There are currently no known outstanding effects for the The Nuclear Regulated Asset Base Model (Revenue Collection) Regulations 2023, PART 1.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.—(1) These Regulations may be cited as the Nuclear Regulated Asset Base Model (Revenue Collection) Regulations 2023.
(2) These Regulations come into force 21 days after the day on which they are made.
(3) These Regulations extend to England and Wales and Scotland.
Commencement Information
I1Reg. 1 in force at 23.3.2023, see reg. 1(2)
2.—(1) In these Regulations—
“the Act” means the Nuclear Energy (Financing) Act 2022;
“absolute value”, in relation to an amount, means the magnitude of that amount without regard to whether that amount is positive or negative;
“additional reserve payment” means a payment an electricity supplier is required to make under regulation 13(3);
“adjusted interim levy rate” is to be construed in accordance with regulation 12(1);
“the Balancing and Settlement Code” means the code for the governance of electricity balancing and settlement in Great Britain, as amended from time to time, which is maintained in accordance with the conditions of transmission licences granted under section 6(1)(b) of the Electricity Act 1989(1);
“BM Unit” has the meaning given in the Balancing and Settlement Code (see section X of that code) and “registered”, in relation to a BM Unit, means registered in accordance with the requirements of section K of the Balancing and Settlement Code;
“BSC volume allocation run” means any one of the following—
an Initial Volume Allocation Run,
an Interim Information Volume Allocation Run,
a Reconciliation Volume Allocation Run (including a Final Reconciliation Volume Allocation Run or a Post-Final Volume Allocation Run);
“the BSCCo” means ELEXON Limited (company number 03782949) or any successor to that company acting in the capacity of the BSCCo within the meaning given in the Balancing and Settlement Code;
“EII excluded electricity” means electricity which constitutes EII excluded electricity within the meaning of regulation 6(1) of the Electricity Supplier Obligations (Amendment & Excluded Electricity) Regulations 2015(2);
“electricity generation licence” has the meaning given in section 1(5) of the Act;
“electricity supplier” means a person who is the holder of a licence to supply electricity under section 6(1)(d) of the Electricity Act 1989;
“estimated quarterly obligation period electricity supply”, “estimated quarterly obligation period income”, and “estimated quarterly obligation period payment cost” are to be construed in accordance with regulation 6;
“final reconciliation determination” is to be construed in accordance with regulation 15(2);
“Final Reconciliation Volume Allocation Run” has the meaning given in the Balancing and Settlement Code (see section U of that code);
“first operational cost period” means the period—
beginning with the first payment period start date; and
ending with—
except where paragraph (ii) applies, the earliest 31st March to occur after the first payment period start date; or
if the first payment period start date occurs on a 31st March, the first payment period start date;
“first payment period start date” means the date of entry into the first revenue collection contract by the revenue collection counterparty;
“first payment period end date” means the earlier of 31st March, 30th June, 30th September or 31st December following the first payment period start date;
“Initial Volume Allocation Run” has the meaning given in the Balancing and Settlement Code (see section U of that code);
“Interim Information Volume Allocation Run” has the meaning given in the Balancing and Settlement Code (see section U of that code);
“interim rate payment” is to be construed in accordance with regulation 7;
“letter of credit” means a letter from a person which contains an irrevocable and unconditional authorisation in favour of the revenue collection counterparty to be paid by that person on demand up to an amount stated in the letter;
“mutualisation amount” and “mutualisation notice” are to be construed in accordance with regulation 17;
“operational cost period” means—
the first operational cost period, or
any subsequent period beginning with 1st April in a year and ending with 31st March in the following year;
“Post-Final Volume Allocation Run” has the meaning given in the Balancing and Settlement Code (see section U of that code);
“quarterly obligation period” means—
in respect of the first such period, the period from the first payment period start date to the first payment period end date; and
for any other such period, a period of 3 months commencing with 1st April, 1st July, 1st October or 1st January (as applicable);
“RCC party” means a person, other than the revenue collection counterparty, who is a party to a revenue collection contract;
“RCC party payment” means any payment which an RCC party must make to the revenue collection counterparty under, or pursuant to, a revenue collection contract, and includes a payment made to a person to whom a benefit under, or pursuant to, a revenue collection contract has been assigned in accordance with the terms of that revenue collection contract;
“RCC period contribution” is to be construed in accordance with regulation 3;
“reconciliation determination” and “reconciliation period” are to be construed in accordance with regulation 15(1);
“reconciliation payment” means a payment an electricity supplier or the revenue collection counterparty is required to make under regulation 16(4);
“Reconciliation Volume Allocation Run” has the meaning given in the Balancing and Settlement Code (see section U of that code);
“reduced reserve payment” is to be construed in accordance with regulation 14(4)(b);
“relevant licence”, in relation to a particular RCC party, means that RCC party’s electricity generation licence;
“reserve payment” means a payment an electricity supplier is required to make under regulation 10(1);
“reserve period” means a period beginning with the 13th working day of a quarterly obligation period and ending with the 13th working day of the subsequent quarterly obligation period;
“revenue collection contract” has the meaning given in section 14(1) of the Act;
“revenue collection counterparty” has the meaning given in section 14(1) of the Act;
“revenue collection counterparty payment” means any payment which the revenue collection counterparty must make—
under or pursuant to a revenue collection contract;
to an RCC party for the purpose of compensating that person in respect of any breach of any duty (however that duty arises) owed to that person by the revenue collection counterparty which is connected to a revenue collection contract;
and includes any payment made to a person to whom a benefit under (or pursuant to) a revenue collection contract has been assigned in accordance with the terms of that revenue collection contract;
“SoS funds” means any financial assistance (within the meaning of section 41(4) of the Act) provided by the Secretary of State to the revenue collection counterparty for the purposes of making revenue collection counterparty payments and adjusting payments due from electricity suppliers in accordance with these Regulations;
“supplier” means an electricity supplier;
“total reserve amount” is to be construed in accordance with regulation 9(1)(a);
“working day” means a day other than a Saturday, a Sunday, Christmas Day, Good Friday or a bank holiday under the Banking and Financial Dealings Act 1971(3) in England, Wales or Scotland.
(2) Any reference in these Regulations to an amount of electricity is a reference to that amount expressed in megawatt hours.
(3) Any reference in these Regulations to a supply of electricity is a reference to its supply in Great Britain, and “supply” is to be construed in accordance with section 4(4) of the Electricity Act 1989(4).
(4) Any reference in these Regulations to an amount to be paid or provided is a reference to that amount expressed in pounds sterling and rounded to the nearest whole penny with any half of a penny being rounded upwards.
(5) Where more than one person is designated under section 16 of the Act as a revenue collection counterparty, these Regulations apply subject to the modifications set out in the Schedule.
Commencement Information
I2Reg. 2 in force at 23.3.2023, see reg. 1(2)
1989 c. 29. Section 6 was substituted by the Utilities Act 2000 (c. 27), section 30. Section 6(1)(b) was substituted by the Energy Act 2004 (c. 20), section 136(1).
S.I. 2015/721. Relevant amending instruments are S.I. 2020/130.
1971 c. 80; see section 1 and Schedule 1 (which was amended by section 1 of the St Andrew’s Day Bank Holiday (Scotland) Act 2007 (2007 asp 2)).
The definition of “supply” in section 4(4) was substituted by the Energy Act 2004 (c. 20), section 179(1).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: