There are currently no known outstanding effects for the The Town and Country Planning (Environmental Impact Assessment) (Undetermined Reviews of Old Mineral Permissions) (Wales) Regulations 2009, Cross Heading: Site notice publicity to be undertaken by applicants, appellants and operators.
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
(8) This paragraph applies to any applicant or appellant to whom a copy of a screening direction is sent pursuant to regulation 9(2)(a), 9(4)(b) or 11(12)(a), or to whom written notification is given pursuant to any provision mentioned in paragraph (4) or (7).
(9) An applicant or appellant to whom paragraph (8) applies must, unless the applicant or appellant has not, and was not reasonably able to acquire, such rights as would enable the applicant or appellant to do so, post on the land a copy of–
(a)any screening direction mentioned in that paragraph;
(b)any written notification given to the applicant or appellant pursuant to any provision mentioned in paragraph (4) or (7);
within 14 days of the date on which such notification is given.
(10) Where a copy of a written notification posted on the land in accordance with paragraph (9)(b) is of the kind mentioned in paragraph (4)(j) or (m), or paragraph (7)(j), (m) or (p), the copy of that notification which is posted on the land must be accompanied by a notice stating an address in the locality in which the land is situated, at which a copy of the associated scoping opinion or direction can be inspected at all reasonable hours.
(11) This paragraph applies to any operator to whom written notification is given under or pursuant to–
(a)regulation 11(3);
(b)regulation 12(2);
(c)regulation 13(4);
(d)regulation 14(5);
(e)regulation 15(5);
(f)regulation 18(6);
(g)regulation 26(1);
(h)regulation 27(2);
(i)regulation 28(5);
(j)regulation 28(8).
(12) An operator to which paragraph (11) applies must, unless the operator has not, and was not reasonably able to acquire, such rights as would enable the operator to do so, post on the land a copy of any such written notification as is referred to in that paragraph within 14 days of the date on which the notification is given.
(13) A copy of a direction or written notification posted on the land in accordance with paragraph (9), and any notification posted on the land in accordance with paragraph (10) or (12), must—
(a)be left in position for not less than fourteen days; and
(b)be affixed firmly to some object on the land and sited and displayed in such a way as to be easily visible to, and readable by, members of the public without going on to the land.
47.—(1) Section 69 (register of applications, etc.), and any provisions of the Order made by virtue of that section, has effect with any necessary amendments as if references to applications for planning permission included undetermined ROMP applications under paragraph 9(1) of Schedule 13 to the 1995 Act and paragraph 6(1) of Schedule 14 to the 1995 Act.
(2) Where the relevant mineral planning authority is not the authority required to keep the register, the relevant mineral planning authority must provide the authority required to keep it with such information and documents as that authority requires to comply with–
(a)section 69 as applied by paragraph (1); and
(b)regulation 48.
48.—(1) Where particulars of an undetermined ROMP application are placed on Part I of the register, the relevant mineral planning authority must take steps to secure that there is also placed on that Part an information of the following kind which relates to the undetermined ROMP application in question—
(a)any screening direction;
(b)any scoping opinion;
(c)any scoping direction;
(d)any written notification referred to in regulation 46(4) or (7);
(e)any environmental statement which is the subject of written notification given under regulation 18(21);
(f)any further information or evidence which is the subject of a written notification given under regulation 28(8);
(g)any other relevant information published in accordance with regulation 37;
(h)any statement of reasons accompanying any of the above;
(i)particulars of any suspension of minerals development;
(j)the date (if any) on which any suspension of minerals development ended;
(k)particulars of any order made under Schedule 9 to the Act pursuant to regulation 51.
49.—(1) Where an EIA application is determined by a relevant mineral planning authority, the authority must—
(a)in writing, inform the Welsh Ministers and the consultation bodies of the decision;
(b)inform the public of the decision, by local advertisement, or by such other means as are reasonable in the circumstances; and
(c)make available for public inspection at the place where the appropriate register (or relevant section of that register) is kept a statement containing—
(i)the content of the decision and any conditions attached thereto;
(ii)the main reasons and considerations on which the decision is based including, if relevant, information about the participation of the public;
(iii)a description, where necessary, of the main measures to avoid, reduce and, if possible, offset the major adverse effects of the development; and
(iv)information regarding the right to challenge the validity of the decision and the procedures for doing so.
(2) Where an EIA application is determined by the Welsh Ministers the Welsh Ministers must—
(a)notify the relevant mineral planning authority and the consultation bodies of the decision; and
(b)provide the authority with such a statement as is mentioned in paragraph (1)(c).
(3) The relevant mineral planning authority must, as soon as reasonably practicable following receipt of a notification given under paragraph (2), comply with sub-paragraphs (b) and (c) of paragraph (1) in relation to the decision so notified as if it were a decision of the authority.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: