Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
4.—(1) The RCC period contribution for a supplier for a quarterly obligation period is the amount given by—
where—
GP is the total amount of revenue collection counterparty payments which the revenue collection counterparty was required to make in the quarterly obligation period;
SoS repayment is—
unless sub-paragraph (b) or (c) applies, the SoS payment in respect of the quarterly obligation period that ended three whole quarterly obligation periods before the quarterly obligation period for which this calculation is made (a “full SoS repayment”);
unless paragraph (c) applies and if the Secretary of State has specified that only a proportion of the full SoS repayment is to be used for the purposes of this paragraph, that amount;
where the contribution is for any of first four quarterly obligation periods, zero;
CP is the total amount of RCC party payments which the revenue collection counterparty received from RCC parties in the quarterly obligation period;
SoS payment is the total amount of any SoS funds that the Secretary of State has specified are to be used when calculating the RCC period contribution in respect of the quarterly obligation period;
DI is any amount of interest which was paid by virtue of regulation 7(6), 8(7), 10(2), 13(7), 16(5) or 17(7) during that period, less any amount of that interest which was paid to electricity suppliers by virtue of regulation 18(2);
SQS is the amount of electricity supplied by that supplier in the quarterly obligation period;
XEP is the amount of EII excluded electricity supplied by that supplier in the quarterly obligation period;
TQS is the total amount of electricity supplied by all suppliers in the quarterly obligation period; and
AXP is the total amount of EII excluded electricity supplied by all suppliers in the quarterly obligation period.
(2) For the purposes of this regulation, the amount of electricity supplied by a supplier in a quarterly obligation period is the amount of electricity which the BSCCo determines was supplied by that supplier on the basis of—
(a)Final Reconciliation Volume Allocation Runs for each day within the quarterly obligation period; or
(b)where a Post-Final Volume Allocation Run has occurred in relation to a day on which electricity was supplied, the Post-Final Volume Allocation Run for that day.
(3) Where the revenue collection counterparty makes a determination under these Regulations which requires the determination of the amount of electricity supplied on a day which is EII excluded electricity, it must, where possible, base that determination of EII excluded electricity on information derived from the most recent BSC volume allocation run carried out by the BSCCo in relation to the day on which the electricity was supplied.
Commencement Information
I1Reg. 4 in force at 23.3.2023, see reg. 1(2)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: