Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART 3E+WConsent

Requirement for consentE+W

8.  The consent of the Welsh Ministers must be obtained before a person commences or carries out a significant project.

Commencement Information

I1Reg. 8 in force at 16.5.2017, see reg. 1(3)

Scoping opinionsE+W

9.—(1) After receiving a screening decision that a project is a significant project, but before applying for consent, the applicant may ask the Welsh Ministers to provide their opinion on what information must be included in an environmental statement (“a scoping opinion”).

(2) If the applicant requests a scoping opinion, the Welsh Ministers must consult the applicant and such of the consultation bodies as they think fit before providing their opinion.

(3) If the Welsh Ministers consider that they do not have sufficient information to provide a scoping opinion, they may ask the applicant to supply any additional information they require within 28 days of the date on which the Welsh Ministers receive the request for the scoping opinion.

(4) The Welsh Ministers must provide the applicant with the scoping opinion within five weeks of—

(a)the date they received the scoping opinion; or

(b)where applicable, the date they received the additional information under paragraph (3).

Commencement Information

I2Reg. 9 in force at 16.5.2017, see reg. 1(3)

Provision of informationE+W

10.—(1) This regulation applies if a consultation body—

(a)is consulted by the Welsh Ministers under regulation 9(2); or

(b)receives a request for information from a person who intends to apply for consent.

(2) Where this regulation applies, the consultation body must—

(a)determine whether it has in its possession any information it considers relevant to the preparation of the environmental statement; and

(b)subject to paragraphs (3) and (4), make that information available to the Welsh Ministers or the applicant within 28 days from the date of the consultation or the request, whichever is the earliest.

(3) A consultation body may make a reasonable charge to the applicant for providing information under paragraph (2)(b), to reflect the cost of making the relevant information available.

(4) Paragraph (2)(b) does not require a consultation body to make available to the applicant any information which—

(a)it may refuse to disclose under regulation 12(1) of the Environmental Information Regulations 2004(1); or

(b)it is prevented from disclosing by regulation 13(1) of those Regulations.

(5) If a consultation body is not a public authority within the meaning of regulation 2(2) of the Environmental Information Regulations 2004, paragraph (4) applies as if it were such a public authority.

Commencement Information

I3Reg. 10 in force at 16.5.2017, see reg. 1(3)

The consent application and environmental statementE+W

11.—(1) An application for consent must—

(a)include an environmental statement; and

(b)be made to the Welsh Ministers.

(2) An environmental statement is a statement which includes at least—

(a)a description of the project comprising information on the site, design, size and other relevant features of the project;

(b)a description of the likely significant effects of the project on the environment;

(c)a description of features of the project and/or measures envisaged in order to avoid, prevent or reduce and, if possible, offset likely significant adverse effects on the environment;

(d)a description of the reasonable alternatives studied by the applicant, which are relevant to the project and its specific characteristics, and an indication of the main reasons for the option chosen, taking into account the significant effects of the project on the environment;

(e)a non-technical summary of the information referred to in sub-paragraphs (a) to (d); and

(f)any additional information specified in Schedule 3 relevant to the specific characteristics of the particular project or type of project and to the environmental features likely to be significantly affected.

(3) The environmental statement must—

(a)be prepared on behalf of the applicant by persons who, in the opinion of the Welsh Ministers, have sufficient expertise to ensure the completeness and quality of the statement;

(b)contain a statement by or on behalf of the applicant or appellant describing the expertise of the person who prepared the environmental statement;

(c)where a scoping opinion has been issued in accordance with regulation 9, be based on the most recent scoping opinion issued (so far as the project remains materially the same as the project which was the subject of that opinion);

(d)include the information reasonably required for reaching a reasoned conclusion on the significant effects of the project on the environment, taking into account current knowledge and methods of assessment; and

(e)take into account the available results of other relevant environmental assessments required under [F1retained EU law] or any other provision of domestic legislation, with a view to avoiding duplication of assessment.

(4) After receiving the application for consent, the Welsh Ministers must—

(a)send a copy of the application to any of the consultation bodies they consider appropriate and inform them that they may make representations within 6 weeks of the date on which they receive the application; and

(b)publish in a newspaper circulating in the locality of the relevant land and on the Welsh Government website, a notice—

(i)stating that the application has been made;

(ii)specifying an address at which copies of the application can be inspected free of charge and where copies of the application may be taken (for which a reasonable charge may be made), at all reasonable hours for 6 weeks from the date on which the notice is published;

(iii)stating that representations on the likely environmental effects of the project may be made in writing to the Welsh Ministers at the address specified under paragraph (ii) for a period of 6 weeks beginning with the date on which the notice is published;

(iv)stating that, if consent is granted, it will be subject to the conditions in regulation 17(2) and any other conditions that the Welsh Ministers think fit; and

(v)stating, where relevant, which of the EEA States, the public concerned in the EEA State, and the consultation bodies will be consulted on the application.

Additional informationE+W

12.—(1) If, after complying with regulation 11(4), the Welsh Ministers decide that a statement included with an application for consent, which purports to be an environmental statement, should contain additional information in order to be an environmental statement, the Welsh Ministers must notify the applicant of the additional information required and the applicant must provide the Welsh Ministers with that information within 28 days of being so notified (“additional environmental information”).

(2) The Welsh Ministers must—

(a)send a copy of the additional environmental information to such of the consultation bodies as they consider appropriate, and

(b)inform the consultation bodies that they may make representations within 28 days of the date they receive the additional information.

(3) The Welsh Ministers must publish in a newspaper circulating in the locality of the relevant land and on the Welsh Government website, a notice—

(a)referring to the application to which the additional environmental information relates and the date on which the application was made;

(b)stating that the additional environmental information has been received;

(c)specifying an address at which copies of the additional environmental information can be inspected free of charge and where copies of the application may be taken (for which a reasonable charge may be made) at all reasonable hours for 28 days from the date on which the notice is published; and

(d)stating that representations in relation to the additional environmental information may be made in writing to the Welsh Ministers at the address specified under sub-paragraph (c) for a period of 28 days beginning with the date on which the notice was published.

Commencement Information

I5Reg. 12 in force at 16.5.2017, see reg. 1(3)

Procedure where a significant project in Wales may affect [F2an] EEA StateE+W

13.—(1) As soon as possible after receiving an application for consent for a significant project, the Welsh Ministers must consider whether that project is also likely to have significant effects on the environment in [F3an] EEA State.

(2) If the Welsh Ministers consider that a project is likely to have significant effects in accordance with paragraph (1), or an EEA State likely to be significantly affected requests, the Welsh Ministers must send to that EEA State—

(a)details of the nature and location of the significant project;

(b)any information the Welsh Ministers have on the impact the project is likely to have on that EEA State;

(c)an indication of whether the Welsh Ministers are minded to grant consent for the project and the likely conditions attached to the consent; and

(d)a request that the EEA State indicate, within a reasonable timeframe set by the Welsh Ministers, whether it wishes to participate in the procedure under these Regulations.

(3) If an EEA State indicates that it wishes to participate in the procedure under these Regulations, the Welsh Ministers must provide that EEA State with—

(a)a copy of the application for consent, the environmental statement and any further information they consider relevant to the application; and

(b)information on the procedure under these Regulations.

(4) F4... The Welsh Ministers must—

(a)arrange for the documents and information in paragraphs (2) and (3) to be made available to the authorities [F5which the EEA State has designated to be consulted about the project] and the public concerned in the territory of the EEA State; and

(b)ensure that those authorities and the public concerned are given an opportunity to provide the Welsh Ministers with their opinion on the information and documents supplied, within a reasonable time prior to a decision for consent being taken.

(5) F6... The Welsh Ministers must—

(a)enter into consultations with the EEA State concerned about, amongst other things, the potential significant effects of the project on the environment of that State and the measures envisaged to reduce or eliminate those effects; and

(b)seek to agree with the EEA State concerned, a reasonable timeframe for those consultations, which must include time for consideration of any opinions received under paragraph (4)(b).

Procedure where a significant project in [F7an] EEA State may affect WalesE+W

14.—(1) If the Welsh Ministers receive information from [F8an] EEA State made available F9... in relation to a significant project in that EEA State, prior to a decision on consent being made, the Welsh Ministers must—

(a)make that information available, within a reasonable time, to the consultation bodies and members of the public which are likely to be concerned by the project;

(b)provide the consultation bodies and members of the public referred to in sub-paragraph (a) with the opportunity to submit their opinion on the information provided within the period agreed under paragraph (2)(b).

(2) F10... The Welsh Ministers must—

(a)enter into a consultation, together with the EEA State concerned, regarding the potential significant effects of the project on the environment in Wales and the measures envisaged to reduce or eliminate those effects; and

(b)seek to agree with the EEA State a reasonable period, before a consent decision is made, during which opinions under paragraph (1)(b) can be forwarded to that EEA State.

(3) If [F11an] EEA State has taken a decision to grant or refuse consent and has informed the Welsh Ministers of that decision, the Welsh Ministers must bring the information received from the EEA State in relation to that decision to the attention of the public.

The consent decisionE+W

15.—(1) When deciding whether to grant consent for a significant project, the Welsh Ministers must consider—

(a)the environmental statement;

(b)any additional environmental information;

(c)any representations they receive under—

(i)regulation 11(4)(a);

(ii)regulation 12(2)(b) and (3)(d); or

(iii)regulation 13(4)(b); and

(d)any social or economic impacts which might result from a decision to refuse consent for the project.

(2) The Welsh Ministers must not reach their decision under paragraph (1) until the latest of—

(a)the expiry of the period in the notice under regulation 11(4)(b)(iii);

(b)the expiry of the period of 28 days after the date on which any additional environmental information was sent to the consultation bodies in accordance with regulation 12(2)(b);

(c)the expiry of the period of 28 days after the date the notice under regulation 12(3) was published; and

(d)the expiry of any period agreed with [F12an] EEA State under regulation 13(5)(b),

whichever is the last to occur.

Additional requirements relating to the Habitats RegulationsE+W

16.—(1) The Welsh Ministers must not grant consent for a project which would be unlawful under [F13regulations 43, 45 or 47] of the Habitats Regulations.

(2) But that does not include anything for which a licence has been granted under [F14regulation 55] of the Habitats Regulations.

(3) Paragraphs (4) to (7) apply when the Welsh Ministers are deciding whether to grant consent for a project which is likely to have a significant effect on a European site, whether alone or in combination with another project (referred to in those paragraphs as “the project”).

(4) The Welsh Ministers may only grant consent for a project if they have considered the implications of the project for the European site (including an appropriate assessment of the implications in the view of that site’s conservation objectives) and are satisfied that the project will not adversely affect the integrity of the site, unless paragraph (5) applies.

(5) If the Welsh Ministers are satisfied that the project must be carried out for imperative reasons of overriding public interest (which may be of a social or economic nature, subject to paragraph (6)) and that there is no alternative solution, they may grant consent for the project even though the assessment of its implications for a European site is negative.

(6) If the European site hosts a priority natural habitat type or a priority species, the reasons in paragraph (5) must be either—

(a)reasons relating to human health, public safety or beneficial consequences or primary importance to the environment, or

(b)other reasons which in the opinion of [F15the Welsh Ministers] are, in the case of the site concerned, imperative reasons of overriding public interest.

[F16(6A) Before deciding whether the reasons are imperative reasons of overriding public interest, the Welsh Ministers must—

(a)consult—

(i)the Joint Nature Conservation Committee;

(ii)the Secretary of State and the other devolved administrations;

(iii)any other person they consider appropriate; and

(b)have regard to the national interest.]

(7) If the Welsh Ministers decide to grant consent for a project in accordance with paragraph (5), they must secure any necessary compensatory measures are taken to ensure that the overall coherence of Natura 2000(2) is protected.

Conditions of consentE+W

17.—(1) Consent granted in accordance with regulation 15 will be subject to—

(a)the conditions in paragraph (2); and

(b)any other conditions the Welsh Ministers consider appropriate.

(2) The conditions required by paragraph (1)(a) are—

(a)the consent lapses if the project not been commenced within 1 year of the date on which the consent was granted;

(b)the consent expires if the project is not completed within 3 years of the date on which the consent was granted; and

(c)the consent only authorises the project described in the consent application, subject to any amendments approved by the Welsh Ministers in accordance with paragraph (4).

(3) After the expiry of a consent in accordance with paragraph (2)(b), the Welsh Ministers may require a further application for consent in accordance with paragraph (5) in respect of any further operations or uses forming part of the project.

(4) The Welsh Ministers may approve any amendments to the consent at the request of an applicant, but any material change in the authorised operations or uses requires a further application for consent in accordance with paragraph (5).

(5) Further applications for consent under paragraphs (3) and (4) may be subject to any requirement of these Regulations that the Welsh Ministers consider appropriate.

(6) In this regulation, a project has been—

“commenced” (“dechrau”) when a material act has been carried out in respect of any of the works permitted by the consent; and

“completed” (“wedi ei gwblhau”) when all works permitted by the consent have been carried out and all changes in use, or the level of use, of the relevant land have been implemented.

Commencement Information

I10Reg. 17 in force at 16.5.2017, see reg. 1(3)

Procedure following a consent decisionE+W

18.  After the Welsh Ministers have made a consent decision in respect of a project, they must—

(a)notify the applicant, any consultation body to whom copies of the consent application were sent under regulation 11(4)(a), any EEA State notified under regulation 13(2) and any authority or person who submitted an opinion under regulation 13(4)(b), of—

(i)their decision;

(ii)the reasons for the decision;

(iii)any representations made by the public;

(b)publish a notice in a newspaper in the locality where the relevant land is situated or by any other means they consider reasonable in the circumstances; and

(c)make a statement available for public inspection that contains—

(i)the decision;

(ii)the reasons for the decision;

(iii)a description of the principal measures that must be taken to avoid, reduce or offset any major adverse effects of the project;

(iv)a summary of any representations made by the public; and

(v)information regarding the right to challenge the decision and procedures for doing so.

Commencement Information

I11Reg. 18 in force at 16.5.2017, see reg. 1(3)

Transborder projectsE+W

19.—(1) In the case of a transborder project where the greater part of the relevant land is situated in Wales, the Welsh Ministers must consult the Secretary of State before—

(a)making a screening decision under regulation 7;

(b)providing a scoping opinion under regulation 9; or

(c)granting or refusing consent under regulation 15.

(2) In the case of a transborder project where the greater part of the relevant land is situated in England, that project will be subject solely to the Regulations applicable to the project in England, except where an agreement to the contrary has been reached under paragraph (4).

(3) In the case of an application in respect of a transborder project to which these Regulations would otherwise apply, if so requested by the Secretary of State, the Welsh Ministers may agree that the application should be subject solely to the Regulations applicable to the project in England.

(4) If the Welsh Ministers so request, and the Secretary of State agrees, a transborder project to which paragraph (2) would otherwise apply will be subject solely to these Regulations.

Commencement Information

I12Reg. 19 in force at 16.5.2017, see reg. 1(3)

Review of decisions and consentsE+W

20.  Schedule 4 applies if, after the date of—

(a)a decision that a project is not a significant project, or

(b)a decision to grant consent for a project,

the relevant land becomes a European site and the Welsh Ministers consider that the carrying out or completion (within the meaning of “completed” in regulation 17(6)) of the project would be likely to have a significant effect on that site and would not be directly connected with or necessary for the management of the site.

Commencement Information

I13Reg. 20 in force at 16.5.2017, see reg. 1(3)

(2)

See regulation 3(1) of the Habitats Regulations for the definition of “Natura 2000”.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.

Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources