Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
28. Subject to paragraph (3)—
(a)the “base discount” in respect of a supply contract for any period (“P”) is calculated as follows—
(b)the “increased discount” in respect of an ETII supply contract for P is calculated as follows—
Where—
RWP is the reference wholesale price applicable to that supply contract for P, subject to paragraph (4);
GSP is the government supported price applicable to that supply contract;
GSPD is the GSP decrement.
(2) The Secretary of State must determine the base discounts and (for ETII supply contracts) increased discounts for fixed price contracts, variable price contracts and DAI price contracts, and publish them with the corresponding reference wholesale prices.
(3) Where regulation 58 applies, the base discount is reduced and (for an ETII supply contract) the increased discount is reduced in accordance with that regulation.
(4) Where paragraph (1) of regulation 49 applies, the reference wholesale price is determined under sub-paragraph (c) of that paragraph.
Commencement Information
I1Reg. 28 in force at 26.4.2023, see reg. 1(1)
29.—(1) For the purposes of these Regulations, “the discount” means the reduction (in p/kWh) in the supply price under a supply contract to be applied pursuant to the scheme in respect of that contract for any period.
(2) In the case of a general supply contract or a QHS supply contract, the discount is calculated as follows—
Where—
BD is the base discount in respect of that supply contract for the period;
MD is the maximum discount applicable to that supply contract;
SP is the supply price for the period;
MP is the minimum supply price applicable to that supply contract.
(3) In the case of an ETII supply contract the discount is calculated as follows—
Where—
BD is the base discount in respect of that supply contract for the period;
MD is the maximum discount applicable to that supply contract);
SP is the supply price for the period;
MP is the minimum supply price applicable to that supply contract;
ID is the increased discount in respect of that supply contract for the period;
IMD is the maximum discount applicable to an ETII supply contract plus the MD increment;
RMP is the minimum supply price applicable to an ETII supply contract less the GSP decrement.
Commencement Information
I2Reg. 29 in force at 26.4.2023, see reg. 1(1)
30.—(1) A supplier must, in respect of each supply contract—
(a)determine the base discount, increased discount (in the case of an ETII supply contract) and the discount for any period;
(b)reduce the supply price by the discount;
(c)reduce the amount charged to the customer in respect of supply in any billing period by an amount calculated as the billed supply quantity multiplied by the discount;
(d)for each billing period, inform the customer in its invoice or other statement of account, or in a separate communication given within the period of 15 days beginning on the date that it issued its invoice or other statement of account, in respect of that billing period, of—
(i)the amount of the discount;
(ii)the discounted supply price;
(iii)the amount by which its charges for supply in the billing period have been reduced by applying the discount, or the basis on which that amount can be determined.
(2) In relation to a flexible price contract the information provided by the supplier under paragraph (1)(d) must include an explanation of how the reference wholesale price for the relevant billing period has been calculated.
(3) Where a supplier adjusts its charges to a customer in consequence of energy reconciliation in respect of any period, the adjustment must be made on the basis of the discounted supply price applicable to such period.
(4) In respect of the period from the scheme start date to the scheme introduction date, a supplier must, no later than 45 days after the scheme introduction date—
(a)determine the amount by which its charges to a customer for energy supplied in that period are to be reduced by the application of the discount;
(b)where it has issued an invoice or statement of account to the customer in respect of any such charges, revise such invoice or statement or issue a credit note to reflect such reduction in charges;
(c)where the customer has paid any amount in respect of such charges, credit to the customer’s account the amount by which such payment exceeds what was payable on the basis of the discounted supply price, or at the customer’s request reimburse such amount to the customer.
(5) A supplier must ensure that—
(a)the amounts which are the subject of arrangements it makes with, or requirements it imposes, on any customer in connection with the payment (or assurance of payment) or collection of charges under a supply contract, are amounts calculated by reference to the discounted supply price;
(b)where a customer takes its supply through a prepayment meter, the prepayment meter is set or reset, or other arrangements are made, as soon as reasonably practicable after the scheme introduction date, and thereafter whenever required, to ensure that the amounts paid by the customer over each scheme period reflect charges at the discounted supply price for supply in the scheme period.
(6) Arrangements and requirements referred to in paragraph (5)(a) include (without limitation) arrangements or requirements for advance payment, payment by direct debit, payment by instalments, security or credit cover for payment.
Commencement Information
I3Reg. 30 in force at 26.4.2023, see reg. 1(1)
31. Where the categorisation of a supply contract under regulation 11 is revised, either by agreement of the contract parties or by determination of the Secretary of State under these Regulations, the supplier must—
(a)redetermine the amount of any charges for energy supplied under the contract prior to the date of such revision on the basis of the discounted supply price applicable to the contract as re-categorised,
(b)determine the amount by which any such charges already included in any invoice or statement of account are to be revised to reflect such redetermination,
(c)notify the customer of its determinations under paragraphs (a) and (b), and
(d)take the necessary steps to ensure the amount in paragraph (b) is credited or debited to the customer by way of credit note, or adjustment of an existing invoice or statement of account, or inclusion in a future invoice or statement of account.
Commencement Information
I4Reg. 31 in force at 26.4.2023, see reg. 1(1)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: