorporating at least 30 megawatts heat off–take for district heating and electrical generator (if not constructed and installed as part of Work No. 2);
(vi)an integrated protection system and uninterruptable power supplies; and
(vii)bottom ash conveyors, including storage bunker, crane and ash collection bay.
(b)[F1Work No. 1B]— an anaerobic digestion system with a capacity to process up to 40,000 tonnes of waste per calendar year including—
(i)fuel reception and storage facilities as constructed for Work No. 1A;
(ii)conveyor and feed system;
(iii)anaerobic digestor, dryers and integrated heating system;
(iv)solid digestate treatment equipment, handling and storage;
(v)ventilation and air collection system;
(vi)emission stack;
(vii)gas flare;
(viii)combined heat and power plant, including combined heat and power engine;
(ix)an electrical switchyard, including switchgear and transformer;
(x)gas storage and upgrading equipment; and
(xi)associated gas and process heat pipes.
(c)Work No. 1C — solar photovoltaic panels on all or part of Work No. 1E and, should a steam turbine building be constructed as part of Work No. 2, on all or part of the steam turbine building forming part of Work No. 2, switchgear, inverters, transformers and permanent equipment for maintenance.
(d)Work No. 1D — a battery storage facility including—
(i)battery energy storage cells;
(ii)transformers;
(iii)protection cabinets; and
(iv)switch gear and ancillary equipment.
(e)Work No. 1E — a building with roof enclosing and/or supporting all or part of Work Nos. 1A, 1B, 1C and 1D.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: